| |
Progress
Report: 2004 Archives |
Archives
Menu Main Project
Menu |
January
February March
April
May
June
July
August
September
October
November
December |
Reports from October, 2004
10/3/04
10/10/04 10/17/04 10/24/04
10/31/04
|
Log for the Week
Ending October 3, 2004
Finally,
some progress! After weeks of delay, I jumped back into construction by
permanently installing the bronze stem casting over the breasthook, completing
the punch list of items that needed to be complete before sheathing the decks.
Click here
for more.
|
I
continued by
cutting the sections of beadboard plywood for the first (bottom) layer of the
decks. Over several hours, I cut all the pieces for the first layer of the
deck, and began the painting process prior to installation. By the end of
the week, I had installed the sections around the stern.
Please click here
to read more about the process.
|
Log for the Week
Ending October 10, 2004
Over
the course of the week, I applied several coats of semi-gloss white paint to the
beadboard for the forward sections of the boat. After three finish coats,
the plywood was ready for final installation, which I completed Sunday
morning. The end result looked terrific from inside.
Click here
to see more.
|
Log for the Week
Ending October 17, 2004
A
couple days after securing the first layer of the deck sheathing, my next step
was to coat the surface with unthickened epoxy in preparation for the next
layer. I hot-coated the plywood with epoxy to promote better adhesion with
the epoxy putty I planned to use to laminate the upper layer of plywood.
Coating the entire surface required about 48 ounces of mixed epoxy, which I
spread using the standard West System foam rollers. I needed two to get
around the whole deck, as they fell apart rather quickly. Click
here for another picture.
|
Also
this week, I finally got rid of the remains of #100's deck, which had been lying
around for more than a year. The deck and old interior pieces (bulkheads
and other stuff) ended up in a 30-yard dumpster that I rented for the purpose,
as well as to get rid of lots of other stuff from around the house, shop, and
yard.
|
Log for the Week Ending October 24,
2004
This
week, I installed the top layer of plywood on the deck surfaces. I
installed the plywood in a troweled bed of epoxy adhesive, then screwed it in
place through the bottom layer and into the deck beams beneath. This took
the better part of a day and a half to complete, but at the end the deck was
smooth, solid, and rigid--and looked great! Click
here to read more about the decking.
|
Log for
the Week Ending October 31, 2004
Boo! Happy Halloween.
There is no progress to report for this
week. Also, there will be no updates for the next three Sundays, but look
for things to get on track right after Thanksgiving. Thanks for reading!
Continue
to November> |
|