(page 57 of 165)

Lyra 68

Monday

Since last time, in the background, I’d continued work on the trim/fiddle for the engine room countertop.  With a coat of varnish on all parts of the trim, I glued it to the leading edge of the countertop, avoiding screws here since there was only the edge of the 1/2″ plywood to accept fasteners.

Once the glue had set up, over a few days I applied three additional base coats of gloss varnish, followed by a final coat of satin varnish.  In addition to finishing off the forward edge of the countertop (the owner would later install additional pieces to complete the trim from the stock I’d milled), the new fiddle provided a handy handle for pulling out and removing the top of the engine room.

The sink had also had plenty of cure time, so I could remove the clamps and weight to complete the installation.

My first and main focus for the week and the balance of my time on this job was to install the ports and deadlights, which the owner had been cleaning up, replacing glass, and repairing.  With these freshly delivered to the shop (minus two of the small ports for now that he hadn’t finished yet), I got started with the deadlights, which required some pre-work before actual installation.

To make installation somewhat easier (read:  possible), I liked to pre-install the lenses (new 1/4″ laminated glass in this case) to the outer frames, to hold those pieces together during the installation process.  I used a sumptuous bead of Sikaflex to secure the glass to the rabbeted channel in the outer bronze frame, pressing the glass in securely (through the clear glass it was easy to see the sealant spread) and then, more to hold things in place than to provide real pressure, clamped the glass beneath a strip of wood.

I repeated this with all four frames.

Those would sit in the clamps for a couple days to allow the bedding to fully cure, so now I turned to the small, opening ports.  The owner had found two of the later-model Pearson opening ports to replace the older ones in the forward face of the saloon, so the original openings were too small and required modification.

I made a cardboard template of the new ports so I could create accurate cutouts for the spigot and fixing ears cast into the port body.  I centered the pattern over the old openings–this looked best and made the most sense here–and cut to the new line so the new ports would fit.

Satisfied with the dry-fit (I had to enlarge the first one I cut–the port side–as the template was a bit tight; I adapted for the starboard side and had a good fit the first time), I finished the installation with sealant and new screws, beginning on the port side.  I applied sealant around the inside edge of the spigot, and also around the perimeter of the frame (and out beneath the trim ring) once I had the body positioned in the opening.

The owner had provided new 8 x 1/2″ bronze screws for the job, but the cabin trunk here in particular was much thicker at the bottom than at the top–as in 3/16″ at the top and over 1/2″ at the bottom, so these screws were too long at the top and too short at the bottom.  Fortunately, this wasn’t my first Triton rodeo, and although it had been more than 10 years since I last installed these types of ports, I had on hand a full selection of lengths of #8 bronze machine screws, running the gamut from 1/4″ to 3/4″ (and beyond, though the longer ones weren’t applicable here).

On this port, I elected not to remove the opening portion (secured to the body with two screws), and this greatly complicated the installation, at one point early on nearly causing the whole unit to drop out the back before I had any screws started.  I saved it by reaching through the gooey opening, but recovery efforts were long and tiresome, and I was sure to gravely note the lessons learned so I could apply them to the next installation.

I ended up using a variety of lengths from 3/8″ t0 5/8″ on the port port, using a clamp as needed to help pull the frame tightly to the inside of the cabin so I could get screws started through the trim ring.  With the first installation eventually complete, I cleaned up the excess (and overly messy, thanks to my drop-out port) sealant.

Wiser, I continued with the installation on the starboard side where, thanks to the port side lessons, the installation took a fraction of the time.  Here, I removed the opening part of the port, making the body much easier to handle.  And I was far better prepared with the screw lengths that I needed and were likely to work (on this side, I needed the tiny 1/4″ length for the top screws).

With dwindling time on the day, I finished up with some advance preparations for the installations of the next two (and, for now, final two) opening ports, which would both go on the starboard side forward (head and v-berth).  These ports were also mis-matched, with one of the old Pearson style, and one of the newer style like the pair I’d just installed.  In any event, now I cleaned up the remnants of the old sealant on the cabin sides and made other preparations to streamline the installation next time.

This left me just enough time to remove the protective paper from the forward hatch, since I was there and it was almost time for the boat to depart.

Total time billed on this job today:  5.25 hours 

0600 Weather Observation:  45°, mainly cloudy.    Forecast for the day:   Cloudy, chance of sun, 58°

Lyra 67

Wednesday

The adhesive securing the countertop had sufficient cure time overnight, so I removed the wedges and weights in order to continue work on the countertop.

