(page 154 of 166)

Danusia 43

< Back to Danusia

Wednesday

During the morning, my intrepid canvas contractor Jason was on site to perform the initial fitting of the new winter cover.  He likes to sew up the rough blank for the cover first (after taking some basic measurements, which he did a few days before), then use the actual cover to template the final shape, cutting it around any obstructions like rail mounts.  The material is a heavy vinyl product used for flatbed long-haul trucking and similarly severe services.  It’s one downfall is that it isn’t breathable, so the frame and cover design would incorporate substantial natural ventilation through the boat (through openings at stem and stern), with some additional features learned over a few past covers of this general type.

On this boat, with the new frame design at the forward end, the stern rail was the only real obstruction requiring this sort of layout and fitting, and the process went smoothly.  The cover blank was in two pieces split at the forward end of the cockpit.

With the rough blank held temporarily taut with small lines and temporary grommets, and the relief cuts made as required, Jason finished up the first round of work my marking 5″ up from the toerails all the way around the perimeter of the boat, which demarked where the vinyl cover material would end and transition to a breathable heavy cotton fabric to wrap over the toerails and hull to about the cove stripe level.  This design would prevent chafe damage at the rails, and also allow better airflow and drying out.

coverfitting4-22416

Once he was done with this work, and had departed with the cover to finish the work as his shop, I could get back to what I needed to do, which was sand the boottop and apply a second coat of the blue-gray paint.  Actually, I’d sanded and cleaned the stripe before Jason’s arrival in the morning, so at this point I could get right to the painting.  Later in the day, impatient, I removed the masking tape to better display the new paint color and finished appearance.  The little tabs of green tape seen hither and yon in these photos show areas where the tape tore at the edge of the stripe, and I didn’t dare try to remove the tiny remaining bits while the paint was still semi-tacked.  I’d remove the final ragged edges of tape once the paint was dry in the morning.

Meanwhile, I applied another coat of varnish to the windlass base.

windlass1-22416

Total time billed on this job today:  1.5 hours

0600 Weather Report:
22°, light snow, about 0.75″ on the ground.  Forecast for the day:  light snow changing through freezing rain, sleet, and rain, high somewhere in the 30s.

Danusia 42

< Back to Danusia

Tuesday

I lightly sanded the boottop primer with 320 grit paper to prepare the surface for the topcoats.  After the usual rounds of cleanup, I applied the first of a couple coats of the owners’ chosen color, a gloss enamel in a blue-gray color.

I finished up the solar panel re-wiring by running the two wires through the new cable clam, which I drilled to accommodate the two wires as needed, and installed the fitting in the deck where I’d prepared the opening earlier before reconnecting the wires to the controller in the locker beneath.

The owner stopped by to check out the nearly-completed project, and we hooked up a temporary battery in order to  test the windlass, which worked well and as expected.  I didn’t think to take any video of the windlass in operation, but both foot switches and the hand-held key fob-type remote control worked as required.  Afterwards, I continued the varnish work on the little windlass block.

windlass1-22316

Total time billed on this job today:  1.75 hours

0600 Weather Report:
5°, clear.  Forecast for the day:  sunny with increasing clouds in the afternoon, high 32°

Danusia 41

< Back to Danusia

Monday

Over the weekend, I finished up the varnish work on the cockpit table, and now I reassembled it as needed and installed it back on the pedestal.

The existing boottop was not a color that the owners liked, so repainting it was one of the final items on my list.  However, it was in generally fair condition overall which would keep prep work to a reasonable minimum.  Most of the paint was sound and well-adhered, and would form an acceptable substrate for new paint without having to completely remove it.

To begin, I masked off the top edge of the existing stripe to protect the hull above during sanding.  I didn’t bother sanding the bottom edge at the moment, since the bottom paint wasn’t in danger if being hurt or sanded away during the prep process.  I sanded the existing stripe with 80 and 120 grits till it was well-abraded and smooth, and ready to accept new coatings.  After cleaning the surface with vacuum and solvent wash, I masked off the bottom edge of the stripe.

With preparations complete, I applied a coat of gray primer to the boottop and left it to cure.

On deck, I masked off the windlass base and began to build up the varnish on the new wood with the second coat on the exposed areas.

windlassbase1-22216

With most of the work either in the final stages or completed, amidst some general cleanup and end-of-project tasks, one of the odds and ends still on my list was to reroute the wires leading to the solar panel, which fit on top of the dodger when deployed.  MC4-equipped wires led from the port side of the cockpit and into the locker beneath, to the small solar controller box.  A previous owner had led these wires through the gutter for the cockpit locker lid, which worked  well enough but tended to want to pinch the wires beneath the lid when it was closed (if they weren’t arranged properly prior to closing the lid).  The current owner asked me to re-lead these through the deck nearby.

