|                    
     |  | 
  
    
      | Progress Report:  2005 
      Archives |  
  
  
    | Reports from March, 
2005
 3/6/05  
3/13/05  3/20/05  
3/27/05
 |  
    | Log for the Week Ending March 6, 2005
 
First, I apologize for the poor quality of many of 
the photos in this week's descriptions and some of last week's.  My poor 
camera, already on its last legs, survived a fall from the boat deck to the 
concrete floor last week.  While it's amazing that it still works at all, 
it's definitely not happy, and a replacement is on its way.  Meantime, the 
photos are coming out rather dark and sometimes filled with lines or fuzziness. 
 Since I'd had such an unproductive week last, and 
no work on Saturday, I decided to do some work on Sunday.  After a few days 
off from working on the cabin trunk, I had had time to contemplate some new 
approaches to the construction that I hoped would have a better chance of 
success.  I jumped right into this task, and cut, fit, and installed one 
side permanently in place, and prepared the second side for installation on 
Monday.  Monday, I continued with more work on the cabin trunk and was 
pleased with the relative ease with which things fell into place, finally. Click here to read about how I built the cabin 
trunk. |  
    | 
  In 
preparation for final work on the coaming boards, I addressed the small matter 
of the rabbet in the port coaming board that I had cut earlier.  My new 
installation plan called for the coaming to be secured entirely inside the 
cockpit well, so no rabbet would be required.  Since the original rabbet 
was on the outside (well, the edge that pressed against the outer wall of the 
cockpit), and would be hidden in the final installation, I cut a strip of 
mahogany to fit the rabbet and epoxied it in place, just to fill the gap.  
This would return the board to full strength.  I left the strip to cure, 
and then sanded everything smooth again. |  
    | 
  Monday was soured by the lack of delivery of my engine.  All day long, I 
kept my cell phone nearby--something I never, ever do, as I loathe the 
things--in case the delivery driver needed guidance to get here or if there were 
any problems.  Phones and email remained mute, but by about 1400 I was 
really starting to wonder.  Finally, I placed a call to the business from 
which I had ordered the engine.  Of course, the delivery had been canceled, 
ostensibly because of a pending snowstorm.  Fair enough:  but first of 
all, no one called me to let me know (this was, to me, the primary failure of 
the company); secondly, the snowstorm, to anyone willing 
to take a pair of seconds to check, was arriving slower than anticipated, and 
didn't reach southern New England, where they were located, until evening.  
Thirdly, they could have easily delivered the engine early and been back well 
before even the earlier predictions of the snow.  Finally, I had already 
waited patiently for three weeks, endured a change in the delivery schedule last 
Friday, and had, frankly, used up my nice-guy points.  I was a bit unhappy 
with them, but nonetheless we eventually settled on Wednesday for engine 
delivery here.  What else could I do but wait? There was no shop work on 
Tuesday because of an ongoing snowstorm.  Unlike last week, I actually 
looked forward to getting back into the project on Wednesday.  My start in 
the shop on Wednesday was delayed by another surprise snowstorm overnight, which 
required plowing again in the morning. |  
    | 
  When I finally arrived at the shop in the late 
morning, I removed the clamps from the coaming repair and those from the cabin 
trunk lamination, and continued work on the coamings.  The port side 
coaming was already cut more or less to the correct size and shape, though I had 
to deepen the relief cuts at each end, since the coaming was now to sit about 3" 
down beyond the deck edge, about twice the distance I had considered during the 
original installation attempts. 
 Click here for more about the 
initial coamings' installation.
 |  
    | 
  Late Wednesday morning, my new Vetus diesel engine 
arrived, at long last, from the dealer in Massachusetts.  (...and 
there was much rejoicing...)  
The engine came installed on a pallet surrounded 
by an enormous orange box, a box of such sturdy construction that I considered 
using it to build a strong boat. |  
    | 
  For the time being, I left the engine safely crated 
and covered in its protective plastic, but looked forward to the opportunity to 
begin its installation in the near future. 
Click here for more about the engine. |  
    | Thursday I was away from the shop all day with other 
commitments.  It seems the last few weeks have been full of delays, which 
are starting to bother me.
 
 In any event, I 
returned to work Friday, armed with the screws I needed, and without difficulty 
secured both rough coaming pieces in place against the cockpit walls.  With 
the coamings secured in place, I carefully used my cardboard templates, which I 
originally made as a cabin/coaming mockup a few weeks ago, to mark the outline 
of the cuts needed to complete the cabin trunk and coamings.  After 
sweetening the lines with a wooden batten, I cut off the excess, a deceptively 
simple job that took more than two hours, all told. Click here 
for more. |  
    | 
  Before 
knocking off on Friday, I made two small glue-ups with some scrap mahogany, 
which I planned to use to create some trim pieces the next day.  I glued 
the pieces together with the standard mix of epoxy resin and cabosil, clamped 
them tightly, and left them to cure overnight.       
 Saturday 
morning, I spent about an hour and a half building two small, 6" bullnosed 
blocks to cover--and highlight--the joint between the coamings and cabin trunk.  
Since there was no way to make this joint invisible, I chose to instead 
celebrate the seam with  a pleasingly curved block of mahogany. 
 Click here to see how I made these 
blocks.
 |  
    | 
  I 
filled the rest of Saturday working on the interior, now that the basis of the 
cabin trunk was finally complete.  The final stages of interior 
construction included installing two small bulkheads (dividers, really) in the 
settee backs, and the beginnings of installing some more beadboard that would 
cover many of the cabin surfaces. 
Click here to see the progress on 
the interior. |  
    | Log for the Week 
Ending March 13, 2005
 
