|                    
     |  | 
  
    
      | Progress Report:  2005 
      Archives |  
  
  
    | Reports from May 2005
 5/1/05 
5/8/05  5/15/05  
5/22/05  5/29/05
 |  
    | Log for the 
Week Ending May 1, 2005
 
 
  I 
spent most of Sunday working towards the clear goal of completing the bulk of 
the trim installation in the cabin, which I had started over the previous couple 
days.  With this focus, I managed to complete the installation, except for 
the v-berth ceiling (coming soon), and a few small trim pieces required to cover 
seams on the overhead; I did cut the bulk trim for this purpose, but wanted to 
apply several coats of varnish to the longer pieces before I began cutting it to 
fit in the spaces between the deck beams. 
Please click here for more about the 
trim. |  
    | 
  Monday, 
after my usual early week late s tart thanks to errands and administrative 
tasks, I set up the planer for more surface planing of the remaining wood in the 
shop--mahogany for the toerails, cypress for the v-berth ceiling, and some black 
walnut for accents and the tiller.  As usual, this devoured a hefty chunk 
of time.  At the end of it all, I realized that I would not have close to 
enough mahogany to finish the project, and would have to place yet another 
order.  This boat sure has used a lot of mahogany! |  
    | After some thought, I decided to turn my attention at last to the bottom of the 
boat--specifically the keel.  Much earlier in the process, during the 
unbuilding stage, I had removed all the bottom paint, but had not touched the 
area since.  Now, with the end of the project becoming ever near, I 
realized the time had come to deal with the keel (hey, I'm a poet and don't know 
it...).
 One reason driving my change in 
focus was that I needed to think about test-launching the boat in the relatively 
near future.  Why?  With no other means of determining where the boat 
would truly float--all the more so since Tritons, in general, seem to float in 
wide variety of locations, but almost never at the designed waterline--I needed 
the test launch so that I could accurately mark the waterline fore and aft, so 
that I could continue with striping and bottom-painting.  Before I could 
accomplish this test, however, I needed to address the keel repairs. |  
    | 
  I 
began by grinding off some Awlgrip and Alexseal test patches that I had sprayed 
willy-nilly on the bottom during several other projects earlier on, and also 
ground off some loose fiberglass and filler from some long-ago repair attempt.    
In particular, the seam between external ballast and fiberglass hull required 
attention, as did the foam-filled keel deadwood. 
Click here for more 
about the keel work. |  
    | 
  And 
so it continued throughout the week.  Honestly, I don't know where all the 
time went.  I spent a fair bit of time each day on the keel repairs, 
usually grinding yesterday's work in preparation for the next step of filling or 
fiberglassing.  By Thursday afternoon, the bulk of the glasswork was 
complete, with only final fairing still ahead. |  
    | With day upon day of rain, I took advantage of a clear afternoon here and there 
to take care of some other projects outside the shop--projects that required 
decent weather to complete, such as some mast work on 
Glissando, which I 
was preparing for launch in a few weeks;  I even took Saturday off to work 
on Glissando.
 |  
    | Log for the Week Ending May 8, 2005
 