Next, I installed the faucet, sealing the base with butyl tape to prevent any stray water on the countertop from seeping through the mounting hole and securing the faucet tightly with its fixing nut.

Though there was reasonable access to the underside of the faucet from the locker just behind it, I thought it’d be nicer to pre-install a length of water hose while access was wide open.  The foot pump, and standard size for water fittings in boats of this sort, was for 1/2″ hose, but the faucet had a hose connection designed for either 5/8″ or, further up, 3/4″ hose, which I discovered when I tried to install the 1/2″ hose.  So instead, I installed a shorter length of 5/8″ hose, which would have to be reduced down to 1/2″ for the pump and the water tank outlet itself.  I didn’t have a reducing adapter on hand, so that would have to wait.

The the nearby bulkhead beneath the faucet pinched the hose more than I liked, so I created another relief cut in the bulkhead to allow the hose to run freely down from the faucet connection.

Next, I installed the sink in a heavy bed of sealant, which would secure and seal the sink in place.  Before doing so, I cut the drain hose to the proper length, secured the lower end to the hull outlet, and, while installing the sink, aligned and installed the upper end at the sink drain.  I filled the sink with heavy things and, needing some additional pressure to flatten and secure the flange, made up a clamping block that pulled things down as needed.  All but the final photo in this series show the sink before final sealant cleanup; somehow I have only the single photo after cleaning up the squeezeout completely.

To help overcome my error on the engine room countertop, I volunteered to make up some trim to cover that edge, and, at the same time, for the remainder of the galley as well.  After agreeing with the owner on a profile for the trim, I milled 8/4 sipo into two planks 3″ wide and just over 3/4″ thick, then planed them down to their final 3/4″ thickness.  To create the fiddle profile, I rabbetted out a 1″ wide by 3/8″ deep section at the bottom of the trim, which would overlap the countertop and hang down the front edge to cover the plywood, then milled a roundover on the remaining three edges.  For the engine room countertop itself, I cut off a 2′ long section, then slightly shortened the overhang at the front edge so the trim just covered the plywood, or about 9/16″ rather than the 1″ overhang on the remaining pieces.

Afterwards, I sanded the new trim smooth, and cut the engine room piece to the proper length, with angled corners since this countertop piece would be removable and the trim couldn’t properly conjoin its counterparts on the sides, once fitted.  Then, I applied a sealer coat of varnish to all sides of all pieces.  The owner would later do the final fitting and finishing of the fiddles on the fixed countertop sections, though I planned to complete the engine room piece myself.

One of the “if there’s time” projects on my dwindling list was to install shelf supports running forward from the galley on each side of the hull, much like the old, original shelf supports further up the hull (now obsolete).  Since I’d be away from the shop for the last couple days of this week, and with only a few work days remaining for me on the project (a couple of which would be dedicated to reinstalling the ports and deadlights that the owner had been cleaning up and preparing), I thought I still might have time to install the supports, so to that end I made up a core blank from some scrap 48″ x 6″ x 3/4″ Corecell foam I had on hand, overlapping pieces and seams, and gluing them together with epoxy and temporary screws to create an oversized blank roughly 6″ wide and 1-1/2″ thick, and 7′ in length.  From this, I planned to mill the roughly square pieces required to form the supports (and thereafter glassed over).    To complete this project, I’d need to lay out the rough position of the supports, grind off the paint on the hull, mill the cores to size and shape, epoxy them to the hull, then glass over to fully secure.

Later in the afternoon, the ring pulls I’d ordered for the galley hatches arrived, so I could finish that up.  These ring pulls required a round recess, which was more straightforward to create than a square one, particularly in high-pressure laminate.

Total time billed on this job today:  3.25 hours (plus 2.25 unbilled hours)

0600 Weather Observation:  42°, mainly cloudy    Forecast for the day:   Partly sunny, chance of showers, 64°

Lyra 66

Tuesday

I spent a surprisingly long day working on the countertops, starting with the two larger sections for which I’d already cut the laminate sheets to rough size.  Now, I prepared a work station with a soft cloth to help protect the laminate surface, then, after cleaning both pieces of laminate and the two plywood countertops, applied contact cement to both pieces. I’d previously aligned the plywood with the wavy pattern on the laminate itself, and traced the outlines on the back of the laminate, so I’d be able to align things properly once the contact cement was in place.

