Arietta 17

Boat:

Arietta, a 1980 Cape Dory 22

Schedule:

Project Schedule:  December 2020 – January 2021

Project Scope: Repairs to cockpit sole and seats, cockpit refinishing, transom repairs, hull paint, and related work

Project Complete:  161.75 Total Hours

Begin Daily Project Logs

December 23, 2020

Arietta 17

Wednesday

With the primer sufficiently cured overnight, I began in the cockpit and sanded all surfaces with 220 grit by machine and hand as necessary, smoothing the primer to prepare it for the next steps.

With the deck areas sanded, I moved on to the hull, sanding all areas with 220 grit paper.

I was pleased with the primer and the resulting substrate in all areas.  Coming up next:  Cleanup, inspection, and fine filler application on pinholes or other areas requiring additional attention before finish primer.  But for now it was time for Christmas break.

Total time billed on this job today:  4  hours

0600 Weather Observation:  29°, clear.  Forecast for the day:  Increasing clouds, 31°