Steadfast 27

Boat:

Steadfast, 1979 Fisher 30' Ketch

Schedule:

Scope of Project:  Hull paint and brightwork maintenance

Begin Daily Project Logs

November 30, 2017

Steadfast 27

< Back to Steadfast

Thursday

I applied the third and last coat of finish to the brightwork during the morning.

Afterwards, I turned once again to the pilothouse door and lazarette hatch.  The hatch required a second coat of paint on all areas, and I turned the door over so I could paint the second (outside) side.

Total time billed on this job today:  3 hours

0600 Weather Observation:  20°, clear.  Forecast for the day:  sunny, increasing clouds in the afternoon, upper 30s