Further 70

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 18, 2023

Further 70

Saturday

To recover from the paint disappointment, I spent time over the weekend lightly sanding the hull by hand (320), just to lightly scuff the surface and prepare it for respraying.  The killer of it is that the paint looked good except for the fact that the primer still showed through; the overall finish was what I’d hoped otherwise.  But that was good news too, as it meant that sanding was quick enough and straightforward, not that I didn’t wish it wasn’t necessary.

Afterwards, I cleaned up the hull and shop to prepare for respraying.

Total time billed on this job today: 4.5 hours

0600 Weather Observation: Foggy, 34°, dew point 34°. Forecast for the day: Fog, then gradual clearing, 48°