(page 75 of 165)

Skeedeen Phase 6-4

Tuesday

The owner asked me to remove the old engine and clean up the engine room to prepare for whatever lay ahead in that department (still pending), so to begin I removed the engine box cover for full access, storing the box at the aft end of the cockpit for now.

With clear access, and beginning at the aft end, I systematically began disconnecting and removing anything securing the engine to the boat, starting with control cables for shifter and throttle and the engine main wiring harness plug.  For better access to this space, before beginning I removed one of two exhaust hose lengths leftover from the original installation; this was difficult and time-consuming, and for now I left the port hose in place, as it was not impeding access.

Continuing, I unbolted the shaft coupling and pulled it just aft of the transmission.  Before doing this, I used some masking tape to mark the shaft where it exited the hull below, for future reference in positioning and alignment.  The metal disc of the dripless packing box prevented the shaft from moving too far aft, but it was enough and I didn’t bother loosening the disc.

I removed several green grounding and bonding wires from the after engine grounds, and removed the raw water intake hose from the engine inlet.

I removed the positive and negative battery cables from their respective attachment points, and removed and plugged the fuel line at the secondary fuel filter.  I also plugged another length of what appeared to be fuel line, but later I realized it was probably the raw water injection line leading to the packing box (which line was made from fuel hose).

Now all that remained was to remove the lags holding the engine mounts to the stringers, and to secure for storage all the loose and sundry semi-dismantled engine parts left dangling by the service yard during the initial diagnosis, including a control box, the remote oil filter, spark plug wires, and portions of the cooling system at the front of the engine.

After debating with myself during the morning’s work whether to move my crane from its spot in the second work bay, or to move the boat over to the crane, I decided to move the crane to the boat.  Normally I hate doing this because the crane is large and heavy, and if the ground outside is remotely soft, it digs in and is hard and frankly dangerous to move, but since apparently it never rains in Maine anymore in the summer, the ground was nearly as hard as tarmac, so I decided in this case it was just more efficient to move the crane.  I had to move a lot of stuff out of the way in both bays to allow the crane’s passage.

Once the crane was in position, in short order I had the engine hooked up and it was soon over the side and safely on the ground, where I stored it on a rolling platform pending its final disposition.

The engine room was filthy beneath the engine, and a good cleanup had been long awaited.

I began by wiping out some of the spooge, then installed the hull plug and filled the bilge with soapy water to let soak for a while.  After a while, I agitated the water and scrubbed the spaces with a brush, then drained the water and cleaned up the accessible spaces as much as possible for now, including the after portion of the bilge near the transom.  There remained behind some greasy residue and dirt that I’d continue working on next time, along with cleaning up the adjacent spaces and wire/hose bundles as much as possible.

Total time billed on this job today:  6 hours

0600 Weather Observation:  50°, foggy.  Forecast for the day:  Mainly cloudy, chance of a shower, sun in the afternoon, 74°

Skeedeen Phase 6-3

Monday

I continued where I left off with the port engine room vent.  After a few more failed attempts to get locking pliers on the nuts of the two middle bolts (the tight space and awkward angle made it apparently impossible for me to get a good grip), I managed to eventually remove these two bolts by arranging an open-end wrench on the nut and hoping it would stay in place while I turned the screws from outside.    I had to reset the wrench two different times on the second nut, but otherwise this approach was ultimately successful.

For the final, forwardmost upper nut, I knew I couldn’t reach it from inside, so I ground off the head enough from outside so I could remove the vent cover.  Since these plastic covers were not to be reused (though I wanted to keep them intact for templates), I didn’t worry about grinding a bit into the plastic to get the screw head free.  Once the plastic vent was removed–as with the opposite side, this one was well-bedded to the hull), I cut off the remains of the screw head and pushed the bolt through to the inside.

The various vent hoses–two per side–appeared to be original and, along with the bilge blower, were slated to be replaced at this juncture.  One hose on each side ran all the way into the bilge beneath the engine (the other on each side were shorter), and I found they were secured in a few places along the way, so now I released the bounds and removed these hoses from the boat.  They were filthy with dirt, debris, and belt dust.

Late in the summer, the engine had had an overheating problem, and the engine room was filled with various engine and exhaust parts that the service yard had left there after diagnosing and inspecting the engine a few weeks back.  To clear the way, I removed all these loose parts, setting them aside for safekeeping.

After removal, the engine room looked better already:

Meanwhile, I continued with some of the exterior hardware removal, the first baby steps towards preparing the hull for painting.  With a little time left before the end of the day, I removed the scupper flaps, and a pair of SS half oval trims from the lower rubrails on the hull.

Total time billed on this job today: 2.75 hours

0600 Weather Observation:  50°, foggy, rain showers.  Forecast for the day:  Mainly cloudy, chance of showers, 70°

Skeedeen Phase 6-2

Friday

To begin, I moved Skeedeen into the workshop, setting her up level fore and aft and side to side.