 Sunday, I 
worked for a few hours to finish a few minor jobs that would put me ahead of the 
game come Monday.  To begin, I added a final cleat to the settee back 
structure, at the forward end.  With that done, I moved on to the task that 
I really wanted to complete:  painting out the insides of the new lockers, 
which I wanted to do before installing the new beadboard backs.  Pulling 
out the gray Bilgekote once more, I applied a coat of paint to all the new 
surfaces, finally covering one of the last remaining vestiges of the raw 
fiberglass beneath. |  
    | Monday was a busy day.  I began by installing the beadboard settee backs, 
and with that out of the way moved onto cutting, fitting, and installing all the 
remaining beadboard in the  cabin areas:  on the lower portions of the 
settees and on the forward-facing side of the chainplate bulkhead.  These 
areas would all be visible in the final interior, and I planned a white-painted 
beaded surface with plenty of varnished mahogany trim.
 
Click here for more about the beadboard 
installation. |  
    | The beadboard jobs took a surprisingly long time and 
consumed most of the morning.  When the installation was complete, I moved 
on to thinking about my new engine foundations, which I wanted to get built and 
installed as soon as possible.  After some thought, I decided to build the 
foundations out of a core of Meranti plywood (of which I had abundant supply in 
the shop) rather than solid wood of one form or another.
 
 To begin, however, I first had to prepare my engine 
base template and set it up in the boat so that I could determine the rough 
dimensions of the foundations needed.  Over the course of an afternoon, and 
the entire subsequent work day, I set up the template, measured for and built 
the engine foundations, and secured the new foundations in place. Please click here for more about the engine 
foundations. |  
    | Wednesday ended up being a non-work day, as plowing 
kept me away from the shop longer than expected and I was simply too tired to 
work in the late afternoon.  Likewise, I had appointments that kept me away 
on Thursday and Friday, disappointing delays in my schedule but unavoidable.
 
 The 
work has continued to be hampered (purely from an available time standpoint) by 
what has turned out to be one real Maine winter, with frequent and continuing 
large snowstorms.  Since January 6, we've had 13 plowable storms, many of 
which featured large accumulations that required multiple plows each.  Your 
weary snowplowing host has had enough, particularly in light of the way these 
storms are adversely affecting my building schedule.  Even after a large 
near-12" storm on Tuesday night, Saturday this week 
continued the trend, with another large storm that set up just right for dumping 
an estimated 18" on us, and prevented 
any work from occurring in the shop yet again. If you're keeping count, that means that I only 
had 2-1/2 workdays in the shop this week...disappointing. Tentatively--and I hardly dare say so--it looks 
as if the next several days might be calm and storm-free.  Perhaps I can 
get done in the shop next week what I had meant to do this week. |  
    | Log for the Week Ending March 20, 2005
 
 Monday morning, I jumped right back into work on the 
engine foundations.  I began by quickly sanding last week's epoxy fillets 
around the bases, and then prepared to fiberglass the foundations permanently in 
place with several layers of heavy biaxial tape. Click 
here for the details on fiberglassing the foundations. |  
    | 
  After the 4-hour (elapsed) chore of preparing, cutting, and installing the 
fiberglass, I continued by taking care of a small, yet important, project:  
filling the holes left by the screws that I used to temporarily secure the 
interior beadboard while the adhesive cured.  This was one of those 
irritating projects, but one that needed to get done so that I could move on to 
begin the priming and painting process. |  
    | Next, I continued by beginning work on the laminated cabin trunk overhead beams.  
I needed 5 or 6 of these beams to frame and support the overhead and thus 
complete the cabin trunk construction.  Since I had delayed the ordering of 
my new mast so that I could get an accurate measurement from the new keel step 
to the mast partners (which would, of course, be defined by the actual coachroof 
position), it was time--past time, really--to get this project underway.
 
