|                    
     |  | 
  
    
      | Progress Report:  2005 
      Archives |  
  
  
    | Reports from June 2005
 6/5/05  
6/12/05  6/19/05  
6/26/05
 |  
    | Log for the Week 
Ending June 5, 2005
 Sunday and 
Monday, I dabbled here and there in the shop and around, but didn't really 
accomplish much of note.  Mostly, I prepared the boat for Tuesday's 
scheduled test launching by removing tools and gear, and making sure the boat 
was ready in all other ways.  I spent some frustrating time changing the 
planer blades for new; one of the screws (out of 14 total) securing one of the 
two blades was frozen solid, and I could not move it; in fact, I quickly rounded 
over the nut, to my great annoyance, and ended up, after many attempts to 
otherwise remove it, grinding the nut out of the small groove with a cutting 
disc.  |  
    | 
  Tuesday morning at 0700, my boat hauler picked the boat up at the shop and 
hauled her down to the town landing for a quick in and out so that I could mark 
the waterline according how she really floated.  I was surprisingly 
completely at ease with the process and felt no jitters.  It was 
interesting seeing the boat outside of the shop for the first time, as she 
braved the daylight for a stealthy and rapid launching. 
Please click 
here for more about the test launching and waterline. |  
    | By 0800, the boat was back in the shop, and I spent the rest of the day running 
around doing errands and other such distractions.  I picked up my propeller 
shaft and coupling and dropped the new tiller strap/cap fitting off at the prop 
shop so they could ensure a good fit with the new rudder shaft,  did 
several other errands of little note, and picked up some 8/4 mahogany to be used 
for the boat's toerails.  Despite all the mahogany I had in the shop, I 
needed something thicker to allow the toerails to work the way I intended, and 
to have the design and shape that I desired.
 
 Test-fitting 
the new propeller, shaft, I immediately discovered that the shaft was too long.  
I had provided the shop with the measurement from the aft end of the 
transmission coupling to the end of the stern tube (3" proud of the hull), 
charging them with figuring out the proper allowances for clearance, shaft 
taper, and the like.  Apparently, this was too much for them, but at least 
it should be easier to shorten the shaft a few inches than it would be to 
lengthen it had it been too short! 
Oops!  
Edit Sunday Afternoon:  My apologies:  
further investigation showed that the shaft actually did fit properly, with no 
modifications necessary.  It was not pressed all the way into the coupling, 
and I had for some reason been thinking that the shaft end had to clear a line 
running straight from the upper part of the aperture to the lower part shown in 
the photo, when of course the rudder aperture will square this opening off when 
complete.  In any event, the shaft is fine! |  
    | 
  Back in the shop late in the afternoon, I worked for a couple hours planing the 
raw stock smooth (with new planer blades--nice!), and then cut the rough-sized 
blanks required for the toerail.  The wood contained substantial internal 
stresses and was quite difficult to resaw into blanks about 2" square (roughly), 
but eventually I got it done.  Afterwards, I began the multi-[step process 
of forming the blanks into the toerail before calling it quits for the evening. 
Click here for 
more on the toerails. |  
    | Wednesday was another pre-occupied day, and it wasn't until later in the 
afternoon that I could return to the shop for more work on the toerails.  
Over the period of about two hours, I completed the rough milling procedures on 
the toerail blanks, forming the basic shape required.   I set the 
pieces aside for sanding on another day.
 |  
    | 
  Friday morning, I spent a marathon session sanding all the toerail pieces 
through three grits:  80, 120, and 220, smoothing them out for final 
installation.  It seemed as if the wood multiplied in length as I 
proceeded, as the job took forever, but eventually I was done.  With all 
the milling and sanding complete, I applied a quick sealer coat of varnish 
before proceeding with other steps. 
Click here to read about the toerails. |  
    | We had to go away to a wedding for the weekend, leaving Friday afternoon, so I 
did not get a chance to do any further work this week, unfortunately.  I 
hardly know week to week how things are going to go, but I do hope to get the 
toerails installed permanently next week, at least.
 |  
    | Log for the Week Ending June 12, 2005
 
