(page 2 of 6)

Aventura 46

< Back to Aventura

Monday

Over the weekend, I finished up the varnish work on the toerails, and removed the masking tape.  I also dismantled the staging to prepare for some boat shuffling in the near  future, as the remaining work could be completed without the boat in the center of the shop, and I needed the room for another boat.

Meanwhile, I continued work on the coamings.  To prepare for installation, I laid on a strip of masking tape to aid in marking,  and laid out the fastener holes required along the bottom edges of the coamings.  Then, I milled 1/2″ counterbores for bungs, and 1/4″ pilot holes for the screws.    With the coaming in the boat, I pressed it into place with my jack, and drilled and tapped the sides of the cockpit coaming to accept the 1/4″ machine screw fasteners.  At the winch islands and coaming return blocks, I bored bung holes and screw holes for the fasteners there.

Now I removed the coamings, and milled little countersinks at each fastener location before vacuuming up the drill spoils and preparing for final installation.  I applied a bead of brown sealant along the top edge of the cockpit, and at all the screw locations, then reinstalled the coaming and secured all the screws before cleaning up the sealant squeezeout.  I used enough sealant to prevent nuisance water from seeping into the cockpit beneath the coamings, and to seal the screw holes, but hopefully  not so much that coaming removal would be impossible in the future should be become necessary.

With the starboard coaming complete, I repeated the process on the port coaming.

At the aft end of the cockpit, I went through the same basic steps to install the two pieces of coaming trim there, and wrapped up the installation by installing the coaming caps on the molded return blocks at the forward ends.

With that work complete, I repositioned the boat to the front corner of the shop, leaving room in the back for another small boat and opening the other shop bay for my next project.  This gave me a chance to see Aventura in the open for the first time, however briefly.

With the yard move complete, I got back to work and installed teak bungs in all the coaming holes.  To wrap up the day’s work, I varnished the various loose trim pieces again, and finished up my fastener order as needed for the deck hardware installation.

Total time billed on this job today:  7.75 Hours

0600 Weather Report:
22°, clear.  Forecast for the day:  Sunny, low 50s (!).

Aventura 45

< Back to Aventura

Saturday

Hoping to wrap up the toerail work, I pressed on with another coat of varnish, bringing the total to a minimum of 7, though actually the buildup was more like 9 on most parts of the rail.

Meanwhile, I lightly sanded and applied a second coat of varnish to the back sides (the sides that would eventually rest and be bedded against the fiberglass cockpit coaming).

varnish12-120515

I finished up the interior fiddles with a coat of rubbed-effect satin varnish.

varnish1-120515

 

Total time billed on this job today:  1.5 hours

0600 Weather Report:
Mostly clear, 30°.  Forecast for the day:  Partly cloudy but clearing, high around 49.

Aventura 44

< Back to Aventura

Friday

Before getting to work on other things, I took the opportunity to test-fit the cockpit coamings.  As expected, I was required to make minor adjustments to the coamings so they’d fit properly in their spaces.  I was able to bend the coamings in by hand for this fitting, so I didn’t set up my jacking system, and the process obviated photo-taking.  In the event, the adjustments were minor and easily effected, and I was glad I’d simply moved forward with final shaping and sanding of the pieces after building them.

In my habitual way, continued by lightly sanding the toerails and brightwork.  Then, later, after final preparations, I applied another coat of varnish.

The main coamings were complete, but now I had to replicate the two smaller pieces that spanned the after part of the cockpit, as well as a pair of caps to cover the tops of the molded coaming return blocks.  To start, I had to plane down a short piece of teak, one left over from and which excess length I’d cut off the original coaming board blanks before I’d dimensioned that stock.  I planed the short piece to the same thickness as the coamings, or about 7/8″.   With the original pieces at hand, I duplicated them as exactly as possible.  Then, I copied the coaming block caps, choosing to use thicker material here as well.  After final shaping and finish sanding, I applied a sealer coat of varnish to the coamings and all the other pieces.

Total time billed on this job today:  4 Hours

0600 Weather Report:
28°, clear.  Forecast for the day:  Sunny, low 40s.

Aventura 43

< Back to Aventura

Thursday

The nonskid was complete, so I removed all the masking tape from the painted areas, but leaving it in place around the toerails and other brightwork so I could continue work there.

I lightly sanded all the brightwork–toerails, companionway, handrails, fiddles, and other trim–and, after cleaning and tacking off, applied another coat of varnish to all.

To fill a bit of time before lunch, I began going through the deck hardware to catalog the fasteners required for its reinstallation, and to clean up the hardware as required before installing it.  I’d continue this process over the next day or two.

hw1-121315

Later, I built the new cockpit coamings, using the originals as guides to shape the new ones from a pair of teak boards.  To keep things moving, after cutting out the new coamings, I decided to press on and edge-mill and sand the coamings even though I’d not yet test-fit them since the new deck paint and varnish work prohibited access to the cockpit at the moment.   I had good confidence in their shape, and in any event any adjustments would be at the lower edge and wouldn’t affect the sanding much.