 Long ago, I had prepared a basic pine template of 
the cabin trunk curvature as defined by the midships bulkhead.  With this 
in hand, I laid out a series of molds on a sheet of plastic-covered plywood that 
I awkwardly set up on two high sawhorses to allow it to fit in the space at the 
front of the shop, above the large box that still contained the engine.  To 
speed up the laminating process, I had hoped to build up to 4 curved molds, but 
after many tedious minutes creating two of the molds out of 2x4 scraps, I 
decided my time would be better spent elsewhere.  With only a maximum of 6 
beams required, at least I had shortened the laminating process to only three 
days' time. Click here 
for more on the cabin trunk beams. |  
    | 
  Over 
the next three days--Tuesday, Wednesday, and Thursday-- I laminated the 
remaining beams till I had six total.  Each morning, I glued up two beams 
and left them to cure till the next day.  On Friday morning, the beams were 
complete, so I spent some time at the planer cleaning up the beams and achieving 
a consistent thickness through all six beams.  Now, they were ready for 
final fitting and installation, which I worked on Saturday. 
Click here to 
see more about cutting and fitting the cabin trunk beams. |  
    | 
  With 
the engine foundations all tabbed securely in place, it was finally time to 
paint out the remaining bilge areas with more gray Bilgekote. I took care of 
this first thing on Friday morning, then covered the open area with the engine 
hatches to keep dust out while I worked on other projects. |  
    | 
  Also 
on Friday, I sanded all the primed beadboard to prepare it for subsequent coats 
of white paint, and also sanded the inside and outside of the cabin trunk to 
prepare for the initial coats of varnish.  By the end of the day Friday, I 
was ready to apply the white paint and varnish, a pleasing way to end the day.  
I also added a coat of white paint to beadboard on the chainlocker bulkhead, 
which had been in primer for some months now awaiting its companions in the main 
cabin to be installed. 
Click here for more on the 
beadboard and cabin. It was a great pleasure to have a full week with 
no snowstorms, and no real interruptions to the construction progress, though I 
was out of the shop all day on Thursday.  I hoped that the trend would 
continue in the coming few weeks, as I anticipated significant progress and 
passing several more milestones during that time.  Stay tuned! |  
    | Log for 
the Week Ending March 27, 2005
 
Anxious to keep cabin trunk construction moving along, I began on Sunday morning 
by working on the new cabin trunk beams, which I had cut and fit roughly in 
place the day before (last week's update).  With that work out of the way, 
I prepared the beams for final installation by routing a chamfer detail on the 
lower edges, and then sanding the beams through 220 grit.  When the beams 
were all prepared, I installed them permanently in the slots in the cabin trunk. 
Click here to read more about the cabin trunk beams' installation. |  
    | 
  Monday 
morning, I headed off to pick up two extra sheets of beaded plywood, which I 
planned to use for the down-facing layer of the new coachroof.  With the 
two sheets in hand, I prepared the two pieces needed to cover the cabin trunk 
beams; one side at a time, I temporarily installed a sheet of plywood and marked 
the outline of the cabin trunk, then cut out the piece as needed. 
Click here for 
more about the overhead/coachroof. |  
    | 
  It 
seemed that the remainder of the week was lacking in major headlines, or 
significant projects I could point to, but it was a very busy week in the shop 
nonetheless.  With plans indelibly set in place that included spraying 
finish primer in the next week, both on the Daysailor and also on the Sanborn's
Dasein next door, I used the week to take care of many smaller aspects of 
the project, including application of several coats of white paint on the 
various beadboard pieces in the cabin and cabin trunk overhead, varnish 
application on the cabin trunk, and several other small chores.  I also had 
several smaller, unrelated projects going on in the shop that I worked on, which 
took quite a bit of my time. |  
    | 
  Later 
in the week, in preparation for final installation of the coachroof, I worked on 
a couple trim pieces, which I fashioned as sort of structural knees running 
between the inside edges of the cabin trunk and the overhead beam in way of the 
mast partners.  The main purpose of these two trim pieces was to cover the 
inside seam where the pieces forming the cabin trunk met, but in reality they 
would also help secure the whole structure together as well.  This photo 
shows the knees after shaping and application of one coat of varnish; I'll post 
more about them next week. |  
    | 
  In 
preparation for priming, painting, and engine installation, I removed the 
cockpit coamings; the coamings also required finish work, sanding, and varnish, 
so it was time to remove them.  Rather than fight with the silly jack 
arrangement I had used during fitting, I purchased an inexpensive scissor jack 
and built a dedicated rig to use for the coamings, both for their removal now 
and for later installation. |  
    | When the coamings were off, I routed edge details on the top edges, cut the 
after ends to their final shape, and finish sanded both pieces to 220 grit.  
Then, I began the long process of varnishing the coamings by applying the first 
of 10 coats of varnish needed.  With two sides to varnish, I was looking at 
close to a months' elapsed time (at a day per coat, per side) before the varnish would be done.
 |  
    | 
  On 
Friday afternoon, with Nathan Sanborn's help, I lifted the new Vetus diesel up 
into the cockpit, and prepared for final installation on the new engine 
foundations.  Saturday morning, I prepared the foundations for the 
installation, by installing some threaded inserts in the foundations and then, 
latte in the day, lowering the engine onto the foundations and securing it 
loosely in place, awaiting final alignment and connections. 
Click here for more about 
the engine installation. 
  |  
    | Continue to April>
 |  |