Jasmine 39

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 29, 2018

Jasmine 39

< Back to Jasmine

Monday

After final preparations, I applied three coats of Alexseal snow white gloss topcoat to the deck areas, working again in two separate phases:  first the remote areas of the coachroof (around the companionway and forward hatch) and the cockpit well; then, three coats on the remaining areas, including the cabin trunk, channels, coamings, and bulwarks, along with the loose hatches on the shop floor.

Total time billed on this job today:  5.75 hours

0600 Weather Observation:  26°, mostly clear.  Forecast for the day:  Sunny, high around 30° but then falling in the afternoon