I looked into routing the wires as far forward on the cockpit seat as possible, near the forwardmost corner, but access from below wasn’t going to allow me to snake the wires effectively, so instead I ended up at the next best location, which was the corner right near the locker lid, where there was access for the wiring beneath and the wires would lead nearly the way they had before, except away from harm with the locker lid.  I planned to run the wires through a Cable Clam, so I drilled a hole through the deck for the wires, and marked and drilled oversized holes–removing the core–for three of the four fasteners that would ultimately secure the fitting to the deck (the final hole was located in solid fiberglass).  I reamed out some of the exposed balsa core inside the larger center hole, then filled the void, along with the three fastener holes, with a thickened epoxy mixture that would, once cured, isolate the fasteners and wiring run from the nearby core.  I’d finish up the wire installation once the epoxy cured overnight.

Total time billed on this job today:  6.5 hours

0600 Weather Report:
15°, partly clear.  Forecast for the day:  sunny, 32°

Nomad 20

< Back to Nomad

Sunday

I had thought I might start masking off the interior, but as it happened I got involved with non-related projects around the shop and didn’t get around to any real progress on the boat.  I did take a few moments to remove the masking tape from the window repair and lightly sand down the epoxy, which more or less completed the work required there.  The window frame would cover this area when installed.  I’d have to order some new teak plywood for the interior so I could get that underway and get the window back in sooner than later.

windowrepair-22116

I wasn’t yet sure how I was going to deal with the old console–work with the original or simply rebuild–but either way, I wanted to remove the steering helm, which I’d left in place earlier because access to the back side was undesirably tight with the console in place.  Now, with full access to the back, I could easily remove the helm and old hoses, and I set this aside for later reinstallation.  I also removed the abominable compass housing from the top, which wasn’t going to survive either a rebuild or a refinishing no matter what.

Total time billed on this job today:  0 .5 hours

0600 Weather Report:
34°, partly clear.  Forecast for the day:  mostly sunny, high around 46°

Nomad 19

< Back to Nomad

Saturday

To repair the small sections where removing the starboard pilothouse window had damaged the core and outer skin of the superstructure, I prepared the area by cleaning away any debris or old sealant, then masking off below the damaged area and the outline of the window frame to ensure that the repair stayed within the footprint of the window as much as possible, which would minimize any cosmetic concerns.  Then, I installed very thick epoxy putty to rebuild the original shape and replace the foam core that had come out with the window.  There was no particular structural aspect nor requirement to this repair, though where the outer skin had separated from the core within I made sure to force some epoxy into the gap with a small brush to help resecure the whole structure together.  To hold things while the epoxy cured, I added some high-tech clamps made of masking tape, which basically pressed the outer skin back into place against the core and new epoxy.  The epoxy was thick enough to hold its shape, and I formed  it into the square-edged shape required for the opening.

Inside the cabin, I set up tools and breathing equipment, and attacked the interior woodwork and paneling.   Restoring the appearance of the interior would go a long way to returning the boat to the cosmetic condition I hoped for.  The plywood paneling (1/4″ teak plywood) and various solid teak trim pieces were in sound condition overall (other than the panel that I’d removed earlier), and an earlier test had shown that the surfaces could be brought back successfully.  However, the overall nature of the interior construction was pure production line (Larry Pardey might have called it “cheap and cheerful”), and I had to come to terms early on with the wiggly paneling and barely-tacked-in-place trim pieces along the edges and seams, lest I find myself ripping everything out to start fresh.  The reality was that the paneling basically looked fine, and would suit my requirements going forward, and while I might have liked (on some level) to start over and do it my way, I’d already done enough of that and at this point in time such a project scope was not of interest nor desire nor need.

These photos showing the beginning state of the interior date to July 2015.

There was really very little finish on the wood at all, and I found it was pretty quick and easy to sand it away with a palm sander and 120 grit paper.  This took care of most of the field areas, and I finished up with hand-sanding as needed for some of the trim, edges, and a couple of narrower panels where the sander wouldn’t fit.  Though I’d not been looking forward to this task, and had managed to postpone it for weeks, in the end only getting it done would get it done, and once I knuckled down I was pleased to find that the job went smoothly and quickly–far more quickly than I’d ever imagined.  The sanding removed most if not all of the various water streaks and stains, at least to a point appropriate to the overall nature of the construction.  In other words, the results weren’t perfect, but then nothing here was remotely perfect to begin with.  It all worked in harmony,.

