(page 144 of 165)

Patience 12

< Back to Patience

Friday

I decided to mount the little solar controller near the companionway, where it’d be readily accessible for connection to the removable solar panel abovedecks, and also where I could run wiring conveniently (and out of sight) into the battery compartment for connection.    After bolting the controller in place, I led wiring from the output side down behind the companionway steps and then along an existing wire run into the battery compartment, where I connected the leads to the battery terminals as required.  When not in use, the connector for the solar panel could be easily tucked in behind the controller for safekeeping.

The owner requested a simple lead through the companionway for the wires, so I modified the top drop board in the companionway to accept the wire from the solar panel–it was easy to slip in and out on its way down to the controller, but allowed the sliding hatch to cover the opening.

With other work in the cabin complete, I installed the new cabin sole panels, and cleaned up any final remnants of the project.

Finally, I masked off and painted the bottom, completing the new appearance, and completing the project.

Total time billed on this job today:  4.25 hours

0600 Weather Observation:
56°, fog and clouds, light drizzle.  Forecast for the day:  cloudy, maybe a shower, 60s

Salty 50

< Back to Salty

Thursday

As a last-minute addition, the owner requested installation of a bilge high-water alarm, which I’d ordered a while back but had been awaiting time to install.  Now was that time.

The system required a little float sensor to be mounted near or at the bottom of the bilge, a challenging prospect on this boat with the available access.  The only way in was through the removable shelf containing the starter battery in the engine room, so I disconnected the battery and moved it aside, removing the shelf.  The bottom of the bilge was juuuuust beyond the realistic extent of my reach, given the limits on head and shoulder room at the top, but I cleaned up the side of the sump a bit to accept epoxy and a fiberglass mounting block, to which I installed the sensor float in its supplied bracket.  With the back of the mounting block buttered up, I pressed it into place at the bottom of the sump.  I led the two small wires through some flexible conduit and brought them up into the engine room, leading them through a space at the forward end of the battery platform.

I prepared an opening for the little control panel (which contained the horn for the alarm) just forward of the battery switch, where there was convenient access for the required wiring.  With existing obstructions, there was pretty much only one place the panel could go, and there indeed it went.  I made the wiring connections to the panel, including the two wires leading to the float switch (which, when activated, would sound the horn), and then power and ground (which I led respectively through a fuse to the hot side of the battery switch, so the alarm would always be powered, and to a nearby negative distribution buss).  I screwed the panel into place and neatened up the wiring, and this completed the installation.  The power light on the panel was lit, as it should have been.

Total time billed on this job today:  1.5 hours

0600 Weather Observation:
45°, sunny.  Forecast for the day:  mainly sunny, increasing clouds late in the afternoon, high in the low 60s

Patience 11

< Back to Patience

Thursday

The final cosmetic change planned for the hull was to add a cove stripe near the gunwale.  The owner selected black to match the name, and I installed the new stripe so it was even with the top of the name, which was 5″ down from the edge of the gunwale above–or, more specifically, two strips of 2″ masking tape and one of 1″ .  I created a series of these tick marks along the length of the hull as required to give me a guideline for the new vinyl striping.

I left a 3″ space between the name and the stripe on each side, and ended the stripe 12″ ahead of the transom, and 36″ aft of the stem, and applied the striping to both sides, following my alignment marks and fairing the actual tape installation by eye accordingly.

Late in the day, some supplies I needed for the final job arrived.  To help keep a fully-charged battery topped off while the boat was not in use, the owner requested a small solar panel, with a portable, removable installation.  This 14W rollable panel seemed to fit the bill for the minimal electrical needs of the boat (mainly ensuring the battery stayed fresh for the new and improved automatic bilge pump system), and taking into account budget and portability requirements.  It wouldn’t light the charging world on fire with its performance, but would be up to the task of maintaining the state of the battery.  The panel could be placed just about anywhere, but on the coachroof tied to the handrails seemed a generally convenient spot despite some loss of production likely from boom shading when the boat was rigged.  The portable nature of the panel, and the non-permanent nature of its eventual wiring, meant that it could be moved around as needed.

solar1-60216

To be sure the panel wouldn’t have any negative effects on the battery from overcharging–not likely, but still–I specified a small solar controller, which I thought would also provide a convenient place to hook and unhook the panel wiring, which the owner wished led through the companionway.  I spent a little time mulling over possible ways I could install the internal wiring to the battery in a pleasing, useful, and safe way, keeping in mind the need to remove the panel and its wire when not in use.  I’d finish up the installation next time.

