Skeedeen Phase 6-20

Boat:

Skeedeen, a 1987 24' Crosby Striper

Schedule:

Project Schedule:  September 2020 – November 2020

Project Scope:  Hull paint; faux wood finish and relettering on transom; brightwork maintenance and other TBD

Project Complete:  144.25 Total Hours

Begin Daily Project Logs

October 23, 2020

Skeedeen Phase 6-20

Friday

After final preparations, over the course of several elapsed hours I applied three coats of Alexseal stars and stripes blue to the hull.  The color variations between photos are the result of the variable positions of the strong lighting and camera in each case.

Total time billed on this job today:  4.25 hours

0600 Weather Observation:  54°, overcast.  Forecast for the day:  Mostly cloudy, 60°