While I was making a mess and in sanding mode, I used a more aggressive tool to sand the old cabin sole, which was in poor condition and not salvageable, though I intended to leave the old plywood in place as a substrate.  I gave it a quick sanding to promote a surface that would be ready for whatever came next, and somehow this step made me feel better, as now instead of a neglected, damaged sole I had a surface that looked like it was on the way to something new.

The overhead would also require refreshing.  The after parts of the cabin featured a textured surface, while the forward section featured a v-match simulated plank pattern.  Both sections were in fine condition overall, except they looked tired and ready for some fresh paint.  I ran my sander over both sections, more on the flat surfaces of the forward part, to prepare them for new paint in the near future.

Afterwards, I vacuumed all the surfaces and generally cleaned up, then solvent-washed the woodwork to clean it; this also showed how the newly-sanded surfaces would look once I applied the finish.

There was plenty left to do, but having the interior prep expunged from my list was a great relief.

Total time billed on this job today:  3.75 hours

0600 Weather report:
32°, light rain, coating of snow overnight.  Forecast for the day:  Rain and showers, then clearing, high in the low 40s

Danusia 40

< Back to Danusia

Friday

The pedestal paint was complete, so I removed the masking tape.  Later in the day (not shown here), I reinstalled the wheel and the cleaned-up winch pocket.

I spent the rest of the morning finishing up the framework for the winter cover.  I extended the ridge aft and past the transom, and supported it with three more verticals.  Then, to hold the whole arrangement securely, I installed tie-down lines as needed to tighten the frame and hold it in place.  Jason, my upholstery and canvas contractor, came by in the afternoon to tale some rough measurements he needed to build the blank for the cover.

I picked up new vinyl graphics for the name and hailport, and installed them on the transom in the afternoon.  The outline color would tie in with the new boottop that I’d be working on presently.  I installed the name lettering as high as I could without interfering with the two vent fittings on the transom, and followed the camber of the taffrail above; I installed the hailport on a  visually horizontal line beneath.

Total time billed on this job today:  5 hours

0600 Weather Report:
8°, clear.  Forecast for the day:  Sunny, 33°

Danusia 39

< Back to Danusia

Thursday

The first order of business was to prepare, then paint again, the steering pedestal.  I chose a semi-gloss finish for the pedestal, as I felt it would look best and was appropriate to the original pedestal finish.  The second finish coat was looking pretty good.

I continued work on the hull, this time on the starboard side, where I cleaned up and polished the topsides, removing various minor stains and increasing the shine.

I finished up the aft part of the port cove stripe with the logo, then replaced the starboard cove stripe with the gold leaf tape as well, simply copying what the old stripe details had been.

Meanwhile, not to be forgotten, I continued my tiny varnish project with the cockpit table, which was now approaching its final coat.

varnisih1-21816

Now that the new foredeck paint had cured for a couple days, I finished up the windlass installation by installing the two foot switches.  The holes were all prepared, with pilotholes for the screws already in place, so installation was relatively quick.  I chose to pull the wires up through the deck in order to connect them from the top just to make life a little easier.  I bedded the plastic switch bodies with butyl sealant.  Testing the windlass operation would have to wait till the batteries were hooked up.

With a new custom winter cover planned, and the project wrapping up soon, I turned to the framework required for the cover, which the canvas contractor needed in place to effect his initial fitting of the cover blank, and to give him time to complete the cover before I was ready to move the boat outdoors, it was time for me to get the frame set up.  I’d get back to some additional hull work as soon as the frame was done.

Earlier, we’d worked out a couple basic details about the frame for this boat, and to get started I pre-assembled two ridge sections down in the shop to streamline the process and keep the sections as straight as possible.  I spliced the sections together with bolts to make setup and removal as simple as possible on an ongoing basis, and sometime later I’d mark and label everything for its proper position.

This frame was to dive from the foredeck to the stem, so I set up the first 16′ section of ridge so it ended at about the foredeck cleats, where I installed a vertical support, and another further aft near the mast step (this one was actually the height benchmark).  With the first section steadied temporarily with some lines, I cut and fit the angled forward section to notch around the base of the bow pulpit on centerline, and secured it to the horizontal ridge with some angled splice brackets.  My goal, as always, was to keep the frame as simple as possible, both for initial construction purposes as well as annual set up and break-down.  The angle of the cover itself would provide enough slope without the need for complicated rafters or side bracing.

