Further 60

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 6, 2023

Further 60

Monday

I wanted to give the new decks ample cure time before I covered them in plastic for several weeks while I worked on the hull, so I’d planned an extra day for this purpose–this day, and I’d made arrangements to do other things in the meantime.  But I spent the early part of the morning removing all the masking tape from the decks before I departed.

Total time billed on this job today: 2.5 hours

0600 Weather Observation: Clear, windy, 34°, dew point 15°. Forecast for the day: Mostly sunny, 39°