Lively Heels Phase 3-23

Boat:

Lively Heels, a 1976 Fisher 30

Schedule:

Project Schedule:  November 2020 – April 2021

Project Scope:  Reconfigure and simplify engine-based heating system; install woodstove for cabin heating; remove sanitation treatment system and replace with holding tank, conceive and build deck storage boxes; miscellaneous and sundry small projects

Project Complete:  145.75 Total Hours

Begin Daily Project Logs

February 19, 2021

Lively Heels Phase 3-23

Friday

In a short work session, I lightly sanded the new fiberglass on the cockpit box and, after cleanup, applied the first of a few rounds of epoxy fairing compound over the sides.

Total time billed on this job today:  .5 hours

0600 Weather Observation:  21°, cloudy.  Forecast for the day:   Another anemic excuse for a snow event, cloudy with a chance of light snow and little accumulation, 29°