Further 48

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

February 17, 2023

Further 48

Friday

In a landmark day, I spray-applied three coats of epoxy high-build primer over the deck areas, starting with the inboard portions of the coachroof and cockpit, which areas I had to access from the nearby sidedecks, and then moving on to the main decks, cabin trunk, toerails, loose hatches and sea hood, and upper reaches of the hull-deck joint above the topsides.

Total time billed on this job today: 6 hours

0600 Weather Observation: Overcast, 39°, dew point 28°. Forecast for the day: Rain before 3 PM, then freezing rai and sleet and snow, temperature falling to 29°