Later, I returned to the starboard vent removal.  I decided to drill out the screw head on the final bolt, since I couldn’t think of a way to get to the inside.  While this approach was ultimately effective, it was still time-consuming and difficult, since the screw tended to spin while being drilled, but eventually I removed enough of the head to pry free the vent itself (which was well-bedded with sealant).  The original dark green hull color was visible beneath the vent face, and the hull core seemed to have been effectively sealed so far, but I thought it would probably be good to remove the sealant and some of the core from the opening in favor of some solid epoxy to better seal the opening going forward.  The plastic vent box inside the hull was also sealed in place, and I planned to leave it as is.

Forearmed with the knowledge of the vents’ installation now, I turned to the port side, and after some minor disassembly within the access panel soon had the locking pliers in place on the four lower nuts, and then from outside presently removed the four lower bolts.  I removed the aftermost, and most visible, bolt from the top set, but after struggling with the next couple–access on this side was even tighter than to starboard–I’d reached the end of the day and decided to attack the final three bolts fresh next time.

Total time billed on this job today:  2.25 hours

0600 Weather Observation:  Clear, 50°.  Forecast for the day:  Sunny, 75°

Skeedeen Phase 6-1

Thursday

Skeedeen arrived at the shop for another round of work, this time focused on repainting the hull, with the added interest of having a local artisan paint the transom in faux teak woodgrain, something both the owner and I were looking forward to watching come together.

The boat had recently spent some time at another boatyard because of some engine problems, and as a result she was quite dirty.  I’d had the boat hauler drop the boat outdoors so I could start by washing the whole boat to remove boatyard grime and dirt, which was my first task.

Preparing for the work ahead, I documented the existing condition of the hull for later reference.  The existing paint, which had been applied sometime before the current owner bought the boat over 12 years ago, was still in good condition with only minor wear, oxidation, and fading.

I planned to start the project in earnest soon, but one of the first tasks I intended to complete was to remove the existing black plastic engine room vents on each side of the hull.  The owner and I had talked about having new vents made from bronze, through some contacts at a local yard, and I hoped to remove the old vents forthwith so they could be replicated as soon as possible.

Starting on the starboard side, I thought I’d quickly remove the vents with a screwdriver, but immediately I found that to my dismay, the vents were throughbolted.  Removing an access panel in the cockpit liner, I found to my further dismay that the vents weren’t directly accessible through the panel:  In fact, the vents were completely forward of the opening, and the narrow space within would make access to the eight nuts and bolts difficult.   Various installations also in the compartment further complicated the access.  The vent box and grill had clearly been installed in the boat before the deck and liner were assembled during original construction, and had equally clearly never been touched or removed before.

To improve access, I unclamped the two corrugated bilge pump hoses from their outlets in the hull, and moved the hoses out of the way.  Then, I removed the bilge blower and its hoses, along with another length of vent/intake hose further forward.  Also in the mix was an old septic system vented loop, which had been disconnected many years earlier, and now with relatively clear access I could remove this from the space permanently as well.

With the clutter out of the way, at least I had a chance of accessing the nuts, though the tight confines of the space and the shape of the vent box itself made it impossible to use regular wrenches or sockets on the nuts.  I managed to get four pairs of locking pliers on the lower nuts, and from outside the boat removed the screws without much added difficulty.  Then, working one at a time because the access to the top side of the vent box was so poor, I removed three of the four nuts there, but simply and physically could not manipulate any wrench or pliers as far forward as the top forwardmost nut.  I left dealing with that for another day.

Total time billed on this job today:  2.5 hours

0600 Weather Observation:  Clear, 50°.  Forecast for the day:  Sunny, 75°

 

Scupper 263

Wednesday

Early in the week before the scheduled and planned departure of Sea Breeze from the shop, the shipper contacted me to ask if the boat was ready (yes indeed) and if it would be OK to pick her up on Thursday, rather than the following Monday.  That was certainly OK with me, but the next day he called again and wanted to move it up to Wednesday, which was also fine by me.

So on the appointed date and time, the first stage of the transport began at the shop with the arrival of the hydraulic trailer that would bring the boat to a nearby (as nearby as anything here) yard, where they’d transfer the boat to a lowboy trailer for the long trip to Florida.

Loading the boat was without drama or issue, and before long she was outdoors for the first time since March 16, 2018, which was the true beginning of the project despite a week or so of work that I’d done the previous fall.  With several breaks in the action between then and the actual completion of the project in March 2020, the boat had regardless been in the shop throughout, and had become a familiar fixture therein.  It was nice to see her back out in full view and daylight once more.  I took a video of her emerging from the shop, but alas, something went wrong (user error) and the only usable footage was 4 seconds at the end with the camera pointing at the ground.  (I come from the pre-video era, folks.)

Once outdoors, we loaded the mast on the outriggers on the trailer, and the driver strapped down the boat and made other final preparations.

The truck departed around 1245.  From here, once past my traditional (now with barely an opening in the brush) final departure photo angle at the end of the driveway, the boat was beyond my purview, but I looked forward to hearing of her successful arrival in Florida, and her successful commissioning shortly thereafter.

