Further 14

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

December 30, 2022

Further 14

Friday

In a short workday, I lightly sanded the small patches on the hull, this time using only a 4″ palm sander and 120 grit paper (or by hand).

A few of the spots required an additional application of epoxy filler, so as needed I cleaned and reapplied to several locations.

Preparing for an afternoon meeting with the boatowners and the canvas contractor, I removed some anchor chocks and other hardware from the sea hood, which hardware needed to be removed eventually anyway.  During the meeting later, the owners and I agreed that for the dodger’s sake, it would be best to remove the three raised ribs from the top of the hood, replacing their stiffening structure with some thin core and new fiberglass instead–since the front edge of the dodger would use a curved track to secure it to the deck, eliminating the raised sections would ensure that the dodger could follow the line it needed to.  More on this all later in the project when it happens.

Total time billed on this job today: 3.25 hours

0600 Weather Observation: 20°, fair, dew point 28°. Forecast for the day: Partly sunny, 43°