Further 52

Boat:

Further, a 1975 Ericson 35

Schedule:

Project Schedule:  December 2022 – May 2023

Project Scope: Hull and deck paint, structural repairs, and miscellany

Project Complete:  452.5 total hours

Begin Daily Project Logs

February 23, 2023

Further 52

Thursday

After final preparations, I applied three coats of epoxy finish primer over all deck areas.  As before, I started with three coats on the cockpit well and inboard coachroof areas–places I needed to reach from the sidedecks–then continued with three coats on all other areas thereafter.

Total time billed on this job today: 6 hours

0600 Weather Observation: Snow, 18°, about 3" down so far, dew point °. Forecast for the day: Snow, 19°