Once the first coat had dried on the plywood, I applied a second coat to the porous material to ensure good coverage.

I milled up some scrap plywood into narrow strips that I used to position the plywood above the laminate before removing them one by one to press the plywood into position accurately against the outline marks I’d made earlier.  Then I rolled the laminate tightly into position from both sides.

Afterwards, I trimmed the excess laminate with a router, leaving the sink and access holes for now.

Hoping to do my best to align the laminate pattern between the two main countertop panels and the center, removable engine room panel, I’d waited on laying that one out till the first ones were complete.  Now I used the port countertop to help align the laminate on the engine room panel and, with the laminate clamped in place, overturned the panel and traced its outline on the back of the laminate before going through the contact cement application and installation as before.  When I trimmed the excess laminate with my router, I had an issue at the front of the panel.  I’d purchased a new trim router for this job since my old one had died, and as this was my first time using the new tool, at first I thought the adjustment had been off, allowing the bit to cut into the front of the panel.  This was an annoying error, but minor enough that the inevitable trim piece or fiddle required for the front of the engine panel would cover it.

Meanwhile, I continued work on the two larger countertops, first using the router and trim bit to open up the various openings (access hatches and sinks), then using small pieces of the laminate over the three access hatches to align the pattern so the hatches would match their surrounds.  With slightly oversized pieces of scrap or offcut, I could move the laminate around till it aligned with the wavy pattern, then carefully remove the hatch and laminate together, without moving things, and mark the outline of the hatch for later alignment.

Afterwards, I applied contact cement and, when appropriate, installed and rolled the laminate onto the hatches, then trimmed the excess.  Here again, my router had an issue and flubbed up one of the hatches, badly enough that I had to cut a new hatch from leftover plywood and go through the laminate process again (not included in the day’s total).  This time, I figured out what was happening with my as-yet unfamiliar router:  The bit hadn’t been properly tightened in the collet and was slipping out while in use, eventually to the point that the guide bearing dipped below the edge of the plywood, causing the error.  Fortunately this mistake, though it happened twice, happened only in recoverable areas, and taught me something about the router too.

I test-fit the sink, and the owner and I consulted on the location for a large brass hand faucet he wanted to use (to be connected to a foot pump or electric pump, not used with the hand pump).  The owner chose the corner location, which looked good and worked well with the access hatch behind, so with this confirmed I cut the hole required for the faucet. The faucet neck and fixing nut cleared the nearby hatch support cleat.

Then, I test-fit the countertop in the boat.  Both port and starboard sections were a good fit with their new laminate–I’d built in extra space beneath the plywood aft bulkhead to allow for the thickness of the laminate.  The engine hatch fit well, and the patterns were aligned enough on both sides.

But I discovered that the faucet hole ended up right over the little divider bulkhead beneath the starboard counter, something I’d not thought about.  That said, this was going to be the case regardless of its position:  it’s simply where it ended up based on the size of the sink and the predetermined position of the bulkhead.  This was a straightforward fix:  I cut out a portion of the bulkhead to provide generous room for the faucet and hose connection.

Happy with things, and after convincing myself that there was nothing else needing to be done inside these lockers, I went ahead with the final countertop installation.  I used 5200 fast-cure for this, applying smallish beads to the countertop edges, hull, and hull supports all around:  not too much, as I didn’t want it to squeeze out all over, but more than ample to secure the countertops.  As needed, I used braces, clamps, and weight to press the counters into position tightly.  I put the engine hatch into place in the center to ensure that both sides of the main countertop were in their proper positions as the adhesive cured overnight (after making sure there was no adhesive oozed out into the engine top supports).

Total time billed on this job today:  6 hours

0600 Weather Observation:  37°, clear.    Forecast for the day:   Sunny, 65°

Lively Heels Phase 3-46

Monday

The new covers for the pilothouse skylight and anchor windlass were complete, and the canvas contractor finished up their installation.

0600 Weather Observation:  35°, partly cloudy.   Forecast for the day:   Mostly sunny and windy, 50°

Back to Lively Heels>

Lyra 65

Monday

With my part of the project wrapping up and the boat scheduled to be moved soon, I turned my focus back to the interior and the galley countertop.  The new laminate the owner ordered had arrived, and now I could finish up the countertops and their final installation.

