Fritz 9

Boat:

Fritz, a 14' Handy Cat

Schedule:

Project Schedule:  May 2020

Project Scope:  Repair centerboard trunk; repair broken seat; miscellaneous maintenance and upgrades

Project Complete:  23 Total hours

Begin Daily Project Logs

May 21, 2020

Fritz 9

Thursday

Now that the paintwork on the centerboard trunk repairs was complete, I removed the masking tape.

Next, I reinstalled the two wooden seat assemblies; each had six screws to secure it to the support cleats beneath.

With that, the project was complete.

Total time billed on this job today:  .75 hours

0600 Weather Observation:  Clear, 40°.  Forecast for the day:  Sunny, 75°

Return to Fritz