Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 21, 2023

Further 72

Tuesday

With the paint cured sufficiently overnight, I could remove the masking from the boottop and sheer strake, revealing a sneak peek at how the trim would ultimately look on the hull.  Other than some other minor prep work, however, this was all I could do for the moment, as the fresh paint had to cure further before I could mask over it to finish the trim, which was the next and final stage of the painting process.

Total time billed on this job today: 2.25 hours

0600 Weather Observation: Mostly cloudy, 28°, dew point 18°. Forecast for the day: Becoming sunny, 49°