Further 62

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 8, 2023

Further 62

Wednesday

After final preparations, I applied three sprayed coats of epoxy high-build primer to the hull.

Total time billed on this job today: 3.5 hours

0600 Weather Observation: Cloudy, 34°, dew point 26°. Forecast for the day: Mostly cloudy, 43°