 Sunday was silly.  Oh, things began innocently 
enough:  first thing, I sanded the latest application of fairing compound 
on the keel, so that I could apply another coat as needed.  This took about 
an hour and a half, including cleanup. 
 Click 
here for more on the keel work.
 |  
    | Then, I spent pretty much the rest of the day working on two boards for the 
ceiling trim in the v-berth, which became increasingly frustrating as time went 
by without, still, an acceptable fit.   The two pieces in 
question--one on each side--were located at the top of the exposed hull, against 
the deck and deck beams.  My goal was to fit a wider board here, with 
cutouts around the deck beams, to hide this area before getting into the nitty 
gritty of the ceiling installation
 |  
    | This proved to be more challenging than expected, and the second board fought me 
every step of the way--so much so that in the end, I stepped back and decided to 
call it quits for the day at 1500, with only one of the two boards cut and 
properly fit.
 Fortunately, a fresh start 
Monday morning saw the second board complete, which was good. Click 
here for more about the beginnings of the hull ceiling in the v-berth. |  
    | Monday was a scattered day.  While it began well enough, I couldn't get 
focused in the shop, as it seemed each time I would go to begin one project or 
another, I'd think of some fasteners, or parts, or additional equipment I would 
need, and would run back into the office to research and place and order--only 
to repeat this process several times throughout the day.  I was ready to 
begin systems installation, but it was pointless to go far without the proper 
parts.  Chief among th4ese was a fuel tank.  I had ordered an aluminum 
fuel tank for the boat, but when it arrived last week, it was damaged in 
shipment, and was the wrong tank--the one I was sent was for above decks 
installation, complete with a removable fill cap.  I ordered a replacement, 
after double-checking the catalog; it seemed I had ordered the right thing, but 
received something else.
 |  
    | When the replacement tank arrived Monday, I was dismayed to find that it was the 
wrong thing again--slightly different from the first, but still wrong.  
This time, the new tank was pretty poor in quality too--I was not impressed.   
Therefore, I scurried to locate a suitable tank, eventually finding one that 
looked good in another supplier's catalog; it was even in stock, which meant I'd 
get it Tuesday morning.
 The long and the 
short of it was that Monday was not that productive, though I did accomplish 
many important steps towards the remainder of the week's work, including getting 
things set up on board--loading tools and parts.  I started some work on a 
new toerail mockup in the afternoon, but then some new computer equipment I had 
ordered arrived, so I knocked off early to set that up. |  
    | 
  Tuesday, after one more final round of sanding on 
the keel work, I got to work on the diesel fuel system.  Once the new tank 
arrived, it was, in concept, a simple matter to install the tank and run fill, 
supply, vent, and return lines.  In actuality, the project took the rest of 
the day, but it was fun to do and a nice change of pace from the earlier 
drudgery of trim installation. 
Click here for details on the fuel 
system. |  
    | 
  Wednesday, I continued by finishing up the fuel fill, arrangement, and then 
moved on to the exhaust system.  Configuring the exhaust took a few minutes 
of thought to determine the location for the fiberglass waterlift, but after 
some consideration and consultation with a few reference sources I chose a 
location right next to the engine on the port side.  With that done, I 
prepared to run the hose and install some fittings.  Late in the day, just 
before quitting time, I epoxied the waterlift to the inside of the hull to 
secure it, and left it till the next day. 
Click here for more about the exhaust 
system. |  
    | Thursday, I wrapped up some exhaust system final details, and continued systems 
installation with work on the through hulls.  I planned three through hulls 
for the boat:  two cockpit scuppers and one engine raw water intake.  
Even though the boat would be destined for fair weather, inshore use, I 
specified full flange bronze seacocks.
 From inside the boat, I determined the locations 
for the fittings, after mocking up the hose installations to ensure clear 
passage for service and accessibility later, and then marked and drilled the 
holes in the hull for the fittings. If this seems like an insignificant 
accomplishment for a full day, rest assured that I spent far less than a full 
day working on the boat, as I had several other outside jobs to take care of 
while the weather allowed (with more heavy rains scheduled for the weekend), and 
other commitments on my time that required my attention.  Friday continued 
in a similar fashion, with no work completed on the Daysailor other than to 
prepare some fiberglass backing pads for the seacocks. |  
    | 
  Saturday, 
I installed the three seacocks and through hulls required, a process that, of 
course, took longer than anticipated, mostly because of some ridiculous backing 
plates that I built and which ended up becoming some sort of twisted labor of 
love. 
Click here for more on the seacocks. |  
    | Log for the Week Ending May 15, 2005
 
