Lyra Phase 2-36

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  December 2021 – April 2022

Project Scope: Deck paint (other than cockpit); hull paint; new dodger

Project Complete:  268.25 Total Hours

Begin Daily Project Logs

February 15, 2022

Lyra Phase 2-36

Tuesday

After final preparations, I applied three coats of glossy snow white LPU topcoat to the deck areas, beginning with three coats on the coachroof, specifically the companionway and vertical transition between the two sections of the coachroof; then on all the remaining deck areas, including the toerails and channels, cabin trunk, poop deck, and companionway sliding hatch.

Total time billed on this job today:  5.25 hours

0600 Weather Observation:  5°, fair.   Forecast for the day:  Increasing clouds, 22°