Phase 2:  Framing 
					(Continued)After 
					a week away from the job, Bob and Rod were back the week 
					after Thanksgiving.  I had high hopes that, with decent 
					weather, they would make great progress on the roofing--the 
					next critical stage in the process.  | 
						 
                  Shop Home 
						Page 
					Shop 
						Planning 
					Phase 1:  Site Prep and Foundation 
					Phase 2:  Framing 
					Phase 3:  Finish Work 
					Phase 4:  Shop Setup | 
					 
					
						 
						
						 I 
						couldn't make it up to visit until Thursday, and was 
						surprised--and disappointed--to see that NO roofing had 
						been done.  There was a green tarp over the back 
						section of the building, and the shingles were waiting 
						on pallets, but for several reasons, no roofing was yet 
						done.Chief 
						amongst these reasons was the fact that Bob's newly 
						acquired hydraulic man-lift had failed, and was 
						undergoing repairs.  He had been counting on this 
						to help lift the shingles to the roof, and that was 
						fine.  There had also been some heavy rain on one 
						of the days.  Still, I was anxious to see some 
						roofing!  | 
					 
					
								| 
								 
								 
								
								 They 
								had, however, accomplished a bit of framing 
								elsewhere.  The dividing wall between the 
								office and the shop was built, which also 
								defined the doorways for the future bathroom and 
								utility room.  Bob had run into a problem 
								with this wall's placement, which was in large 
								part dictated by the plumbing rough-ins in the 
								slab.  We had carefully measured for the 
								rough-ins at an early stage, but something had 
								gone wrong.  As it turned out, it was my 
								basic shop drawings that were to blame, though I 
								didn't figure this out till later on.  The 
								end result, in any event, was that the wall 
								needed to be moved a foot or two further out 
								into the shop to allow for enough room in the 
								bath to install a toilet.  Certainly there 
								would be no moving the plumbing stacks!  | 
								 
					
						 
						I also met with the company installing my garage doors, 
						so that we could determine the ultimate door height and 
						the sizes of the rough openings.  The front wall of 
						the building was completely unframed, as we wanted to 
						ensure that the largest possible size doors be 
						installed.  With standard lift hardware, which 
						required 18" of clearance, it looked like I'd end up 
						with doors that were 15'-6" high, and 18'-0" wide.  
						This is pretty much where I had figured it would end up, 
						but it was nice to confirm it and move on in the 
						process.   With these measurements complete, 
						it would be a few weeks before the doors could be built 
						and installed. | 
					 
					
						 
						
						 Also 
						well underway was the framing and sheathing for the hip 
						roof over the little office bumpout in the back corner.  
						I left before the sheathing was done, but the framing 
						looked great, and began to truly define the shape of 
						things to come.  Additional pictures can be found 
						on the previous page. | 
					 
					
								| 
								 
								 
								
								 Every 
								job site needs a big summer sausage hanging from 
								a nearby stud, ready for one to hack off a hunk 
								if they become a bit peckish.  I had to 
								chuckle when I saw this as I passed through the 
								shop! 
								   | 
								 
					
								| 
								 
								 
								
								 Work continued inside and out.  One day I 
								arrived to find that the crew had installed 
								sheets of a waterproof roofing underlayment over 
								the entire roof, making the building essentially 
								watertight.  While I hoped for actual 
								roofing to be done soon, the new underlayment 
								meant that I could begin my electrical rough-in, 
								which I had been impatiently anticipating as the 
								weather began to slide inexorably into the realm 
								of downright cold.  | 
								 
					
								
								 
								
								       | 
								 
					
								| 
								 
								 
								The same day, Bob and Rod finished off the 
								garage door openings in the front, installing 
								headers and side framing.  The openings 
								were ready for doors once they were complete.  | 
								 
					
								
								 
								
								     
								
								     
								
								  | 
								 
					
								| 
								 
								 
								
								 The underlayment was just in time, too, as 
								within a week we had our first real snowfall of 
								the season, coupled with temperatures that chose 
								to stubbornly remain below freezing--well below, 
								on many days--for a couple weeks straight.  
								Fortunately, the crew took advantage of one nice 
								day and finished off the actual roofing on the 
								office hip roof, allowing more substantial work 
								to continue inside. 
								I moved forward 
								with the electrical installation. 
								Click here for more.  | 
								 
					
								| 
								  
								
								