 After 
being away for the weekend, I was anxious to get back to work on the boat as 
soon as I could on Sunday afternoon.  By the time I got going, it was a bit 
later than I had hoped, so I did not try to work on the toerails.  Instead, 
I went to work on the teak-covered engine room hatches, applying black 
polysulfide caulk into the seams between the teak planks. A previous experience 
with a similar project had prepared me for the length of time that the job would 
take, but even so, it took about two tedious, tiring hours to pump caulk into 
the grooves.  Nonetheless, this was a necessary project, and completing it 
on an otherwise unproductive weekend was an excellent use of time. 
Click here for more about the teak engine room hatches. |  
    | When that job was finally complete, I set up the staging around the boat again, 
at the highest level so that I could work on the toerail installation.  
After last week's test launch, the boat was slightly farther back in the shop, 
and a bit more to the side, so the staging was tight on the starboard aft side, 
but it worked.  When the staging was up, I played around with one of the 
toerail sections, trying to get a feel for how the installation would begin--and 
then how it would continue thereafter.
 |  
    | The Darkening of the Light
 One by one, inexorably, the lights in the shop are dying.  I don't know 
what is causing the premature death of these fluorescent fixtures, but fully 25% 
of the lights have stopped working (that's 5 out of 20 total).  Things are 
starting to get pretty dark in the shop.  Each day when I arrive, I hold my 
breath, wondering if yet another light blinked out for the last time the night 
before.
 
 I 
took one fixture down and changed the bulbs, but it seems to be the ballast that 
has failed.  Given the relatively inexpensive nature of these lights, I 
doubt it makes sense to replace the ballast, and I am annoyed at this 
inconvenience.  Frankly, I did not anticipate any maintenance on these 
fixtures, other than a very occasional bulb change.  To have them 
dropping like flies is beyond an irritation.  16' off the floor does not 
make for convenient maintenance or replacement, particularly when one must move 
the ladder twice for each fixture in order to reach the chains for removal--and, 
more importantly, I just don't have time to deal with it.  Buying new 
ballasts (or, more likely, whole new fixtures), removing the old, dead lights, 
repairing them, and replacing them (or simply swapping out the old for new) 
would consume the better part of a day, all told. These fixtures were the middle-of-the-road shop 
fluorescents from Home Despot, chosen over the ultra-cheap ones because of the 
larger reflectors.  I am very unhappy at this development, and find the 
failure of these shop lights to be unacceptable.  In any event, I am 
working through the relative darkness for now, until I can dedicate the time for 
replacement.  It is not something I should have to do after less than 2 
years' use.    Fortunately, with the warmer summer weather, I now 
usually work with the large doors open, so there is even more natural light at 
my disposal. |  
    | Monday morning, I tackled the toerails.  It took me a bit of time to 
collect the various tools needed, find the right drill bits (counterbore and 
pilot), and move various pieces and parts to the boat for convenient access.  
Working alone, I began at the port bow with the first section, feeling my way 
along as I went, since I wasn't sure how the installation was going to pan out.
 |  
    | 
  By 1100, I had the first section dry-fit, and although the process had gone 
relatively smoothly, I was feeling rather discouraged at the progress.  
Presently, I got into the groove, however, and managed to permanently install 
both sides of the toerail (6 sections) by that evening, completing, for all 
intents and purposes, the toerail installation. 
Click here to read about installing the toerails. |  
    | Completing both sides of the toerails--dry fit, removal, and permanent 
mounting--in a single day was something of a bonus for me, since at best I had 
hoped to do one side per day.  Toerails had been my main goal for the week, 
though of course I hoped to accomplish much more, but I knew that I had a busy 
week ahead of me, with other commitments appointments to deal with.
 