This brought me to the end of the day, but it’d be no trouble to finish up the aft part of the frame next time.

Total time billed on this job today:  7.5 hours

0600 Weather Report:
20°, partly clear.  Forecast for the day:  decreasing clouds, 34°

Danusia 38

< Back to Danusia

Wednesday

After a light sanding, vacuum, and solvent wash, I applied the first of a couple coats of enamel to the steering pedestal.

The hull was in good condition overall, but needed just a touch of sprucing up.  I started at the transom, where I removed the rest of the old name and hailport and cleaned and polished the surface to prepare it for the new graphics, which would be on hand soon.

I continued with the port topsides, which started out looking pretty good but with some staining and minor wear or oxidation.

Though the forwardmost waterline would require a little more work–there was some yellow staining just above the boottop that I wanted to get rid of with another product, as well as some marks probably left by a mooring buoy–after a straightforward polish and buff the topsides looked cleaner and renewed.

With some color changes on hand, my first step was to replace the existing blue cove stripe with classic gold leaf.  I was running out of shop time, as I had another commitment for the afternoon, so as of this writing there remained some work at the aft end of the cove stripe and with the original logo, but the remainder was complete.  I’d repeat these basic processes on the starboard side next time.

Total time billed on this job today:  3.5 hours

0600 Weather Report:
30°, clear.  Forecast for the day:  partly sunny, high around 42.

Danusia 37

< Back to Danusia

Tuesday

One more washing and light sanding, and I was done with the stern tube repair, so I went ahead and reinstalled the propeller, along with a new zinc on the special nut at the end.  It was interesting to compare the old zinc with the new one.  The old cotter pin had either been purposely broken off inside the shaft, or accidentally so, so I knocked out the remains and replaced it through the zinc’s special prop nut.

I lightly sanded the primer on the pedestal and foredeck, and after cleaning up I masked off the rest of the starboard side of the foredeck so I could repaint the area with paint that matched the existing areas.  Because the deck was conveniently sectioned with white borders, I chose to paint this entire area to better blend in the repaired area around the windlass.  With past experience using Kiwi-grip (the paint that a previous owner had applied to the decks sometime before), I knew to mask in a wider area (especially where the sides of the roller might touch) because the stuff was messy to work with.

With preparations complete, I applied a coat of cream-colored Kiwi-grip that I fortunately had on hand, and which matched the paint already on deck.  Once the paint had cured just barely past the potential disaster stage, I removed the masking tape from the edges, as leaving the tape on till this particular paint cured completely would pull up the edges.  This was always my least-favorite feature of using this particular product, but in this case was uneventful.  The end result looked good, and I’d leave the new paint to cure for at least a full work day before attempting the final installation of the windlass foot switches over the fresh surface.  Later, I removed the masking tape from the cleat, choosing to wait to lean over the fresh surface till it was basically dry.

Next, I applied a coat of primer to the steering pedestal–the entire thing this time.

My work list grew ever shorter, with most of the remaining work to be done on the hull, but before I moved the staging down to hull height I went around and installed new set screws in all the stanchion bases, in the existing holes.  These, along with the fixing screws that passed into each stanchion, would help hold the stanchions tightly in place and prevent wobbling.  I had to clean out a couple of the holes with a 1/4-20 tap, but otherwise the project was without note.  I put a little waterproof grease on the screws since a new winter cover would require annual removal of the stanchions, and this would prevent the set screws from freezing.

I continued the varnish work on the cockpit table with another coat on the top surface (4).

varnish1-21616

With whatever work remained on deck and inside the boat just as do-able without the staging, and a need to continue work on the remains of the project list, I spent the rest of the afternoon breaking down and resetting the staging at hull height.

Total time billed on this job today:  5.75 hours

0600 Weather Report:
22°, 2″ of snow plus some freezing rain overnight, light freezing rain/drizzle.  Forecast for the day:  continuing to warm through the 30s and 40s and even the 50s, turning to all rain, with another round of heavy rain and wind due late

Danusia 36

< Back to Danusia

Monday

Over the weekend, in two separate events, I continued work on the stern tube and sanded and fine-tuned the new fairing with additional epoxy material, sanding between rounds.

Round 1:

Round 2, which was a minor fairing to take care of a few lingering low spots:

Now, I washed and lightly sanded the aperture a final time to smooth the last application of fairing compound.  To finish off the area, once I’d cleaned up I applied a coat of unthickened epoxy as a sort of sealer for the fairing compounds beneath, and left it to cure.

