Further 56

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

March 1, 2023

Further 56

Wednesday

After final preparations, I applied three coats of snow white gloss topcoat (LPU) to the deck areas, beginning once more with the inboard areas of the coachroof, along with the cockpit and cockpit well.  With three coats on all those areas, I could continue with three coats on all remaining deck areas and the loose hatches.

Total time billed on this job today: 5.75 hours

0600 Weather Observation: Clear, 13°, about 8" snow from overnight, dew point 14°. Forecast for the day: Partly sunny, increasing cl ouds, 39°