Lyra Phase 2-34

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  December 2021 – April 2022

Project Scope: Deck paint (other than cockpit); hull paint; new dodger

Project Complete:  268.25 Total Hours

Begin Daily Project Logs

February 11, 2022

Lyra Phase 2-34

Friday

With a couple days of prepwork ahead before I could spray the gloss topcoats on the deck and hull, I began with a comprehensive cleanup of boat and shop, including vacuuming, compressed air blowdown, rinsing off the staging and floor, and solvent-washing the hull and deck, all to remove dust and clean the surfaces sufficiently to allow me to continue work.

With what little time I had left on this day, I gathered various supplies to prepare for the deck masking ahead, and began by masking off the hull below the toerail with tape and plastic sheeting.

Total time billed on this job today:  3.5 hours

0600 Weather Observation:  27°, clear.   Forecast for the day:  Sunny, 43°