Total time billed on this job today:  1.75 hours

0600 Weather Observation:
45°, sunny.  Forecast for the day:  mainly sunny, increasing clouds late in the afternoon, high in the low 60s

Waanderlust 8

< Back to Waanderlust

Wednesday

The final job on my list was to install the new mast winches, which I’d ordered earlier and which had just arrived.  Installation onto the flat pads provided by the spar maker was straightforward, and I added an antique bronze cleat on each side to finish off the installation.

Total time billed on this job today:  .5 hours

0600 Weather Observation:
50°, sunny.  Forecast for the day:  sunny, 70s

Patience 10

< Back to Patience

Wednesday

Back at the shop after a long weekend, the colored stripes of the new boottop had had a lavish amount of time to cure, so I continued the process by masking over the new stripes as needed so I could paint the white (i.e. hull color) portions between them, which was required in this case because the original condition of the underlying hull surface dictated this approach.

After final preparations, I applied a coat of gloss white enamel to these areas.

Next, I applied a second coat of light gray nonskid paint to the new cabin sole sections.

Late in the day, after a close inspection, I decided I was pleased with the new white paint at the boottop, and decided to remove the masking tape.  All that remained to complete the new look now would be to repaint the bottom up as far as the lowest white stripe, which I’d do as soon as I felt I could overmask the fresh paint.

Total time billed on this job today:  2 hours

0600 Weather Observation:
50°, sunny.  Forecast for the day:  sunny, 70s

Patience 9

< Back to Patience

Thursday

To finish up the knotmeter patch, I lightly sanded the fairing compound, bring the area smooth and level with the adjacent surfaces.  No further fairing was required, so after a solvent wash I applied a coat of plain epoxy over the fairing material as a sealer.

I sanded the primer on the cabin sole panels, and after final preparations applied the first of a couple coats of nonskid paint, which I mixed to a light gray color.

In the cabin, I finished up the new bilge pump wiring, leading four wires as needed to the new switch location, on the starboard bulkhead just beneath the electrical panel.  I made connections in the battery compartment as required to connect the new wiring to the wires already leading to the bilge, and this completed the electrical side of the pump installation.

With the connections made, I could test-run the pump.  These pumps have the idiosyncrasy, as it were, of running capably in either direction, and with two unmarked black wires leading from the motor, there’s no required–nor conveniently marked–polarity.  So determining the pump inlet and outlet ports for the hoses requires operating the pump first, once wired, to determine which is the suction side.  Both the manual switch and auto switch tested operational, and with the ports’ correct orientation determined, I could make up the inlet and outlet hoses as required.  (The inlet has the strainer.)

This quickly pushed out the remaining water in the long hose leading to the transom, leftover from the old installation.

Total time billed on this job today:  3 hours

0600 Weather Observation:
55°, sunny.  Forecast for the day:  sunny, high near 80

Patience 8

< Back to Patience

Wednesday

After a quick water wash, I lightly sanded the new patch over the knotmeter through-hull hole, sanding it flush on the outside as needed.  Then, I applied a coat of fairing filler over the area, leaving it to cure overnight.

With the epoxy coating on the bottom sides of the cabin sole panels now cured, I turned them over and sanded the top surfaces to smooth them as needed.  Then, after cleaning up and solvent-wash, I applied a coat of primer to the panels.

I installed the new bilge pump on its platform, and the float switch in the keel sump, then began some of the wiring, leading a new 2-conductor wire between the bilge and the compartment containing the pump, and making up the various connections in the bilge area between the switch, pump, and an existing wire leading to the battery compartment.   In this case, there was really no way to avoid having wires running through the bilge compartment, but I kept the wires as high as possible with wire clamps.  The old pump had been wired directly to the battery without a separate on/off switch, so I’d finish up power wiring and wiring to the new panel switch next time, along with the pump hose connections.

