Adeline 16

Boat:

Adeline, a 1987 22' Cape Dory Typhoon Sr.

Schedule:

Project Schedule:  April 2020

Scope of Project:  Assess and repair coach roof and mast support structure

Project Complete:  55 Total Hours

Begin Daily Project Logs

April 22, 2020

Adeline 16

Wednesday

The final task to complete the project was to install the new hinged mast step.  With all preparatory work already completed, now this was a simple chore of applying sealant and securing the base with four long bolts, large washers, and nuts.  Once the base plate was secured, I cleaned up the excess sealant, removed excess bolt length from inside, and attached the hinged top plate with its two pins.

To finish off the interior, where I’d cut a large hole in the liner to gain access to the underside of the deck, I installed the teak trim piece I’d made earlier.  Along the aft edge, where there were some small gaps, I installed a cosmetic bead of sealant to finish off the appearance.

With work complete, I cleaned up the decks, removing the protective coverings and completing the project.

Later, I moved Adeline back outside, parking her next to her sistership.

Total time billed on this job today:  2 hours

0600 Weather Observation:  30°, clear. Forecast for the day:  Sunny, increasing clouds, windy, 41°