Further 75

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 25, 2023

Further 75

Saturday

At long last, the great unveiling!  With all the paintwork finally done, I could hardly wait to get rid of all the masking and see the boat in entirety for the first time.

Total time billed on this job today: 3 hours

0600 Weather Observation: Mostly clear, 21°, dew point 19°. Forecast for the day: Increasing clouds, 42°, ran and snow coming late in the day and overnight