Meanwhile, upstairs I continued varnish work on the cockpit table top.

varnish1-21516

To better support the windlass and spread any loading across a larger area of the deck, I elected to prepare and install a fiberglass backing plate belowdecks.  With various existing installations to work around, I started with a piece of 3/4″ prefabricated fiberglass sheet and, after rough-trimming it to fit within the allotted space, pressed it temporarily into place with a stick to hold it so I could go on deck and mark it for the cutouts and bolt holes, which I cut down on the bench.

For a close fit with the built-up structure forward of the backing plate, I scribed the leading edge of the backing plate to the shape, which allowed all four windlass bolt locations  a good bearing surface.  After I removed a bit of extraneous and pre-corroded aluminum from the edge of the existing structure, the new backing plate was effectively flush to allow the fourth bolt, which was half in and half out of the backing plate, a place to rest.

I prepared the windlass for its final installation by slipping the supplied gasket over the base.  The “knife edge” of the windlass base would probably seal the edges at the gasket fairly well, but to add some extra sealant and protection against water intrusion I added some butyl sealant around the tops of the fixing bolts and around the two large openings of the windlass base.

windlass1-21516

Pressing the windlass firmly into place from above–I had to push hard to get the butyl around the bolts to squeeze into the holes, which was a good thing–I moved below to install the backing plate, fender washers, and nuts, and I tightened the bolts in turn to pull the windlass securely into place.  As I’d hoped, back on deck the gasket looked well-compressed below the windlass base, and some of my butyl had squeezed out as well.

On paper, the windlass setup, with its threaded collar and shaft, castellated gearbox, and separate electric motor, looked fairly well thought-out from an installation standpoint, and so it turned out to mainly be.  To begin the installation, I applied good waterproof grease to various areas, as directed, including the shaft and key, inside of the gearbox, castellated interface, and the threads to accept the large fixing nut on the shaft, as well as the motor shaft, bolts, and mounting flange,

The system allowed easy positining of the gearbox and motor assemblies for various situations, and after trying a position or two I settled on facing the gearbox and electric motor aft and to port, which offered the best access, kept it out of the way of the windlass chain pipe, and away from the two foot switches to keep access there as good as possible also.  The notched end of the gearbox housing fit into corresponding notches on the shaft housing, with a st ainless key to secure the windlass shaft within.  To secure the gearbox, the large plastic nut from the housing simply threaded hand-tight over the gearbox threads, with a simple clamping ring at the bottom of the shaft to secure the key within.

The motor was heavy, and with limited arm and shoulder access into the chain locker its initial positioning took a little wrestling till I figured out the best way to hold it in place–and lined up with the shaft–while getting the bolts started.  The two bolts threaded into the motor housing itself, so there was no need to juggle nuts and double wrenches, amd once the weight of the motor was supported it was no task at all (though I wished–as I frequently do–that manufacturers would leave enough room around bolt heads for a ratcheting box end or even a real socket and ratchet).  Yipe, yipe, yipe.

Now I could make up the final cable ends to the windlass motor.  The ground/negative cable was already terminated from earlier, and I secured it to the center post along with a smaller ground wire that led back to the control box.  Then, I cut and terminated the two positive wires (F1 and F2), which controlled the motor’s (and windlass’s) direction and attached them to their corresponding posts on the motor, and covered all three wires with protective boots and secured the cables out of the way as needed.

Final installation of the foot switches would await my repainting of the foredeck where I’d patched it, but while I had the wiring tools on hand I determined the lengths and made up the terminal ends of the wires to allow for easy final installation later.

Finishing the foredeck was now a priority, so to that end I masked off as needed and prepared some epoxy primer for the newly-epoxied areas, as most one-part paints and primers wouldn’t cure properly directly over semi-cured epoxy (the alternative would be to wait a couple weeks).  I applied the primer over the epoxied areas, and this would allow me to continue with the final deck treatment as I chose.

Similarly, back at the cockpit I masked off the steering pedestal as required, and applied some of the epoxy primer to the areas where I’d installed  epoxy fairing compound there as well, so I could soon continue with the final primer and paint on the pedestal.

Total time billed on this job today:  7.5 hours

0600 Weather Report:
-19°, clear.  Forecast for the day:  Sunny, high near 20, then increasing overnight to freezing and above. Snow late in the evening turning to frozen mix and eventually rain.

Older posts Newer posts