Unfortunately,  I had a disappointing amount of 
time available this week to spend on the Daysailor, with a number of other 
commitments that prevented me from working on the boat until Saturday, save for 
a half hour one afternoon spent attaching the final exhaust hose connection on 
the engine manifold (I had been awaiting a hose clamp shipment--and yes, it 
actually took a half hour to wedge the 1-1/2" hose onto the slightly larger 
outlet!). |  
    | Saturday, however, I jumped right in and managed to strike several items from my 
weekend list--an admittedly aggressive listing of around 10 items.  
Deciding to hold off on any further woodworking till Dasein departed the 
shop next week, I moved ahead with systems work and began the electrical wiring.
 |  
    | 
  Over 
the course of the day, I installed the battery boxes in the engine room, got a 
good start on the rough wiring (at least until I ran out of wire...a second reel 
I needed was backordered, and I had pilfered some of my other stock earlier in 
the week for another project I was working on), and began installing the battery 
cables--all of it time consuming, but highly enjoyable. 
Please 
click here for more about the electrical system. |  
    | 
  Also 
on Saturday, I finally installed the two top pieces of my v-berth ceiling, which 
I had built a couple weeks ago.  I had waited on their installation so that 
I could run wires beneath the ceiling to service the future sidelights at the 
bow. |  
    | 
  In 
between running the bulk wire for the electrical system and the battery cables, 
I installed the engine's raw water system, bolting a bronze sea strainer to the 
engine foundation and running the two short lengths of hose required.  This 
job was made overly time consuming by the ridiculous design of the sea strainer; 
the mounting bracket (integral with the strainer) was designed in such a way as 
to prohibit the insertion of screws or bolts from the strainer side, meaning 
that instead the strainer could only be hung from through bolts passing into the 
bracket from the other side; there was just enough room to squeeze a nut in 
there.  I would have returned the strainer in favor of a different one, 
after seeing this ridiculous feature, but had already disposed of the box it 
came in, as I am wont to do.  I got the job done, but what should have been 
a 5-minute job turned into a 30-minute one.  And so it goes. 
Click 
here for more on the raw water system. |  
    | The end must be approaching, as I also ordered 
interior cushions and sails for the boat.  The question is:  will I 
make my self-imposed completion date of the end of June?  Your guess is as 
good as mine.  Well, maybe not quite as good...
 |  
    | Log for 
the Week Ending May 22, 2005
 
 
  It 
was another busy week that left little shop time for construction progress, but 
I managed about three full days on board. 
Sunday was a full day in the shop.  I began by picking up where I left off 
with the battery cables.  I had just enough left on the reels to make the 
two sections required to run between the negative distribution buss (located 
behind the future electrical panel) and the battery, and also the main positive 
battery feed.  I had to order another reel of each color so  that I 
could make the various jumpers and such required, so I did not work on those at 
this time. 
Click here for more 
about the battery cables and terminal ends. |  
    | 
  With 
the cables complete and permanently installed (but still disconnected from the 
batteries, for now), I continued work on the electrical system.  Even 
though I was out of primary wire, and therefore couldn't finish the rough wiring 
runs yet, I spent some time connecting some of the ground wires to the main 
negative distribution buss, and permanently labeled all the existing wires using 
small adhesive number labels, which I covered with clear heat shrink tubing. 
Later in the day, I dug the old, decrepit rudder and 
rudderpost out of storage, and spent some time measuring for the new rudderpost 
and propeller shaft, as I planned to stop into the local prop shop the next day 
(since I happened to be going by there) to order these crucial parts. |  
    | Finally on Sunday, I turned my attention to the scuppers in the cockpit.  I 
had earlier chosen a set of Spartan bronze scupper fittings for the deck, and 
now mocked up a few possible locations for the fittings before finally settling 
on the outboard cockpit corners at the forward end.  If you recall, during 
construction of the cockpit I pitched the sole forward about 3/4" to allow for 
proper drainage.
 |  
    | 
  Once 
I had the location set, and had double-checked to confirm that there were no 
obstructions below, I drilled the holes for the fittings and installed them 
permanently; I needed some additional hose before I could finalize the 
installation, but when the hose arrived I immediately secured it in place, 
completing the scupper installation. 
Click here for more about the 
scuppers. |  
    | 
  I 
had another full day on Tuesday, with progress slightly slowed during the early 
afternoon by a power outage, which meant that I had only natural light from the 
doors and windows to work by.  This was OK, but a bit tough inside the 
cabin, where I happened to be working on wiring.  In any event, I ran the 
remainder of the rough wiring, wiring for the four cabin lights and stern light. 
Because of the convoluted run that the stern light and lights on the port side 
of the boat required (with the panel located on the starboard side), this 
seemingly simple task took most of the day.  After a few days away from the 
shop, I was finally able to finish up the rough wiring on Saturday afternoon, 
when I ran the final wires required for the electric bilge pump, and finalized 
many of the connections in the main wiring area behind the panel location. 
Click here for more about 
the wiring installation to date. |  
    | 
  I 
also finally installed some teak strips on the long-neglected cockpit hatches 
that cover the engine room.  Earlier, I had cut all the 1-1/2" 
(approximately) strips for the job, but hadn't installed them.  Now, I 
finally finished this part of the job. 
Click here 
for more on the cockpit sole hatches. |  
    | 
  I 
planned a full day Sunday (as of this writing), and looked forward to several 
good working days in the week ahead, though, once again, I had too many other 
commitments pulling at my time to dedicate full-time in the shop. |  
    | Log for the 
Week Ending May 29, 2005
 
