~MENU~

Home
The Concept
The Boat
Bringing Her Home
Weekly
Progress Log
Daysailor
Projects
     
The Boat Barn
Resources
Other Sites
Email Tim
 
 

 

                   

 

 

Boat Barn:  Raising the Walls and Roof Framing               

The walls were framed on the ground and lifted into place with a crane.  In the space of a day, the barn was suddenly there!  Of course, much work remained before the structure was complete.
Framing
        Framing Detail Photos
 
Raising the Walls
     
Wall Photos  
     
Truss Photos       
Roof and Trim
Electrical
  Insulation/Windows/Doors  
Barn Home Page

Tuesday, September 2, 2003
Walls and Trusses

At 0600, the crane arrived, followed closely by Bob, and by 0630 some initial preparations had been made (including moving some of the lumber piles in order to back the crane closer to the slab).  Before 0700 hit, the back wall had already been raised into place, and temporarily braced.  Two additional guys arrived at about 7, and the four of them proceeded to make short work of raising the remaining three walls.   By 0800, all four walls were standing and were partially secured in place.

raisesouthlg.jpg (83023 bytes)Each wall was raised into place carefully by attaching straps to the crane from the top of the wall (through gaps in the framing on the front and back walls, through two of the window openings in the south wall, and attached to temporary eyebolts secured to the top plate on the north wall).  Then, it was a matter of raising the top edge of each wall while guiding the bottom plates into place.  Once each wall was standing, it was temporarily braced into place and secured, as applicable, to the adjacent walls.


wallsupfar.jpg (63593 bytes)

Click here to see a series of photos of the walls going up.


truss1lg.jpg (85328 bytes) Once all four walls were up and braced, the crew took a break and then got to work on the trusses.  There were 21 trusses to raise and brace into position.  Onto the first truss, they nailed two long sections of 2x6 lumber, which extended about 8 or so feet beyond (beneath) the bottom chord of the truss.  With this extra height, it took some juxtapositioning of the crane to get the first truss over the sidewall, but once that hurdle was passed, placement of the first truss--the most difficult, perhaps--went smoothly, except that the boom on the crane couldn't extend quite far enough to reach the very back wall of the barn and lift the truss and braced high enough above the wall to clear it.  Therefore, it just took a little fiddling to get the vertical braces over the edge and secured to the framing beneath, thereby holding the truss in position.

bigbarn.jpg (81107 bytes)Once that was done, the trusses came into place one by one, each one being nailed in place at the sidewalls and secured with horizontal bracing about halfway up the slope to hold them in the proper position.  Other bracing was added along the way as necessary.  By about 1500, the work was complete--all 21 trusses were in place and braced securely enough for the moment, and the weary crew packed up and went home, leaving me to pace around the barn and stare in admiration, awe, and wonder.

Click here to see a series of photos of the trusses going up.


Wednesday, September 3, 2003
Sheathing

After a day in which the site went from nothing to a full-sized barn (if only in framing) in only 9 hours, anything less was bound to seem insignificant.  Knowing full well the nature of construction, I was prepared for this apparent slowing of the progress.  Still, one always hopes things can magically go faster.

barnfront90303.jpg (76669 bytes)On this day, the extent of the progress was the completion of the sheathing on the two gable walls, not including the gables.  It didn't seem like much, but of course moving and installing all that plywood is time consuming and difficult.  Bob has a great set of high-quality staging and jack system that surely made the job easier, but it's still a big, tall building--and sheathing isn't the fastest job in the world to begin with.


backwall90303.jpg (69709 bytes)


Friday, September 5, 2003

Gable Framing, Sheathing, and Other Details

barn90703.jpg (69264 bytes)After a rainy day on Thursday (no work was done), Bob arrived alone on Friday morning.  This meant that there would be no major work done on things like sheathing, but there was plenty that could be done alone in an efficient manner.  He began by setting up a taller set of jacks that would enable him to reach the higher parts of the gable, and then set to work on some cross-blocking between the roof trusses, gable framing (he admitted that he should have ordered two gable trusses, which come with all the appropriate framing installed 2' on center), and other smaller jobs.  This stuff all needed to get done, of course, and sometimes it's just good to have a day dedicated to knocking off that annoying punch list.  Next week, work in earnest on the roof sheathing and shingling can begin.  It didn't look like much, but progress is progress!


anchorbolt.jpg (32320 bytes)The anchor bolts, installed after the walls were standing, consist of hardened steel bolts and an insert.  Holes are drilled in the framing and into the concrete, the bolts (and inserts) are installed, and the nuts tightened.  As the nuts are tightened, the action expands the insert, firmly securing the fixture in place.

 


Continue>

 

All photos and text on this site ©2002-2009 by Timothy C. Lackey and Lackey Sailing, LLC
All rights reserved.