Late Tuesday afternoon, with a few hours to work in 
the shop, I cut 100 mahogany bungs for the toerail fasteners and installed them 
with resorcinol glue, knowing I would  be away all day Wednesday and 
therefore giving the glue plenty of time to cure before I might be able to 
return to shave off the excess. |  
    | 
  Friday, I planned a full day in the shop.  I began by shaving the plugs 
flush with the rail, using a small block plane.  Then, I sanded the rails 
and plugs smooth to remove any final roughness and glue residue, using 120 where 
needed to get the glue off and finishing up with 220 on everything. |  
    | 
  I also worked on the engine and shaft log.  Now that I had the propeller 
shaft on hand (and had determined that it actually was the right 
length), the next step was to install it, and then secure the stern tube.  
Rather than align the engine to the shaft, I had long ago decided that I would 
hold off on stern tube installation until the engine was in place, and then 
epoxy the stern tube in place when the shaft was perfectly aligned with the 
engine. 
Read more about this process. |  
    | To finish off Friday, I began to think about laying out and striking the 
waterline, and the boottop striping.  My first step was to determine 
whether the boat needed leveling after last week's test launching and moving.  
With a level across first the cockpit sole, then inside the cabin, on two 
surfaces that I knew to have been leveled according to the way the boat was 
blocked previously, I determined that only minor adjustments were needed from 
side-to-side.
 
 
  Then, I turned my attention to the longitudinal leveling, always a bit more 
tricky.  I decided to try using my inexpensive laser level for the job.  
Unfortunately, the tripod was not tall enough to allow the beam to reach the 
needed height, but I placed the whole unit on top of my rolling staging at its 
lowest level, which raised it appropriately and also made it easily mobile.  
After leveling the unit, I set the height at the stern waterline that I had 
marked with the boat in the water, and then rolled the whole thing forward.  
It seemed to align almost perfectly with the marked bow waterline, so I tried 
marking out the remainder of the waterline by moving the level off to the far 
side of the shop, where it could shoot a beam to all portions of the boat 
without moving. This seemed to work at first, but eventually I 
realized that I was not getting accurate marks, so it looked like I would have 
to use the level at a closer range and with a more direct beam shot at the boat 
in all areas.  That pretty much ended the day, though I stayed in the shop 
to wait out a powerful thunderstorm that rolled through, turning day into night.  
It was fun watching the storm in the safety of the shop, though with the large 
front doors open I felt as if I was truly experiencing the storm. 
More on the waterline later. |  
    | 
  Saturday 
afternoon, with a few hours to spare, I sanded the new trim pieces at the 
forward end of the toerails, on the breasthook, and then applied masking tape to 
the inside and outside of the rails on the hull and deck in preparation for 
varnish.  I also sanded the varnish inside the cabin so that I could apply 
another coat there.  Over the next several days and weeks, I planned to 
continue applying varnish to the toerails whenever possible to build up the base 
I wanted, and also to finish up the varnishing in the cabin once and for all. |  
    | 
  My hopeful completion and launching schedule seems to bear no relationship to 
actual reality.  At this point, all I can do is keep working as much as 
time allows and keep my eye on the goal.  However, with no mast in sight 
yet (return calls pending), full rigging construction ahead (only after the mast 
arrives on site) and substantial work remaining on deck, it is extremely 
difficult to predict when things might be done enough to consider launching for 
sea trials.   Trying too hard to meet an impossible deadline, imposed 
only by me, runs the risk not only of ultimate failure anyway, but also taking 
the fun out of the process. |  
    | It seems clear to me that the boat will not be ready for launch by the end of 
June, as I had hoped.  I will continue plugging away as efficiently as I 
can, one project at a time.
 |  
    | Log for the Week 
Ending June 19, 2005
 After a day 
off Monday to work on, and sail, Glissando, I returned to the shop 
looking forward to a productive week.  With few significant plans to draw 
me away from work, and lousy weather predicted for most of the week, I hoped to 
knock many items off my most recent to-do list.  Every so often, I'll write 
out a realistic list of chores on my board in the shop to help me stay on track. |  
    | I began by addressing the trim around the top of the cabin trunk, to cover the 
seam left by the plywood coachroof.  I wanted to get this done so that I 
could begin varnishing the cabin trunk in earnest, along with the multiple coats 
required on the toerail.  I'd been postponing serious varnish work for too 
long, and now it was time to make an effort.
 
