Further 66

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 14, 2023

Further 66

Tuesday

Over the course of the morning hours, I sprayed four coats of epoxy finish primer on the hull.  For this boat, I mixed equal parts of white and gray primer bases to lighten the primer a bit, hoping it’d be a good base for the final hull color.

Total time billed on this job today: 4.5 hours

0600 Weather Observation: Cloudy, 35°, dew point 29°. Forecast for the day: Snow after 11, 6-10" forecast, 35°