 Sunday, I worked on the electrical panel.  I wanted to locate the main 
distribution panel, battery switch, and bilge pump switch in a recessed panel 
that would be hidden from view behind the eventual settee back panels, which 
would feature upholstered cushions attached to hinged panels.
 
In order to do this, I had to first build some basic 
cleats to support the panel, then construct a plywood panel into which I could 
install the various components.  I ended up trashing the first panel I 
made, since I found that I had made it too small to properly accommodate the 
electrical panel, and made a new, larger panel after enlarging the opening in 
the settee back to better accommodate things. 
 I 
also completed the various battery cables and connections required, including 
jumpers to connect the two batteries in parallel, wiring the main switch, and 
connecting the main distribution panel. 
Read about the process here. |  
    | We had a bout of stormy weather during most of the week, which raised many 
concerns for me about Glissando, now floating on her mooring in exposed Falmouth 
Foreside.  The first several days of the week were filled with numerous 
boat checks and an overriding worry about her potential fate in 40-knot winds.  
Eventually, the winds died, and by Thursday afternoon I was able to get aboard 
and check things out.  Despite some minor anchor platform damage, all was 
well, and I looked forward to concentrating on work once again.
 |  
    | 
  During 
this period, I did manage to get a few things done, but nothing of particular 
note.  I whittled away at the wiring and panel construction when I had a 
few spare minutes, and then, on a relatively productive day Friday, I completed 
the wiring for all intents and purposes; final fixture installation remained, 
but the panel was fully wired and ready to be placed into service. 
Click here for more 
about the wiring. |  
    | 
  Wednesday 
or Thursday, I received a box of goodies from Spartan Marine--it was like 
Christmas!  I had ordered a number of bronze parts for the boat, including 
winch stands, tiller head and strap, flush lifting rings, cleats, and secondary 
chainplates. |  
    | 
  I 
also finally secured a date for test-launching the boat to mark the waterline:  
next Tuesday, May 31.  In preparation for this, I temporarily closed over 
the stern tube opening in the aperture, the only remaining opening in the 
bottom, since my shaft had not arrived and I had not installed the stern tube 
permanently.  I simply applied a single layer of fiberglass tape over the 
opening. |  
    | 
  Late 
Friday, I masked off the remaining wooden trim in the interior so that I could 
begin applying varnish to the bare pieces, and then vacuumed the interior and 
applied the first, thinned coat of varnish to the bare wood. |  
    |    Continue to June 2005> |  |