(page 56 of 166)

Arietta Phase 2-5

Friday

Now that the staging and other setup was complete, I could get into the early stages of the project for real.  I began by documenting the existing condition of the decks and hardware, for my own reference later, and for posterity otherwise.  The decks were original, with the usual minor and expected cracking here and there at the corners and in the main parts of the deck.  I didn’t anticipate the need for any real repairs, though there’d be a fair bit of crack mitigation.

I wasn’t ready to crawl up in the nether regions of the bow just yet–where I normally tend to start my hardware removal–so this time I began at the stern.  The owner mentioned that the oarlock, as installed last year, didn’t allow him to properly use a sculling oar since the angle was too acute given the orientation of the mounting block and the oarlock installed.  He requested that I reinstall the block, and the oarlock itself, at an angle approximating that of the transom, to better give him the sculling orientation he needed.  So to begin, I removed the oarlock and its mounting block, setting it aside for later attention.

Next, I removed the stern pulpit, as the forward two bases were located in the part of the sidedeck I’d not worked on last time (the poop deck and environs had been part of last year’s work that included the cockpit and hull).

I hadn’t planned on getting into this just yet, but sometimes the stream of consciousness method takes hold.  My attention was drawn to a couple screws in the toerail adjacent to the stern pulpit:  Another of the small projects the owner had requested, if possible, was to deal with the various (17, as it happened) screws in the toerail that had, over the years, lost their bungs.  Since the wood was in good shape all around and given its age, repairing these screws and bungs seemed a good option versus replacing all the exterior wood.  Earlier in the project, I’d gone around the boat and marked with tape all the screws requiring attention.  I’d planned to get around to these later, but since I was in the area and staring at three such screws at the aft end of the port toerail, I thought I’d go about seeing what the prospects were.

The exposed screw heads were covered with a lot of the toerail finish, but were easy enough to engage with a screwdriver–just a hand driver, as I didn’t want to strip any screw heads–and remove.  I started with a single screw as a trial, but once it was out (and with ease), it just seemed to make sense to bang out this little project now.  So, one screw at a  time (to avoid disturbing at all the bedding of the rail with the deck), I removed the screws, cleaning out the remnants of the bunghole as needed and carefully extracting the screw.  Then, I used a 3/8″ Forstner bit to drill a deeper hole for the screw and a new bung, and reinstalled the screw after dipping it heavily in some brown sealant.  I finished each hole with a new teak bung, counting on the excess sealant I made sure was in each hole to secure the bungs.

And in such fashion I worked my way up the port rail, then down the starboard side, repairing all 17 locations.  Later, once the sealant had cured sufficiently, I’d return and pare off the bungs, and dab on and build up some finish so that annual toerail maintenance in the spring would finalize and cover all the new bungs.  Each screw typically only took about two minutes start to finish, though a few required more effort to clean out the heads, and more finesse to remove without damaging the surrounding finish or wood.

With this small job checked off, and now back on hardware detail, I continued working forward, turning next to the cockpit winch bases.  Before removing the winches, however, I used some tape to strike a line between the port winch (at the inboard side of the drum where a line would lead) and the old bullseye fairlead in the sidedeck, which up till now had served as the lead for the working jib.  The owner wanted to install short tracks in its stead, but we also had to ensure that the line leads from the various positions of the track would line up with the winch without chafing on the coaming along the way.  The tape approximated the path the line would lead between the existing bullseye (which would demark the aft end of the new tracks) and the winch, so I’d have this for reference later.  I also struck a second line of tape, this one led as far inboard as it could go while maintaining a fair lead aft, past the coaming, and to the winch drum.

Between these two marks, somewhere, was the sweet spot for the new tracks’ position, which detail I could finalize a little later; I mocked up a couple things and took some measurements that I’ll get into more in the immediate future.  For now, I had enough information on the decks to proceed with the winch removal.  (I didn’t need to repeat this process to starboard, since on that side, with the line leading to the outboard edge of the winch drum, there was sufficient clearance regardless, so I could simply replicate the final track position as determined to port).

The winch bases had a single bolt passing through the sidedeck, which was accessible from beneath at the aft ends of the quarterberths, and removal proved to be no problem.  Two additional screws secured the bases to the coamings, and after removing these both winches were out of the way.

Continuing forward with all the “easy” hardware, I removed, in turn, the bullseye fairleads, anchor hawsepipe, a little fairlead up near the bow pulpit, the bow cleat, and, finally, the mast step and wiring bases nearby, bringing me to the end of the day.

