Arietta Phase 2-3

Boat:

Arietta, a 1980 Cape Dory 22

Schedule:

Project Schedule:  October 2021 – December 2021

Project Scope:  Deck Paint (other than cockpit); miscellaneous maintenance projects

Project Complete:  194.75 Total Hours

Begin Daily Project Logs

November 3, 2021

Arietta Phase 2-3

Wednesday

With some time at the end of the day, my impatience got the better of me and I decided to remove the mast; I’d planned to wait till the bay next door was free in a few more days, at which time I could easily use the crane there to remove the spar, but after inspecting the situation and test-lifting the mast I decided it was light enough to remove safely by hand, which I did using a pair of ladders, eventually lowering the mast easily onto my rolling staging so I could move it outside and out of the way for the duration of the project.

Total time billed on this job today:   0.75 hours

0600 Weather Observation:  Clear, 30°.  Forecast for the day:  Mainly sunny, 5o°