 After considering a number of possible approaches in 
my mind, and one bending failure with some existing trim profile that I had, I 
succeeded with a basic strip that I bent around the edge of the cabin trunk and 
secured with epoxy and temporary screws; I planned to shape the piece by hand 
once it was permanently affixed. Click here 
for more about the cabin trunk trim. |  
    | 
  While the epoxy cured, I moved on to other tasks.  I next turned my 
attention to the waterline and boottop, which I had tentatively approached last 
week and again over the weekend.  Now, it was time to get these lines 
struck properly, particularly since I knew that painting the boottop and bottom 
would add a needed look of completeness to the boat--and I was excited to see 
how she would look. |  
    | 
  Since I planned on a double boot stripe, laying out the myriad lines was quite 
time consuming--it took most of two full days, in fact, before the final tape 
was in place.  With the taping complete, I moved on to some sanding and 
preparation before applying Flag Blue Awlgrip to the stripes, using three coats 
to obtain a satisfactory finish. 
Click here for more about the boottop and 
waterline. |  
    | Marking, taping, prepping, and painting the waterline, along with some 
additional work on the new cabin trunk trim and varnishing on the toerail and 
cabin trunk, took up the bulk of the work week. Finish work is so important, but 
everything takes a very long time.  In between sanding, prepping and 
painting the boottop, I removed the temporary screws from the cabin trunk trim 
and installed bungs to hide the holes, and cleaned up and slightly shaped the 
new trim to finish it off.  Then, the new trim was ready for varnish.  
I also installed permanently the two after coaming blocks that I had built some 
time ago, so that they could be incorporated seamlessly with the cabin trunk 
varnish.
 |  
    | 
  By the end of the week, however, the boat had taken broad steps towards a more 
complete look--an gave me an important psychological edge.  The existing 
wooden trim on deck--cabin trunk and toerails--began to glow beneath new 
varnish, and the completed boottop and bottom paint looked great. I looked 
forward to jumping into some major woodworking next week. |  
    | Log for the Week Ending June 26, 2005
 I 
just had to take Monday off to go sailing.  It was one of those perfect 
days, so I treated myself, with the caveat that I would push myself the 
remainder of the week; it was to be a short week, as we were going away Friday 
and Saturday, so I needed to get as much done as possible. 
 Tuesday, I got right back to work, and spent the 
morning doing some final fiberglass repairs to the keel; some areas that had 
been inaccessible beneath the blocking before were now exposed, since I had had 
the boat blocked slightly differently after the test launch, and I needed to 
just clean up some of the last vestiges of the miserable old polyester 
fiberglass work that had been done to the keel some time long ago. 
I also secured the stern tube with additional fiberglass, and wrapped fiberglass 
around the outside of the tube as well for some additional thickness.  The 
fiberglass work cured so quickly in the heat of the day that I was able to apply 
a coat of fairing compound to the new work by the end of the day, speeding along 
the process. |  
    | 
  Tuesday morning, I also sanded all the brightwork, inside and out, in 
preparation for the ongoing varnish process.  Then, I continued work on 
the teak-covered engine hatches, which I had placed aside a week or two earlier.  
Now, I pulled them out and sanded the surface to remove the excess polysulfide 
and smooth out any unevenness between the planks, creating a very expensive pile 
of teak sawdust at the end. With that out 
of the way, I prepared to mill up some wood for the final woodworking projects 
on board, including the cockpit seating areas.  I had an appointment in the 
middle of the afternoon, which really cut into the day, but when I returned to 
the shop afterwards I managed to get all the rough-cut wood through the planer, 
smoothing it and reducing its thickness to 7/8".  With about 10 boards, 
each 12 feet in length, this took a few hours; cleaning up the chips afterwards 
seemed to take equally as long! |  
    | 
  Wednesday, I straightened one side of the boards--a laborious, dusty process 
using a long straightedge and circular saw.  I hate this.  I'd give 
anything for D3S lumber, but I can't complain with the wood and the delivery, so 
it is what it is.  With the boards finally planed smooth and with one 
straight edge, I  could begin milling them into slats for the cockpit.  
After determining that about 14" was a good width for the seats, I milled four 
3" slats for each side, planning on 1/4" between each slat, plus an edge band 
for an additional 7/8", bringing the total width to nearly 14". 
 With that, the rough work was out of the way, but I still needed to conceive 
exactly how I was going to design and build the supports for the seats.  I 
wanted to build laminated arched supports that would avoid the need for vertical 
legs at the outer edge of the seats.  Over the course of the week, this 
conception managed to get pushed temporarily aside, so look for more next week.
 |  
    | 
  With the new fiberglass work on the stern tube and keel cured, I sanded the 
fairing compound and cleaned up the areas.  The stern tube was now ready 
for final installation of the Cutless bearing, so I took care of that simple 
job. 
Click here for more about the stern 
tube and shafting. |  
    | Thursday, I built a blank for the new rudder, using four pieces of 1" thick 
mahogany that I glued together to make a large panel.  I planned a slightly 
different shape for the new rudder, compared to the old crescent-shaped version, 
but I thought that traditional solid wood construction, with excellent adhesive 
and drift pins, would certainly be an adequate choice.  I had dreams of 
foam and carbon fiber, but then I came back to reality.  Next boat...
 