 

Total time billed on this job today:  5 hours

0600 Weather Report:
35°, light rain showers.  Forecast for the day:  Occasional showers, around 40.

Aventura 42

< Back to Aventura

Wednesday

Continuing work on the deck and toerails, I got started by lightly sanding and cleaning the toerails, companionway, and handrails to prepare for the next coat of varnish.  With that complete, I took the opportunity to apply a coat of paint to the two lazarette lockers (well, one locker and one outboard well, if you must).  I used white Bilgekote for these lockers.

Next, I applied a second coat of nonskid paint to all deck areas.

Then, I applied another coat of varnish to the toerails, companionway trim, and handrails.  (Actually, I did the companionway first, while I could still reach it before the second coat of nonskid, but I’m showing it here.)

I had a small pile of original woodwork that I planned to restore and reuse, including the companionway swashboards, some minor companionway trim, and the tiller.  This wood was heavily weathered, but in otherwise sound condition.

woodwork1-120215

I cleaned up all the woodwork, and stripped any remaining old finish (mainly on the tiller) with aggressive sanding as required, then working through the grits to smooth and clean the surfaces for new varnish.

woodwork2-120215

After solvent-washing the raw wood, I applied a sealer coat of varnish to all pieces.

One of the key aesthetic features of the simple interior was a pair of long, thin teak fiddles that formed the shelves on each side of the boat.  I’d removed these early on in the project to allow access for the paint work in the main cabin, and although I wasn’t doing much varnish work in the cabin, I couldn’t leave the fiddles as they were.  The old finish was in poor condition, and had lifted in many areas, so I chose to refinish these pieces.    Accordingly, I stripped the old finish from the boards and sanded them clean and smooth before applying a sealer coat of varnish.

 

Total time billed on this job today:  6 Hours

0600 Weather Report:
35°, light rain showers,  Forecast for the day:  showers, high around 40.

Aventura 41

< Back to Aventura

Monday

The interior paint was complete, so I removed the masking tape.  Sometime towards the end of the project, I’d clean up the remaining interior areas to finish the work list there.

After trimming the bungs from the new toerails, and lightly sanding all the new wood, I masked the wood to prepare for the varnish coats.  At the same time, I masked off the glossy deck areas so I could move forward with nonskid paint, now that the toerails were complete.   At the stem, where I’d created a wider band of the glossy white paint, I marked a new 1″ border–to match the others–according to the contours of the stem cap, and sanded the area within to prepare for paint.

After final preparations and cleanup, I applied a coat of nonskid paint, a custom mix of beige and white (50% each).

Then, I applied a coat of varnish to the toerails, and to the handrails in the varnish room.

Total time billed on this job today:  5.75 Hours

0600 Weather Report:
15°, clear.  Forecast for the day:  Sunny, high around 30.

Aventura 40

< Back to Aventura

Sunday

Now that the stem and taffrail pieces were complete and prepared with a sealer coat of varnish, I continued with their final installation.  The taffrail was all set to go, as I’d prepared all the fastener holes during initial fitting, and installation went quickly.

To install the stem, I marked and drilled/tapped all the fastener holes, as usual, and with that complete I installed the wood in a bed of sealant.


Afterwards, I bunged the screw holes.

Finally, I applied a second coat of semi-gloss white enamel to the interior overhead.


Total time billed on this job today:  1.75 Hours

0600 Weather Report:
Clear, 12°.  Forecast for the day:  Sunny, high around 30.

Aventura 39

< Back to Aventura

Saturday

The holiday break had cut into my time earlier in the week, but I very much wanted to keep the toerail project moving along.  To this end, I worked for a while to build the new wooden stem pieces.  Using the old ones as a guide, and a paper template I’d made earlier, I cut two blanks from some teak stock I’d reserved for the purpose.    On the boat, I test-fit the blanks and made minor adjustments as required, recutting one of the edges that had started out slightly oversized.

Once I was satisfied with the fit, I sanded the blanks smooth, and rounded over the exposed edges where necessary for appearance and coating retention.

Finally, I applied a sealer coat of varnish to all surfaces, and left the blanks to cure overnight.

stem9-112815

 

Total time billed on this job today:  1.25 hours

0600 Weather Report:
Cloudy, 30°.  Forecast for the day:  Mainly cloudy, 40.

 

Aventura 38

< Back to Aventura

Wednesday

After some final preparations, I got back to work in the cabin, and applied the first of probably two coats of semi-gloss white enamel to the areas I’d primed earlier.  In these photos, the paint’s still wet, so it looks glossier than the final finish.

At the stem, I made cuts in the new toerails to accommodate the stem piece, using reference marks I’d made earlier, along with the actual old stem sections to confirm the positioning.    Then, I cleaned up the sealant that had been beneath parts of the rail ends, and made a pattern of the area to use in creating new stem pieces.

At the stern, I repeated this process with the taffrail, first cutting away the excess toerail, then patterning the areas using the original taffrail sections as a guide.