Return to Scupper Home Page

Scupper 262

At the end of March and with the completion of the project, I prepared the boat generally for transport to the owner’s new location in Florida.  I packed various loose gear into several lockers in the boat, and filled the cockpit lockers with sails old and new, stowing everything carefully to prepare for the boat’s long over-the-road journey ahead.

With the country embroiled in the various lockdowns and restrictions related to the advent of COVID-19 in March, along with additional complications at the owner’s end and this country’s utter inability to better handle (or in certain circles even properly acknowledge) the spread of the virus, transportation of the boat was delayed for several months, during which time I maintained the boat indoors for protection, keeping the batteries topped off with weekly charging.

Towards the end of the summer, the owner, having moved to Florida and taken care of the boat registration  and other requirements, scheduled a transport date of August 24.  With this date a few weeks ahead, I took care of a short list of final preparations, including storing the full-length mainsail battens and main boom in the cabin, all carefully secured and chafe-protected within.  I also moved the mast around to the front of the shop where it’d be readily accessible for the truck.  Back in March, I’d wrapped the spars in plastic for protection during transportation; with the delay in shipment, I covered the stored mast with additional heavy tarps for extra protection and to keep the clear plastic from falling apart in the sun and weather, but now I removed the excess tarps.

Also, at the owner’s request I installed the garboard drain plug in advance, so the commissioning yard wouldn’t have to worry about its proper installation.  I used a small amount of sealant on the threads, and screwed in the plug tightly before coating the plug with bottom paint when I took care of the jackstand patches.  Since this particular hard bottom paint had a limited time it could be exposed before launching, the owner chose to have the commissioning yard apply a second and final coat over the whole bottom in Florida.

On deck, I made sure all the locker lids and companionway were secured properly, and added small bolts through the locking holes just to ensure the latches couldn’t spring open unintentionally.  With all loose gear, canvas covers, and so forth stowed below, and the tiller secured, the boat was ready above and belowdecks for her relocation.  Note that for transport purposes, I chose to use the ugly old plywood companionway drop board, keeping the newly-made versions safely in the cabin.

With the new registration from the owner, I had a set of numbers made up for the bow of the boat, using the same gold leaf and dark blue outline as with the name on the transom, but in a basic block to satisfy the display requirements.  With an indicated state requirement to display properly the HIN on the transom–if there’d ever been a stamped or molded number there it was long gone by the time I started the project–I had a set of the numbers made up from vinyl and installed them on the upper starboard side of the transom as well.

 

Maya 10

Friday

The primer was well-cured overnight, and to begin I lightly sanded the hull to smooth the primer and prepare it for whatever topcoat the owner chose (final painting was outside my project scope).  It was easy and quick to sand the primer, and afterwards I removed the masking tape, vacuumed, and solvent-washed to complete the project.

<Back to Maya

Total time billed on this job today:  .0.5 hours

0600 Weather Observation:  62°, fog.   Forecast for the day:  Becoming mostly sunny, 83°

Maya 9

Thursday

After letting the new varnish sit for more than a day, I turned the boat over carefully and propped it on some saw horses to raise the hull to a comfortable working level.  As I was masking off varnished gunwale and the waterline, I discovered a series of old holes in the transom that I’d not noticed before, so before I could get to the primer I had to prepare and epoxy-fill these holes.

Fortunately, it was a very warm day, and with some heat lamps trained on the epoxy to help even further, the filler cured sufficiently to allow sanding after lunch, enabling me to continue with masking and final primer preparations.

With cleaning, masking, and other preparations complete, I applied the first of two planned coats of white primer.

After a few hours, I could go right over with a second coat.

Total time billed on this job today:  1.75 hours

0600 Weather Observation: 60°, fog.  Forecast for the day:  Sunny, 87°

Maya 8

Wednesday

The owner asked me to fill a series of small, abandoned fastener holes in the hull, just beneath the gunwale, so to start the day I prepared the holes by using a countersink to enlarge them a bit, then, after masking over the insides, filled the holes with an epoxy mixture.  Later in the day, this had cured enough for me to sand and refill as needed.

With the varnish work complete, I removed all the masking tape, and reassembled the support beneath the center thwart.  Then, I secured the after oarlocks with new bronze screws.

Otherwise, I let the fresh varnish sit for most of the day, giving it additional cure time before I had to flip the boat over and prime the hull, which would by my next (and final) task according to the project scope.

Total time billed on this job today:  0.5 hour

0600 Weather Observation: 60°, cloudy.  Forecast for the day:  Cloudy, thunderstorms in the afternoon, 82°

Maya 7

Tuesday

After a light sanding and thorough cleanup, I applied the sixth coat of gloss varnish to the thwarts, gunwales, and other woodwork in the dinghy.

Total time billed on this job today:  1 hour

0600 Weather Observation: 66°, mainly clear.  Forecast for the day:  Mostly sunny, 76°

Older posts Newer posts