Click here for more on the ongoing rudder work. |  
    | I
  continued work on the engine hatches by boring 
3/8" counterbores with a Forstner bit at each hole left by the installation 
screws (which I had previously removed), and then installing teak bungs to fill 
the holes.  I used resorcinol glue leftover from gluing up the rudder 
blank.  In all, there were 120 holes to be plugged. 
Click here to read more about the engine room 
hatches. |  
    | 
  With most of the significant raw wood preparation complete, I turned my 
attention once more to the cockpit.  The sides of the cockpit well needed 
to be painted with Alexseal.  While most of the deck would eventually be 
covered with nonskid, the vertical sides of the cockpit would not, so I began to 
prepare to finally apply the finish paint to those areas.  Since we planned 
to be away for two days, I thought this was the perfect opportunity to apply the 
paint and allow it to cure for a couple days, which would get it past the 
initial cure stage and help prevent unwanted damage to the paint during later 
construction steps. |  
    | 
  I swept up the shop, and then blew down the walls, surfaces, shelves, and 
corners, extracting large quantities of dust, debris, and wood chips.  It 
certainly was easier to clean the shop with only one boat inside!  Once 
that was done, I vacuumed the boat, inside and out, and masked off the areas to 
be painted, and then covered the entire remainder of the deck in plastic, to be 
sure that no overspray got on any of the brightwork or other areas. |  
    | 
  Finally, late in the day, I applied, by spray, two 
coats of Alexseal snow white.  It was an easy job, complicated only by the 
significant setup and preparation time.  The two coats covered adequately 
and left pleasing depth and gloss. 
Click here for more about the cockpit paint. |  
    | 
  Saturday, 
after removing the plastic and masking tape from Thursday's painting, I worked 
on the varnish.  With a clean shop on hand, it was the perfect time to 
apply a clean coat to all surfaces.  For some time, the interior had been 
sanded and awaited a coat of satin varnish, so I began there.  Afterwards, 
I varnished the cabin trunk, toerail, and coamings, closing in on the buildup I 
wanted for each section. |  
    | 
   
 |  
    | 
  Things are slowly 
shaping up.  With the myriad delays and the "everything takes longer than 
expected" syndrome that plagues all projects, I re-evaluated my proposed 
completion and launching schedule, and now planned to complete the boat by the 
last week in July, prior to my departure on a Glissando cruise, and to launch 
and rig the boat in August, after cruising. 
All I'll need then is an enthusiastic buyer for her! 
Continue to July>
   |  |