Jasmine 35

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 23, 2018

Jasmine 35

< Back to Jasmine

Tuesday

Starting again with the inboard areas of the deck–the coachroof and cockpit well–I applied three coats of epoxy finish primer to the deck areas.  With the first phase complete, I continued with three coats on all other areas of the main decks, cockpit, cabin trunk, and loose parts.

Total time billed on this job today:  6 hours

0600 Weather Observation:  20°, light freezing mist, 1.5″ snow/sleet on the ground.  Forecast for the day:  Warming, freezing rain supposedly changing to rain later in the morning and through the afternoon, 30s.