Further 2

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

December 12, 2022

Further 2

Monday

From the inception of the project the owners had agreed to undertake the deck hardware removal and installation themselves, and true to form, they worked over the weekend to remove nearly all of the deck hardware.  This series of photos shows the results, and also documents the condition of the decks at the onset of the project.

0600 Weather Observation: 9°, partly clear, dusting of snow overnight, dew point 9°. Forecast for the day: Mostly cloudy, then clearing, 30°