December 19, 2017
Jasmine 13
Tuesday
To begin, I unloaded the sandbags from the newly-laid core on the sidedecks and elsewhere, exposing the new core.
I had other commitments away from the shop later in the day, so with only a limited amount of time I chose to focus on the new core installation at the poop deck. After final preparations, I installed the core in the same manner as the rest of the deck.
Total time billed on this job today: 1.75 hours
0600 Weather Observation: Clear, 20°, 4-5″ snow yesterday afternoon and overnight. Forecast for the day: Clouds and sun, near 40