With the pattern cut out, I transferred the shapes to a piece of teak stock and cut out the raw pieces, leaving them a little oversized at the ends to allow room for some fine-tuning where they met each other on centerline, and also where they met the toerails at the new cuts.  Then, I test-fit the sections, one at a time, making adjustments as needed to first one section, then the other, before temporarily securing the pieces with screws (same fastening protocol as the toerails) to check the fit and make final notations for fine-tuning on the bench before final shaping.

Afterwards, I sanded the two sections, rounded corners where necessary, and applied a sealer coat of varnish, which I’d leave to cure before installing the new pieces.

Total time billed on this job today:  5.5 hours

0600 Weather Report:
15°, clear.  Forecast for the day:  Sunny, highs near 40.

Aventura 37

< Back to Aventura

Tuesday

I moved the staging back alongside the boat so I would work at deck height comfortably, and made final preparations for the toerail installation, collecting tools and so forth to be close at hand, and rigging various support and control lines that I’d need to act as my second set of hands as I manipulated the long rails into position.

At the stem and stern, I used the original wooden assemblies to make some reference marks on the deck so I could determine where the end screws in the new  toerail needed to be.  I also marked with tape on the hull and deck the original locations of the toerail scuppers, which locations I’d carefully maintained throughout the rebuild process; I’d mark the toerail in these spots once it was dry-fit, so I could make the notches before permanent  installation.  Finally, I made additional notations to mark the locations of the genoa track fasteners so I could ensure the toerail screws were staggered a safe distance away.

I had ample extra length available with the toerail blanks, and I chose to keep much of this at the bow, as the longer overhang would allow the rail to bend into position more easily:  the bow was quite narrow, with a strong curve required over the first few feet.  This also kept the second scarf joint well forward of the transom, and, as it happened, beneath the genoa track location.

Getting the toerail started at the bow, particularly with a strong curve and while working alone, tends to be a bit of a challenge, as the rail needed to be pre-bent while essentially unsupported, and then somehow fastened  in just the right place.  To start the installation, I adjusted the various control lines as needed to start the rail bending into shape, then, with the rail positioned at the deck edge where it needed to be right at the bow, I installed one screw near the stem, in a section of the rail that would later be removed to accommodate the stem piece.  This pinned the rail securely, and prevented it from twisting, as it had badly wanted to do.

Now it was relatively simple to mark the actual first fastener locations, just aft of the reference mark I’d made where the stem piece would later fit.  To help hold the rail end securely, I liked to install a pair of fasteners near the end, so I measured and marked the locations and prepared the holes, in a process I’d repeat over and over for each fastener in the rail:  first a 3/8″ counterbore to recess the screw head and accept a bung; then a pilot hole for the screw shank, just through the wood; then, with the rail held properly in its final position, a smaller pilot hole into the deck, followed by a pass with a 10/24 tap; and finally, a 10/24 x 1″ pan head machine screw.

After securing those first two critical fasteners, I could relax a little, but didn’t rest till I’d installed 6 or 10 more fasteners, spaced six inches on center, which got the rail past the most critical bend and safely secured.

I continued in this way to the transom,  adjusting screw locations as necessary to miss the eventual scupper locations and the genoa track fastener locations.  At the transom, I made sure the screws were safely on either side of the approximate taffrail location that I’d marked before, and, with the dry-fit complete, I marked the scupper locations on each side of the rail so I could make the cuts required once I’d removed the rail again.

Now I reversed the process and removed the rail so I could make final preparations for its permanent installation.  With the rail safely off the the boat (they come off very quickly and easily), I bored small countersinks at each fastener hole in the deck, to provide that little bit of extra sealant where it’s most important, and cleaned the decks of drill spoils and debris.

Meanwhile, working off the marks I’d made and with a section of the old toerail as a guide, I chiseled out spaces for drainage scuppers, in the same locations as original.  On other jobs, I often created these openings only after the rail was fully installed, but in this case, with the design and position of the vinyl rubrail prohibiting easy access, I chose to make them first, a process made that much easier by the fact that I had marked and maintained the original locations right on the vinyl rail throughout the rebuilding.

With all preparations complete, I installed the toerail in a heavy bed of brown-colored sealant.  To ease the issues at the stem, I started with one of the fasteners several down from the bow, now that their positions were already determined, and then worked my way back to the curvy stem before continuing aft, applying sealant and maintaining the rail in such a position as to avoid messing up the sealant.  I was overly generous with the sealant, which made cleaning it up on the outboard side–where the rail sat just inboard of the bulbous edge of the vinyl rubstrip–a fairly tedious and messy process, but before long the port installation was complete.  To wrap it up for now, I trimmed off the excess rail at stem and stern.

Wood makes such a dramatic and positive difference to any boat’s appearance, don’t you think?  I do.

I repeated the basic procedure chapter and verse on the starboard side.  The second side usually goes more quickly, in part because all the initial setup and prep is already done. and the appropriate rhythm well established.  I was a bit more reserved in my use of sealant this time, particularly along the edge of the rubrail, so cleanup was a bit more streamlined.

To wrap up the installation for now, I bunged all the screw holes.

 

Total time billed on this job today: 7.75 Hours

0600 Weather Report:
Clear, 18°.  Forecast for the day:  Sunny, highs in the 30s

Older posts Newer posts