Further 90

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

May 1, 2023

Further 90

Monday

Over the past few weeks since I finished the paint, the owners had installed some of the deck hardware, focusing on making the boat weathertight.  Now, with the boat scheduled to leave the shop soon, I removed a few last things from the boat and prepared her and the shop for the upcoming transport.

Meanwhile, I continued work on the new cockpit hatch, which wouldn’t be ready to leave with the boat but wouldn’t be far behind.  Now, I sanded the recent application of fine fairing compound, which did a good job filing the small pinholes, remaining fiberglass texture, and a few minor low areas.

After final preparations, I spray-applied several coats of light gray finish primer.

 

Total time billed on this job today: 1.5 hours

0600 Weather Observation: Heavy rain and wind, 48°, dew point 50°. Forecast for the day: Rain ending, then clearing in the afternoon, 62°