First, though, I needed to cut some access hatches.  Several weeks previously, I’d made some reference marks to show the centers of the battery boxes, for eventual top-access hatches required to remove the battery box lids and, if necessary, service the wiring connections or detach things should the batteries need to be removed.  Now, I laid out what seemed to be a reasonable hatch size, 12″ x 6″–large enough for access, but no larger than necessary either.  I cut out the hatch openings with a jigsaw.

I’d laid out the galley sink cutout earlier as well, and now I made the cut.  Then, I test-fit the starboard countertop in the boat to check the sink location, measure for the drain hose, and confirm that the battery access hatches performed as and provided the access needed.

Satisfied with the fit, I prepared some hardwood blocks to support the countertops where they met the hull on both sides.  I’d previously marked the correct height and prepared the hull by removing the paint in the general area, and now I glued the blocks in place with epoxy and a dab of hot glue to help hold them while the epoxy cured.  There was no need for full-length cleats here, and installing those would have been substantially more effort for no gain.

To finish off the new hatch openings, I milled, cut, and installed with glue and screws hardwood cleats around each opening from the bottom.  The owner and I collaborated on a final hatch in the starboard countertop to afford access to the large storage area outboard of the sink and battery storage areas, which I eventually laid out outboard of the sink, leaving room for a future upper cabinet against the hull.

With the countertops and hatches prepared, next I laid out the laminate for the countertop.    The chosen material had a wavy pattern of faint, but discernable, lines running through, and this pattern meant that I had fewer options in laying out the pieces than I would with a solid color, as the waves had to be consistent from section to section.

There wasn’t enough length to the piece of laminate to allow me to lay out the three sections of countertop (port and starboard, plus the engine room cover) with the pattern running athwartships, which was probably just as well since keeping the pattern aligned between sections would have been tough.  So this meant that the pattern needed to run fore and aft, which have me more options in terms of laying out the countertop sections to maximize use of the available material.  With laminate shears, I cut sections of laminate slightly oversized for each section of countertop, and ensured that I had adequate offcuts/scrap with which to make the three small hatches.  The pattern direction was crucial on the hatches, so I drew on the plywood accordingly.  I expected it would prove to be a challenge to align, at least remotely well, the wavy pattern on the hatches with that of the parent countertop, but that was a problem for a little later.  This all left ample material leftover for a future countertop in the space opposite the head.

At this point I was ready to permanently install the laminate.  Alas, my plans were stymied when I found that both cans of contact cement I had on hand were hardened and dried out.  Rather than waste what was left of the afternoon getting the replacement cement right away–there’d not be time to do the gluing once I returned–I made plans to go after work and instead turned to the final hardware installations I needed to do.

Over the past few days, I’d finished up the varnish on the anchor roller support block (six in all), and now I could finish up the installation.  I prepared a backing place from fiberglass laminate, then installed the roller with sealant and 3/8″ bolts, nuts, and washers.

Finally, I installed the long-awaited chainplate cover for the backstay, applying ample sealant around the opening and pressing the cover in to place.  I’d trim the excess later, once it cured.

Total time billed on this job today:  7 hours

0600 Weather Observation:  35°, partly cloudy.   Forecast for the day:   Mostly sunny and windy, 50°

Lively Heels Phase 3-45

Friday

With the project at an end, and great weather that had continued for several weeks–and looked to continue more or less going forward–it was time to move Lively Heels back outdoors, where her owner could take care of his annual commissioning tasks before the boat was picked up here in a couple more weeks.

Total time billed on this job today:  1.5 hours

0600 Weather Observation:  35°, mostly cloudy.   Forecast for the day:   Sunny and windy, 56°

Lively Heels Phase 3-44

Thursday

With the extra materials I needed, I finished up work on the laptop desk for the pilothouse.  With a short 3/8″ screw, I secured the rubber clamp beneath the table, and with a 1-1/4″ (70mm) M6 knurled screw to replace the original screw, the clamp became easy enough to install and remove without tools.  This concept worked, but left the desk at a slight forward angle.

To allow the desk to sit more level, and be better supported by the console at the forward edge, I milled a strip of cherry 1″ wide on the short end, with a bottom angled to match that of the console.  I secured this to the front edge of the desk with screws.  This helped, but to further enhance it, I added some flexible rubber beneath the wooden support, which not only raised the desk just a  bit, but cushioned and stabilized the desk against the console.  With the cushioned wheel clamp in place, one could turn the wheel just slightly till the action essentially forced the desk more firmly into position, creating a pretty decent platform that was easy to install and remove, and satisfied the core job description.