Total time billed on this job today:  4.5 hours

0600 Weather Observation:
58°, foggy.  Forecast for the day:  Becoming partly sunny, high 73°

 

Waanderlust 7

< Back to Waanderlust

Monday

Though the project was essentially complete, I’d continue minor work as new  hardware arrivals trickled in for the mast.  Today’s arrival was the VHF antenna, which I test-fit, then inverted in its bracket for storage and transport.

0600 Weather Observation:
42°, sunny.  Forecast for the day:  mainly sunny, some increasing clouds in the afternoon, high in the 70s

Patience 7

< Back to Patience

Tuesday

To prepare the old knotmeter through hull hole for patching, I ground the exterior to remove paint and taper back the laminate accordingly, as needed to install new flush fiberglass to cover the opening. This area of the hull was solid fiberglass with no core.  Inside, I sanded away the interior gelcoat/paint to bare fiberglass.  Then, I masked over the opening from inside, and filled the round hole with a thickened epoxy mixture.

A bit later, the epoxy plug had cured to the green stage, and I applied three layers of fiberglass in epoxy resin from the outside, and a layer on the inside to complete the structural patch.

To replace the ailing and ineffective self-contained bilge pump in the keel sump–which operation was hampered by the long hose run to the transom–the owner selected, at my suggestion, a remote-located diaphragm pump that would be more effective at dewatering and would avoid backflow issues into the tiny sump that we thought had kept the pump running too frequently during the previous season.  Because of where the existing discharge hose led (which I’d installed the year before), and also because it was a good location on its own, I chose to locate the new pump in a roomy storage space beneath the port settee.

After ensuring there was ample headroom for the pump, I prepared a basic cardboard template of the platform required, which would run between an internal structural member and the nearby hull for support.  I positioned and sized the platform to avoid the existing hoses and the hole through the structural stringer that led to the sump, and through which I’d run the suction hose.

From the template, I cut a platform from marine plywood, and after a test-fit and dry run with two fasteners on the inside, I epoxy-coated the bottom side and edges, then secured the platform in place with epoxy adhesive where it met the hull, and a pair of screws (and a little epoxy) at the inside.  Finally, with the platform in place, I epoxy-coated the top surface as well.

To give me a mounting location for the float switch that I’d install in the keel sump (thus avoiding fasteners directly into the bottom of the sump), I epoxied in a small fiberglass block, which I’d pre-drilled to accept the float switch later.

bilge6-52416

As it happened, there was a large hole in the starboard bulkhead just below the electrical service panel, where some old control panel had been installed, and this seemed a good location for the new bilge pump switch.  I cut a piece of teak plywood large enough to cover the old opening, and installed the new switch in the teak panel, which would cover the old hole and provide a convenient mounting spot for wiring and operation.

bilge7-52416

Down in the shop, I used the existing cabin sole pieces as exact patterns to cut new 12mm marine plywood to the correct sizes.  The largest piece, the aftermost one, had its bottom side routed out in way of the support cleats inside the boat, which I didn’t plan to emulate unless I absolutely had to.  At the moment, I could see no reason for lowering the apparent height of the aft piece.

Once I had the pieces trimmed to size as needed, and tapered to fit the hull (the small forward section only), I test-fit all three in the boat.  All fit well without a need for further trimming.

With the sole panels back on the bench, I prepared support cleats for the small access hatch over the bilge sump, and secured them in place with epoxy adhesive and temporary fasteners.  Then, I epoxy-coated the bottom sides and edges of the plywood panels.

Total time billed on this job today:  6.5 hours

0600 Weather Report:
58°, cloudy.  Forecast for the day:  clouds, maybe showers in the afternoon, low 60s

Precision 11

< Back to Precision 23

Monday

The final item outstanding from the original project list was new interior cushions, and these were now complete and looked terrific.  The color is sapphire blue.

< Back to Precision 23

Older posts Newer posts