|                    
     |  | 
  
    | Barn
      Home Page Monday, August 25, 2003Running Electrical Conduit
 The barn requires good electrical service,
      of course.  Several weeks earlier, before any of the barn work had
      actually gotten underway, I had consulted with an electrical that I use
      from time to time about what would be required to get power out to the
      barn, and the best way to go about it.  He came over and chatted with
      me for a time, and we worked out a plan.  I planned to do most of the
      electrical work myself, but wanted a professional to deal with the main
      feed and panel, especially since it involved reworking the main service
      panel in the house. The distance between the closest corner of
      the barn and the house was about 115', including about 15' of run directly
      beneath the deck on the back of the house.  Connecting the new cable
      run to the barn with the house service would require some fiddling, as
      access from the outside to where the panel is is a little interesting
      because of a 14' house addition that was added sometime in the past. In any event, the plan we came up with
      involved installing a new master panel in the house, and moving the
      existing house panel out to the barn for the service there.  To run
      the cable, I was to install PVC electrical conduit underground between the
      house and barn. Once the new slab was poured and in place,
      I could install the conduit at almost any time.  I had to wait for
      the slab, obviously, so that I knew exactly where to run the
      conduit.  For ease and convenience, I chose the front right corner
      (near the entry door) for my eventual panel location, and decided to run
      the conduit to that location. Even though the trench required for
      electrical conduit  only needed to be 12" or 16" below the
      surface (unlike the 48" required for plumbing--which I am not
      installing to the barn), the distance involved was too great to dig by
      hand.  I decided to rent a trencher, usually referred to as a Ditch
      Witch (for a common name brand).  It
      was kind of amusing, actually.  The rental place I use is 20 or 25
      minutes away, usually.  By the time I drove there, waited for the
      machine, and returned, over an hour had elapsed since I had placed a phone
      call to inquire about renting the machine.  I arrived back at the
      house and unloaded the huge Ditch Witch.  Driving one of these things
      is interesting; they steer with the rear wheels (there is only one front
      wheel to steady the tool), so turning involves a sort of crab walk. 
      This takes some getting used to.
 |  
    | 
  I
      positioned the machine where I wanted to start digging the trench, fired
      up the evil-looking digging chain thingie, and went to work.  Despite
      some minor directional issues (my trench didn't end up as straight as it
      could, mostly because of my inexperience adjusting the direction--very unusual
      to drive), I had the 100' of trench dug out in all of 10 or 15
      minutes.  I couldn't believe how quickly it went.  I had to turn
      the machine around and begin trenching from the barn side as well, which
      meant that I needed to meet up with the other half of the trench partway
      out.  It's a good thing I wasn't one of the engineers on the Chunnel
      project, because I didn't do that well.  As soon as I started digging
      from the barn end, I saw that I needed to make a course adjustment, and as
      a result this part of the trench ended up with a decided arc to it. 
      Oh well!  It doesn't really matter much, as the conduit can bend
      enough. |  
    | 
 |  
    | It was anticlimactic,
      really.  In short order, I had the machine loaded back on the
      trailer, and went to return it--another 20 minute trip.  $63.60 later
      (despite the shortness of time I actually used the tool, I felt this was
      money well spent), I was done, and headed to the nearby  warehouse
      store for some electrical conduit.  I picked up 12, 10' sections of
      2" conduit (for the main cable), and 24, 10' sections of 1"
      conduit (for two runs for phone, cable, Internet, or future additions),
      along with some elbow fittings and a new, longer electrician's snake that
      I'd need to pull wires through.  I also found some polypropylene
      messenger line designed for pulling wires, so I picked some up so I could
      run some through each conduit for ready use in any future addition later. |  
    | Back at home, I unloaded
      and distributed the conduit along the run.  Beginning at the barn
      end, I assembled the pieces.  (Sorry, no pictures of this
      part.)  The 2" conduit went together easily with some gray PVC
      glue at the joints.  I added a 90° elbow at the barn end, and a 3'
      stub up vertical piece for later use to tie into the barn.  
      When I had most of the sections assembled (stopping short of the back
      deck, where I still needed to dig a trench the remaining 18' to the
      house), I lay the 2" conduit in the trench, pushing it as close to
      the bottom as possible.  Then, I began to work on the two lengths of
      1" conduit, which I decided to install for additional wire chases and
      for phone lines, cable lines, and Ethernet cables for Internet
      access.  It's easy to put extra conduit in the ground; why not add
      some, thought I?
 |  
    | 
  The 1" conduit was
      irritating to work with.  Each section of electrical conduit features
      one flared end, which is designed to slip right over the regular-sized end
      of the next piece.  In theory, this works well--and did work well,
      with the 2" conduit.  However, many of the pieces of 1"
      seemed to have distortion at the ends, meaning that the flared section
      wouldn't fit without a fight.  I developed a series of solutions to
      this problem as I went, including using a drum sander to ream out the
      opening, cutting off the end part of the flare to expose a section farther
      up that seemed wider, and gently squeezing the flare with pliers to sort
      of bend it back into shape.  Eventually, and with far more effort
      than should have been necessary, I prevailed.  As with the larger
      2" conduit, I stubbed up 3' sections of vertical conduit at the barn
      end. |  
    | Now, I had the best part left to complete:  digging a trench under
      the deck.  The distance from the edge to the side of the house where
      I wanted to stub up the conduit was about 18', and there was not standing
      headroom beneath the deck.  Fortunately, though, it is about 4-5' off
      the ground, so there was adequate room to work--on my knees.