My main complaint was that the wheel clamp was a bit harder to install than I would have liked, since the longest knurled hand fastener I could find was only just long enough to allow the clamp to spread open without removing the screw completely.  A different type of hand screw might be available that could give the extra length desired.

If nothing else, this sort of Beta version, using the existing desk, could serve as a way to refine the concept going forward.  While the owner and I discussed building from scratch, ultimately he decided that it was worth using the existing, modified table to see whether any refinements were necessary.

With work wrapped up, and a transport date only a few weeks hence, I unloaded my tools, lighting, and the like from the boat and cleaned things up before making other final preparations to move her outdoors in the immediate future, so the owner could finish his pre-launch chores.

Total time billed on this job today:  1.5 hours

0600 Weather Observation:  30°, snow shower.   Forecast for the day:   Snow and rain showers, then cloudy, windy, 42°

Lyra 64

Thursday

Now that the backing plates were ready for installation, I could finish up the main halyard winch and cleat on the cabintop.

I continued with a third coat of varnish on the anchor platform block.

Next, I installed the stanchions in their bases.  Each required two #8 screws to secure it through the base and into holes tapped in the stanchions.

I was still awaiting the cover plate I’d ordered for the backtstay chainplate, but the sealant securing the four main chainplates was cured now and I could trim and clean up around these bases.

Total time billed on this job today:  1.75 hours 

0600 Weather Observation:  30°, snow shower.   Forecast for the day:   Snow and rain showers, then cloudy, windy, 42°

Lyra 63

Wednesday

To install the anchor roller, I needed a spacer block to equal the height of the molded gunwale and small stem platform, on which block the end of the anchor roller would be supported and through which it would be bolted to the deck.  With a piece of sipo cut slightly larger than I needed, I marked the rubrail height and trimmed the thickness down accordingly.  Then, I scribed the curved shape at the end of the stem and cut this out so the block would follow the contours.  After some additional test-fits and adjustments, trimming to final size, and rounding over the exposed corners, I ended up with the block I needed.

I held the block back enough from the stem that there’d be room for air and water to pass in front of it, then marked and drilled the three holes required for the anchor roller.   Afterwards, I marked the deck with tape for future positioning and for eventual installation.

After final preparations, I applied a sealer coat of varnish to all sides of the block.  By late in the day, the thinned coat had cured sufficiently for me to install a second coat all over as well.

While laying out the anchor roller, I also determined the locations for the bow chocks, and afterwards I installed these with new bronze fasteners.

The main halyard winch and its cleat required backing plates, which I made up from some 1/4″ fiberglass.  Since these would be highly exposed in the main cabin, I painted them to match, applying two coats over the course of the day.  Final installation of the hardware would come later, once the backing plates were ready.

For now, though, I could install the turning block at the forward end of the coachroof, using three #10 machine screws.  The two holes at the center of the sheave were too close for anything but the silly little standard #10 washers, which are barely larger than the nut, if at all.

Armed with some genoa foot-length measurements from the owner, I confirmed the position of the genoa tracks, more or less as I’d laid out; the sheet leads would be somewhat aft of the lengths, so I left plenty of track for that while allowing room forward as well, for reefed or smaller sails.

I held the forward end of the track far enough aft of the stanchion base to allow cars to be installed or removed from that end (there was plenty of room at the aft end), then dry-installed the track along the gunwale, curving it in place to follow the shape of the deck.  With three drilled-and-tapped fasteners holding the shape, I drilled out the remaining holes, then, with the track removed, finished the tapping and other preparations.  Then, I installed the track in a bed of sealant, remembering to slide on the lead car before I installed the removable end stops.

On the starboard side, I positioned the track accordingly, 4″ aft of the stanchion base, and laid out the curve dry in the same way.  In marking and drilling the remaining holes, I also had to slide the plastic end caps in place so I could drill their fastener holes.  These little caps, which slide around the leg of the T-shaped track, are often tight fits with the track installed, so with some issues getting the cap in place at the aft end I first loosened the temporary screw there, to no avail, then removed it completely so I could fit in the end stop.  An apparent molding error in the plastic piece meant that it simply wouldn’t go, so I trimmed it a bit with a knife and finally slipped it over the end of the track.

