Boat:

Skeedeen, a 1987 24' Crosby Striper

Schedule:

Project Schedule:  September 2020 – November 2020

Project Scope:  Hull paint; faux wood finish and relettering on transom; brightwork maintenance and other TBD

Project Complete:  144.25 Total Hours

Begin Daily Project Logs

October 20, 2020

Skeedeen Phase 6-18

Tuesday

Over the course of several elapsed hours early in the day, I applied six coats of a special base color required for the faux finishing on the transom.  I applied the extra coats to ensure there was plenty of paint for me to sand smooth and flat in advance of the faux.  I covered the entire transom with the base coat even though some areas, such as below the swim platform and at the edges, would later receive the regular hull color.

Total time billed on this job today:   4.25 hours

0600 Weather Observation:  45°, mostly cloudy.  Forecast for the day:  Mostly cloudy, 58°