Lyra Phase 2-4

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  December 2021 – April 2022

Project Scope: Deck paint (other than cockpit); hull paint; new dodger

Project Complete:  268.25 Total Hours

Begin Daily Project Logs

December 29, 2021

Lyra Phase 2-4

Wednesday

Preparing for the imminent commencement of the real work on this project, I took advantage of a quiet afternoon to set up the staging all around at deck height.

Total time billed on this job today:  1 hour

0600 Weather Observation:  Partly cloudy, 26°.   Forecast for the day:  Sunny, 33°