Total time billed on this job today:   4.75 hours

0600 Weather Observation:  Clear, 25°.  Forecast for the day:  Sunny, 48°

Skeedeen Phase 7-8

Friday

Jason was back this morning with the completed winter cover, which we installed successfully and with ease.  The fit was excellent, though–not seen here–Jason insisted on taking back the forward section so he could install zippers on each of the slots around the bow pulpit bases, which was a nice addition and really brought together the forward end of the cover.  (It’s done and I didn’t photograph that stage.  We’ll see detail on that later, once the boat is outdoors and fully buttoned up).

Now that the cover was complete, I had to remove the aft section, as well as move two of the frame braces, to leave enough room for the mechanic to come do his engine maintenance and winterizing chores in a couple days, after which I could complete the cover for good.

Total time billed on this job today:  1.75 hours

0600 Weather Observation:  Clear, 25°.  Forecast for the day:  Sunny, 47°

Skeedeen Phase 7-7

Thursday

In a short day, I finished up the brightwork maintenance by reassembling, then reinstalling, the companionway hatch and doors on the boat.  Jason was also at the shop for a quick test-fit of the winter cover, which fit well but he’d left some of the grommets uninstalled as he’d wanted to be sure of their placement first, so after confirming the fit, he returned to his shop with the cover to finish these final details, and would be back the next day for the final installation.

Total time billed on this job today:  1.5 hours

0600 Weather Observation:  Clear, 26°.  Forecast for the day:  Sunny, 46°

Arietta Phase 2-4

Thursday

The first step in any project is some basic setup and prep, and here I started with the cockpit, which I’d repaired and painted a year ago and wouldn’t be getting any attention now.  However, to protect it during the adjacent deck work, and the ins and outs through the companionway while I removed hardware and performed other tasks, I covered the sole and seating surfaces with protective plastic designed for the purpose.

Most of the work would be at deck height, and now I set up staging around the boat to improve access.  I had to work out some optimum spacing and use of my various horses and planks, slightly complicated by the bulk of the trailer, and ultimately found I needed to remove the loading guide supports at the aft end, as they protruded too far and prevented the staging planks from being where they needed to be–and these steel bars would also be a constant headache for snagging cords and hoses.  I made reference marks to register the guides’ positions, then removed them for now.

Afterwards, I could finish setting up the staging planks around the boat, getting everything just right for safety and to ensure the right distance from the boat in all areas for access and to avoid being too close.  I secured all the planks with little L-brackets and screws to prevent shifting.

Finally, to protect the hull during the work above, I hung plastic sheeting that I taped to the toerails all the way around.

Total time billed on this job today:  3.25 hours

0600 Weather Observation:  Clear, 26°.  Forecast for the day:  Sunny, 47°

Arietta Phase 2-3

Wednesday

With some time at the end of the day, my impatience got the better of me and I decided to remove the mast; I’d planned to wait till the bay next door was free in a few more days, at which time I could easily use the crane there to remove the spar, but after inspecting the situation and test-lifting the mast I decided it was light enough to remove safely by hand, which I did using a pair of ladders, eventually lowering the mast easily onto my rolling staging so I could move it outside and out of the way for the duration of the project.

Total time billed on this job today:   0.75 hours

0600 Weather Observation:  Clear, 30°.  Forecast for the day:  Mainly sunny, 5o°

Skeedeen Phase 7-6

Wednesday

I began the day with some minor reassembly on the boat, beginning with the anchor roller and chain stopper on the anchor platform; the grabrails on the windshield; and the forward bow for the bimini top.  I did not reinstall any of the snaps along the edge of the windshield, since the canvas guy said he planned to replace all these when installing the new canvas later.  I also reinstalled some of the loose trim, including the cockpit edge trim and access panels, that were now complete.

The companionway hatches and doors required a second maintenance coat on their main sides, so after the usual prep and cleaning I applied the varnish.

Next, I needed to install the framework for the winter cover so that Jason could come back the next day and properly fit the cover he’d built about a year ago, but which had never been installed.  Even though I’d have to remove parts of the framework to make room for the mechanical work that would happen a few days hence, it was important for Jason to have the opportunity to install the cover in the controlled conditions of the shop.  Though I’d conceived and built the framework myself the previous year, this was the first time I’d installed it on its own, and, following some instructions I’d put together after the original construction, I was pleased with its simplicity and modular construction, and that the installation was straightforward and logical.  The frame took an hour to install start to finish.  Afterwards, I removed both sections of the bimini frame, since the cover required they be out of the way–but the support they provided during the installation of the frame was invaluable and a key part of the installation simplicity.

