Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 20, 2023

Further 71

Monday

After final preparations, I applied another three coats of zinc yellow paint to the hull.  This felt vaguely familiar, but fortunately the results were more in line with expectations this time.

Total time billed on this job today: 3.5 hours

0600 Weather Observation: Clear, 16°, dew point 7°. Forecast for the day: Sunny, 45°