								 Over 
								the next several days, while I was onsite daily 
								working on the wiring rough-in, Bob, Rod, and a 
								third crew--Tom--finished off a number of 
								projects, all important and all leading up to 
								the beginning of roofing.  They 
								straightened the gables and installed the 
								subfloor in the attic area, tying the whole 
								structure together significantly.  With 
								that done, they installed strapping on all the 
								ceilings, built and installed several interior 
								walls, and moved on to exterior trim, vinyl 
								soffits, and roofing drip edge.  The 
								pictures below tell the story, at least for now.  
								More detail on some of the areas will be 
								forthcoming.
  | 
								 
					
								
								 
								
								     
								
								     
								
								  | 
								 
					
								
								 
								
								     
								
								     
								
								 
								
								     
								
								     
								
								  
								
								     
								
								     
								
								   | 
								 
					
								| 
								 
								 
								
								 After 
								weeks of delay, the crew finally completed the 
								roof on Wednesday, December 21, after a very 
								efficient 2-day process.  Bob called in 
								lots of help--up to 5 guys--to get this job over 
								and done with.  Since I had completed the 
								wiring on Sunday, I didn't return to visit the 
								new shop until Wednesday, partly to check on the 
								progress and partly to deliver some materials to 
								the site.  I was pleasantly surprised upon 
								arrival to see one whole side of the roof 
								complete, and the other side 2/3 finished!  
								Excellent.  I was very pleased to finally 
								have this out of the way, since it was nearly 
								January.  For weeks, I had been worried 
								about the weather, and the possibility that a 
								stretch of bad or very cold weather might 
								prevent the roof from being done until late 
								winter.  | 
								 
					
								| 
								 
								 
								
								 I 
								suspect Bob was equally pleased to have the job 
								off his back; even though he didn't actually do 
								any of the roofing himself, there's no doubt the 
								absence of a real roof was weighing heavily upon 
								him. 
								
								The roof is shingled with Iko asphalt/fiberglass 
								shingles, with the so-called "architectural" 
								design, which not only provides a more 
								interesting textured look, they also are thicker 
								and last longer than regular 3-tab shingles.  
								I chose basic black, the color that goes with 
								everything.  The roofing crew did a great 
								job.  Watching their practiced motions, 
								with nary a wasted move, was fascinating.  | 
								 
					
								| 
								  
								
								
								 Nearly 
								a year ago, I was given a beautiful copper 
								weathervane and cupola, which were intended for 
								the "old" shop in North Yarmouth.  When, in 
								February, we decided to relocate, I postponed 
								installation of these decorative elements, 
								choosing instead to save them for the new 
								facility.  Now the time had come to install 
								them!  Bob wanted to have the cupola on 
								hand, so I made a second trip home and back to 
								pick it up and bring it up, so that it would be 
								ready to go.  I used a compass to align the 
								directional tabs on the weathervane with the top 
								of the cupola, with the cupola lined up with the 
								axis of the building.  Then, I installed 
								the base for the weathervane, a frustrating 
								process since I had failed to bring my entire 
								workshop of tools and supplies with me in the 
								truck; ah, the frustrations of working far from 
								home base.  With some cobbed-together 
								materials and purloined tools from the jobsite, 
								I managed to get the base installed. 
								 
								In 
								this photo, the large base is not shown; the 
								cupola will stand taller on the roof.  This 
								is a 42" cupola.  | 
								 
					
								| 
								  
								
								 Once 
								installed, the cupola and weathervane looked 
								perfect:  the focus was clearly on the 
								beautiful weathervane, which seemed ideally 
								proportioned for the size of the building, and 
								the cupola, while not overly small, was not so 
								large as to dominate the building.  I was 
								thrilled with how it looked, and how its 
								installation immediately created a more 
								finished, classy look to the building. 
								   | 
								 
					
								
								 
								
								  | 
								 
					
								| 
								  
								
								Click here to 
								continue... 
								   | 
								 
					
						
						This page was originally 
						posted on December 3, 2005.
							
								
									| 
									Updates | 
									
									 
									12/18/05  | 
								 
								
									|   | 
									
									 
									12/21/05  | 
								 
								
									| 
									 
									12/30/05  | 
								 
								
									|   | 
								 
							 
						  | 
					 
					 
					 |