 The ground beneath the deck
      was happily sandy and quite loose, so digging by hand wasn't bad.  I
      used a garden trowel to dig, along with my hands for scooping out loose
      dirt once it was freed by the trowel.  After some time (I don't know
      how long it took--not too bad), the trench was complete, and I finished
      the three sections of conduit, cutting the final pieces to length as
      needed and adding stubs at the house end like the ones at the barn end.  When I was sure all the
      joints were complete, I ran an electrician's snake through one of the
      pieces of 1" conduit to ensure that it would pass through unimpeded
      the whole way.  It did, meaning that I would be able to pull wires
      through as necessary later, so I began burying the conduit.  Using a
      metal rake, I pulled some of the piled dirt into the trench and tamped it
      down with the rake and my foot as necessary.  This was tiring work,
      much harder than any other aspect of the job.  There was excess dirt,
      as some had been displaced by the three lengths of conduit, so I piled the
      excess here and there as necessary for later removal.
 |  
    | Thursday -Saturday, September 11-13, 2003
 Electrical Rough-In
 After a few weeks' delay waiting for the barn construction to progress
      to a point where wiring could be installed, a flurry of activity over a
      few days saw the installation of most of the wiring inside the barn, as
      well as a new  panel and main electrical feed out from the house. During two evenings earlier in the week, I had installed the myriad
      plastic electrical boxes needed for the many outlets, switches, and
      ceiling fixtures that were to be installed in the barn shop. 
      Following a schematic that I had drawn up, I installed over 50 boxes in
      the walls and ceilings.  With that preparatory work complete, I enlisted the help of my friend
      Nathan to pull wires and complete the electrical rough-in.  Two sets
      of hands make for quicker work than one, and  the two of us managed
      to accomplish much--but not all--of the wiring in one productive
      day.  With a right-angle drill, we drilled holes through the studs to
      accommodate the wiring as needed, and pulled the 14/2 Romex cable through
      to each box as called for in my schematic.  Because outlets are
      cheap, I spec'd one approximately every six feet around the perimeter,
      with several extras here and there as seemed appropriate.  In
      addition, the ceiling features outlets for up to 25 ceiling fixtures (fluorescent
      shop lights) and three ceiling fans.  In a solid day of work between
      the two of us, we managed to rough in all of the wall outlets (which I
      mounted 42" off the floor--the same as the light switches--for ease
      of access), run bulk cable for two of the five banks of ceiling fixtures,
      and for several other applications.
 |  
    | 
    The next day, working alone, I worked on various
    aspects of the wiring without clear direction, as I needed some materials
    but couldn't really leave because I had an electrician on site pulling the
    main feed cable to the barn and reworking the main house service
    panel.  The plan  was to remove the older panel from the house and
    install the shell in the barn (it's a 20-circuit panel).  To better
    suit the house's needs, I had them install a new, larger panel in the house,
    so of course that required shutting down the power for much of the
    day.
  With the power out (though I could plug into
    Bob's generator as needed), I didn't end up getting that much done in the
    wiring, though I did install 10 ceiling outlets  that had been rough-wired
    the day before, and took care of some loose ends (no pun intended) by
    installing an outdoor outlet box on the south wall of the barn, where the
    12' wide boat pad is located.
 |  
    | 
  Much
    of the morning was spent setting up some pipe staging that Bob had offered
    to bring down--he needed it for a little later in the project in order to
    strap the bottoms of the trusses, but offered its use to me for completing
    the wiring.  Setting up the two, five-foot sections was easy enough,
    but then it required a platform on top.  I chose three of my old
    homemade staging planks (a pair of 8'  2x4s on edge with plywood
    screwed to the tops) and heaved them up on top of the staging.  Then, I
    had to brace things in place to prevent the staging from racking, so I
    screwed more 2x4s to the bottoms of my three evenly-spaced planks. 
    Finally, I laid a sheet of 1/2" plywood over the whole arrangement and
    screwed it down.  Success!  The staging platform ended up about
    12' above the floor, between the planks I had laid on top and the large
    rolling casters on the bottom.  The casters were the key to the whole
    setup:  the staging could now be rolled around whilst perched atop,
    making it extremely useful.
 I couldn't imagine having
    done the job without the rolling staging.  Oh, it would have gotten
    done, but it sure would have been less convenient, and more
    time-consuming.  Having the right tool for the job is simply priceless. Unfortunately, Bob and I
    spent a good part of the day chatting, slowing up both of our respective
    work schedules.  Oh well...
     |  
    | 
  The
    next day, Saturday, I attacked the wiring with a vengeance.  Early in
    the morning I purchased several more rolls of wire that I needed, and some
    other things, and got to work at once.  My plan was to complete the raw
    wiring runs, so as to be ready to wire the breaker panel the next day. 
    I worked alone on the wiring all day, beginning with running 5 lengths of
    14/3 cable for the three-way light switches I wanted for the overhead
    lighting.  I thought it would be useful to have the lights controllable
    from either the man door on the north wall, or the smaller rolling door on
    the south wall.  Great idea on paper...but in practice it required 5
    runs of this heavy, kinky, unwieldy cable, each one ending up using about
    70' of cable.  It took me most of the morning to complete the
    job.  With that done, I moved on to running a dedicated 20 amp circuit
    for my table saw, dropping a pair of 20-amp outlets near the electrical
    panel, and completing the remaining three banks of overhead outlet--15 in
    all, plus associated wiring and connections.  The overhead outlets will
    be used to install the shop lighting; the fixtures I chose feature a normal
    wiring plug and are not hardwired.
 |  
    |  
 |  
    | Continue>
 |  |