Lyra Phase 2-52

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  December 2021 – April 2022

Project Scope: Deck paint (other than cockpit); hull paint; new dodger

Project Complete:  268.25 Total Hours

Begin Daily Project Logs

March 14, 2022

Lyra Phase 2-52

Monday

Jason was back to finish up the final dodger installation, having completed the final details over the weekend.

The last step for me, at least under current job scope, was to move the jack stands and finish painting beneath them, as well as painting over the three patched through hulls.

Total time billed on this job today:  1 hour

0600 Weather Observation:  19°, clear.  Forecast for the day:  Sunny, 44°