Lyra Phase 2-55

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  December 2021 – April 2022

Project Scope: Deck paint (other than cockpit); hull paint; new dodger

Project Complete:  268.25 Total Hours

Begin Daily Project Logs

April 13, 2022

Lyra Phase 2-55

Wednesday

With departure originally scheduled for the day before, but postponed, I’d previously prepared the boat for travel, removing my temporary braces beneath the interior handrails, securing the lazarette hatch and companionway, and whatever else was needed.

Now, she headed back to her owner’s home so he could work on a few things to get her ready for the season ahead.

Back to Lyra

0600 Weather Observation: 0600 Weather Observation: 42°, mostly clear. Forecast for the day: Partly sunny, 59°.