Luna Mia 13

Boat:

Luna Mia, a General Boats Rhodes 22

Schedule:

Project Schedule:  February 2022 – (Ongoing)

Project Scope: Patch and repair existing saildrive hole; hull paint; sundry minor repairs

Project Complete:  72 Total Hours

Begin Daily Project Logs

March 18, 2022

Luna Mia 13

Friday

I spent the morning sanding the hull primer, now with 320 grit as the final stage before topcoat.

Afterwards, I cleaned up the shop again via compressed air, vacuum, sweep, and rinse, then vacuumed and solvent-washed the hull to better inspect it and prepare for the next steps, which I’d continue next time.  There’d be a few areas to touch up the sanding (for example, I missed the narrow spot above the upper gudgeon), along with marking and masking for the boottop and other things required to prepare for the gloss topcoats.

Total time billed on this job today:   4.25 hours

0600 Weather Observation:  35°, foggy.  Forecast for the day:  Foggy, becoming mostly sunny, 63°