Further 83

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

April 5, 2023

Further 83

Wednesday

I had various other requirements throughout the day, so only a little time for progress, but in a short afternoon had the chance to cut and install the  balsa core in the new cockpit hatch.  I’d originally thought I might install the bottom skin laminate at the same time, but ultimately decided it better to wait for a separate session.

Total time billed on this job today: 1.25 hours

0600 Weather Observation: Mostly cloudy, 36°, sleet showers, dew point 21°. Forecast for the day: Rain and sleet showers, then rain, sleet, freezing rain into the night, 36°