Further 9

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

December 22, 2022

Further 9

Thursday

As usual, I started the day with a round of sanding, now to scuff the new fiberglass and ease any hard edges.

After cleaning the area, I applied a coat of fairing filler over all areas, tapering it to the bottom edge of the sheer strake and, at the top edge, beginning to form a clean rounded edge to enhance and replicate the original molded character line.

I had a bit of time left in the day, so I continued work on the topsides, sanding most of the rest of the starboard side with a 6″ finishing sander and working through 60-80 grits.  I left only a smallish section on the counter that was too high to reach from the floor, and too low/far away to reach from the staging, as well as the uppermost portion of the quarter near the transom where there was fresh epoxy work.

Total time billed on this job today: 7 hours

0600 Weather Observation: 16°, mainly clear, dew point 15°. Forecast for the day: Mostly cloudy, 35°