Here I made a stupid mistake. Happy to have the end cap finally in place after cursing its ill-fitting cheapness, I drilled the remaining bolt holes (the ones between the three screws holding the track in place)–except I’d removed the after screw to fit the end cap, and had forgotten to reinstall it, so the track was running straight from the central screw, rather than curved along the rail.  This meant that the holes aft of center were in the wrong place, further outboard than they should have been.  Since I’d been drilling from bow to stern, I hadn’t noticed the mistake till the last hole.  This displeased me.

The only thing for it was to fill the mistaken holes with epoxy, which I did immediately, then set some heat lamps in place to cook the epoxy during lunch break.  Fortunately, the track would hide most of these filled holes, but a couple at the aft end would require touch-up.  Also fortunately, at least this was in an area of the deck slated for future refinishing rather than one that I’d just refinished.  So the errors in my ways would be expunged during the next phase of the project.  In any event, I deducted time from the day to make up for the foolish mistake.

Later, with the epoxy cured enough to move on, I repositioned the track properly and redrilled the after holes, then finished the installation with sealant, nuts, and washers.  Only the after couple holes were visible (just) once the track was in place, and I planned to touch them up with some of the old deck paint on hand from the former refinishing project a decade before.

The owner had, during the previous summer, installed new stainless steel rubrail around most of the hull, but small sections at the quarters required rail installation, along with the transom.  The transom piece, which was curved to fit, had come from another boat, while the side pieces were new and required trimming to fit.

Dry-fitting each side in turn, I determined where to cut the rubrail, then installed the trim pieces afterwards to finish up the perimeter of the hull.

Total time billed on this job today:  6 hours (after time subtracted)

0600 Weather Observation:  40°, mostly cloudy.   Forecast for the day:   Clouds, showers, and eventually rain, 54°

Lyra 62

Tuesday

In the cockpit, I finished up with the installation of the starboard sheet winch.

Just aft, I installed a cleat for the roller furling line on a little pad that was already drilled for the cleat base (shown before cleanup).

I spent a good portion of the day working on the various installations on the poop deck, starting with the mooring cleats.  Using old holes leftover from their previous installation, I installed these on each side with new fasteners and backing plates.

Next, I installed the stern chocks and a flagpole socket on the taffrail.

Since I was in the area, I remembered to bed and permanently install a through hull fitting for the bilge pump the owner had dry-installed on the starboard counter.

Now that the taffrail modification/repair was complete I could proceed with the final layout and installation of the stern pulpit.  I started by centering the pulpit and getting the two aft bases where I wanted them, then secured each with a single screw for now through newly-tapped holes.  Once the center of the pulpit was temporarily secured, I could lay out and mark the two forward bases, then remove the pulpit and drill, tap, and prepare all the fastener holes.

Afterwards, I installed the pulpit fully with new fasteners, sealant, and fiberglass backing plates, along with the plastic spacers I’d made for the forward bases.  It would have been easier to install the forward bases before the locker lids were in place as I’d originally planned, but so goes the flow of a project; as it was, it was somewhat challenging to reach around the lids and under the deck to hold the fasteners and tighten the nuts below, but possible, if messier and slower than I’d like.

On the cabintop, I laid out for a main halyard winch, cleat, and turning block, following the owner’s chosen configuration.  This part of the deck had not been previously repaired, and around the still-open bolt holes leftover from another hardware installation (where I planned to install the cleat), and a little bit forward, I found dark core when I overbored the fastener locations to fill with epoxy.  The core was partly stained at the after winch holes, but clean at the forward holes.  Further forward, where I prepared the holes for the cheek block, I found clean, good core.

In any event, after preparing all the future fastener locations with a 1/2″ bit, and masking the adjacent areas, I filled all the holes with a thickened epoxy mixture, leaving it to cure before continuing.

With new 48″ genoa tracks now on hand, I began to plan their installation.  First, I had to clean up the decks on each side to give a reasonable bonding surface.

The tracks would be mounted outboard, near the gunwale, and the only lingering question was their fore and aft placement.    On several sisterships I worked on previously, I’d installed identical 4′ tracks generally towards the forward end of the space between the center and after stanchions on each side, which placement worked well and afforded enough adjustment room  for the typical genoa size of 120%-140%.  Three iterations are shown below.

I proposed a similar location for Lyra, with the track aligned roughly as shown, but for the moment it was late in the day and I awaited input from the owner before I proceeded.

Total time billed on this job today:  6.5 hours

0600 Weather Observation:  32°, clear.   Forecast for the day:   Sunny, windy, 67°

Older posts Newer posts