Further 1

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

December 6, 2022

Further 1

Tuesday

Further arrived at the shop in the late morning.  I’d cleared out the shop in advance, so it was ready for her to go right in.  The project would begin in earnest soon.

0600 Weather Observation: 38°, overcast, dew point 35°. Forecast for the day: Mostly cloudy, 48°