Total time billed on this job today: 5 hours

0600 Weather Observation:  Clear, 30°.  Forecast for the day:  Mainly sunny, 5o°

Skeedeen Phase 7-5

Tuesday

Pleased with the second planned maintenance coat of varnish on the windshield, handrails, engine box, companionway trim, and other areas on the boat, I removed the masking tape and cleaned up the inevitable small varnish boo-boos on some of the adjacent surfaces.  I planned to leave things as is for another day before thinking about any reassembly or reinstallation of hardware, to give the fresh varnish ample cure time.

The first side of the two-sided hatches from the companionway were complete and had had enough cure time so that I could turn them over and finalize the prep work on the opposite (in this case the “money side”, or most exposed side in the finished product) before applying the first of the two planned maintenance coats of varnish here.

The end of this project was quickly approaching, and to prepare for my needs over the next couple days, I pulled the new winter cover frame I’d built a year ago from storage, and prepared the pieces for assembly next time, once I felt the varnish had cured to a safe stage.  This would allow Jason, the canvas guy, to return shortly thereafter with the custom cover he’d patterned and built a year ago, for its first actual fitting before the boat was ready to head outside.    This would be a temporary installation, since the owner’s mechanic would need access to the boat a few days hence to perform his own annual maintenance and winterizing chores, at which time the boat would move outdoors and I could finish up the cover installation permanently.

Total time billed on this job today:  4.75 hours

0600 Weather Observation:  Fair, 35°.  Forecast for the day:  Mainly sunny, 51°

Skeedeen Phase 7-4

Monday

Starting early, I lightly sanded the first coat of varnish on the windshield, handrails, forward hatch, bow platform, and other trim on the boat, preparing it for the second coat ahead.    Afterwards, I vacuumed and solvent-washed the prepared surfaces and nearby to remove dust.

I had to leave the shop for an appointment, but upon my return I tacked off the wood I’d sanded earlier, then spent the remainder of the day applying the second coat of maintenance varnish to all the on-board trim.  I didn’t have time to continue with the doors, hatches, and other trim that I’d been working on at the bench, but would resume work there next time.

Total time billed on this job today:  3.25 hours

0600 Weather Observation:  Fair, 46°.  Forecast for the day:  Mainly sunny, 53°

Arietta Phase 2-2

Wednesday

Having sewed together a blank of cover material roughly 30′ x 13′, Jason returned to perform the initial templating for the new winter cover.  This process looks awkward, but works out in the end with a cover that fits the boat tightly and accurately.

We began by repositioning the mast a bit further aft, which gave better extension beyond the transom to improve the cover’s coverage and create better lines for the aft termination.  This mast position would be crucial in the future, as the fitment of the cover would require the same mast position each time.  Fortunately, this was straightforward:  The mast was positioned so the halyard cleats at the base were tightly against the forward mast support on the trailer.

Now, with the blank centered and draped over the boat, Jason used a few temporary grommets and lines to pull the centerline tight, and also secure the blank amidships at the widest point of the boat.  From there, he let the blank tell him what it wanted (the Tarp Whisperer), and in this case the cover did fairly settle right into its desired contours, at least once the magic happened back at Jason’s shop.  With temporary darts stapled in place (and duly marked), and key points marked on the blank itself (e.g. the edge of the rubrail, stem and stern, etc.), the process in situ went swimmingly and rather quickly.  The stapled darts would ultimately become tight seams, and the ends would eventually become trimmed and neat terminations with simple lacing.

We won’t likely see the finished result till the end of the project in some weeks’ time.  With this step out of the way, now I could think about removing the mast and getting to work for real.

Total time billed on this job today:  1 hour

0600 Weather Observation: 43°, clear, windy.  Forecast for the day:  Partly sunny, 53°

Skeedeen Phase 7-3

Thursday

With the existing brightwork sanded and cleaned, my next step was to mask off around the wood as needed, on the windshield, helm area, engine box, around the handrails, forward hatch, and anchor platform.

After final preparations and tacking off, I applied a coat of varnish to all these areas on the boat, as well as to the loose hatches and trim pieces down in the shop.

Total time billed on this job today:  5.25 hours

0600 Weather Observation:  43°, clear, windy.  Forecast for the day:  Partly sunny, 53°

Older posts Newer posts