(page 158 of 167)

Danusia 14

< Back to Danusia

Tuesday

After finishing up the last of the masking, and other final preparations, I applied a sealer coat of varnish to all the newly-bare wood.  With an afternoon commitment, and not knowing how long the varnish work would take, I started earlier than later to ensure completion and to better gauge future days’ varnishing timing.

Total time billed on this job today:  3 hours

0600 Weather Report:
10°, clear.  Forecast for the day:  Increasing clouds, snow by evening, high around 30

Danusia 13

< Back to Danusia

Monday

To begin, I finished up the final bits of sanding and prep, taking care of a few tight hand spots and the anchor platform.

Afterwards, I cleaned up the boat and shop, and vacuumed and solvent-washed the deck and trim as necessary to prepare for the day’s main focus, which was to start masking off the newly-bare trim for varnishing.  By the end of the day, I’d  completed most of the masking, with just a little remaining to complete next time.

Total time billed on this job today:  6.5 hours

0600 Weather Report:
34°, partly cloudy.  Forecast for the day:  growing colder, mainly sunny.

Nomad 17

< Back to Nomad

Saturday

With the fresh new hull looking good, it only followed that my next tasks needed to focus on the deck areas, which currently looked downtrodden and neglected.  This boat had obviously spent a lot of time stored outdoors, whether covered or otherwise, and there were signs that the boat had been powerwashed to remove the worst of the dirt and neglect, with the stroke marks of the nozzle clearly evident.  But despite this, the original gelcoat was in essentially good condition beneath the remaining dirt and oxidation, and I’d known from the getgo that I could salvage the original finish on the deck, a great time-and labor-saver.  I only took a few photos showing the decks’ condition on this day, but other entries in this project log at the beginning of the project also show the original condition.

As anticipated, it took very little work to clean up the original gelcoat with a finishing compound, which I applied and buffed by hand.  This removed dirt and oxidation, and restored color and shine to the gelcoat.  Over the course of a few hours, I polished most of the deck areas, excepting the two cockpit wells, which I left for another time.   But the main portions of the deck were done, and looked much better next to the shiny new hull.

Total time billed on this job today:  2.5 hours

0600 Weather Report:
Snow flurries, 22°.  Forecast for the day:  Partly sunny, 35°

Danusia 12

< Back to Danusia

Friday

During the day, I finished up most of the remaining sanding work, starting with the starboard eyebrow trim and coaming, then working around the taffrail before moving on deck to hand-sand the handrails and various coachroof trim.  Later, I sanded the cockpit coamings and surrounding trim, leaving only the hard-to-reach pockets at the forward ends of the coamings for later attention–my hands couldn’t face any more just then.  I’d also have to finish up the anchor platform, which I’d not yet touched.  But the bulk of the prep was complete, for which I was grateful.

Total time billed on this job today:  5.75 hours

0600 Weather Report:
10°, clear.  Forecast for the day:  Sun, then increasing clouds, high in the low 30s

Danusia 11

< Back to Danusia

Thursday

Now that all the old finish was stripped, it was time to sand the raw wood to remove any final vestiges of old finish and smooth the wood to prepare for the new coating.  Starting on the port side, I sanded the toerail, eyebrow, and outboard coaming through the grits as required to clean up the wood and brighten any weathered spots.  Because of the small size and various profiles involved, most of this work was by hand, though I could use a palm sander on the coaming.

I continued the work on the starboard side, completing the toerail sanding before the end of the day.

Total time billed on this job today:  6.25 hours

0600 Weather Report:
5°, clear.  Forecast for the day:  Sunny, high in the 30s

Danusia 10

< Back to Danusia

Wednesday

Picking up where I left off, I continued stripping the brightwork on the port side, finishing up the outboard side of the coaming and the eyebrow trim and handrail on the cabin.

I moved my operation from the staging to the deck itself so I could continue with the remaining brightwork on the cabin top and inside the cockpit.  As with all the other wood, this woodwork was in basically good condition beneath old and weathered layers of Cetol.

During the rest of the day, I removed the old finish from these remaining areas, completing the raw stripping work on deck.  A few removable pieces, such as the swashboards and cockpit table, remained to be done, but I could do those on the bench anytime.

Total time billed on this job today:  7.5 hours

0600 Weather Report:
0°, clear.  Forecast for the day:  Sunny, temperature rising to the low 30s

Danusia 9

< Back to Danusia

Tuesday

Before getting back to the brightwork, I decided to finish up the garboard drain installation.  To begin, I dry-fit the bronze assembly and drilled and tapped the hull for four #10 machine screws that would secure the fitting.

After cleaning up the bonding surface, I installed the fitting with 5200 sealant.  I left the plug out and placed it, along with its wrench, in the boat for safekeeping.

I continued work on the starboard side of the boat, and stripped everything else I could reach from the staging, including the outboard side of the cockpit coaming and cabintop handrail, and then worked around the taffrail.

I continued my way up the port side, starting with woodwork that was in more or less the same condition as the starboard side.

By the end of the day, I’d stripped the port toerail and rubrail, along with the remaining half of the bow platform.

Total time billed on this job today:  7 Hours

0600 Weather Report:
0°, clear.  Forecast for the day:  sunny, high around 20

Danusia 8

< Back to Danusia

Monday

After a morning appointment away from the shop, I prepared to begin stripping the old finish from the exterior brightwork.  The original finish, an opaque, heavily-colored coating called Cetol, had been well-maintained over most of the boat’s life and, despite a few recent coatings failures, had well-protected the original woodwork beneath, but it was time to start over and remove all the old finish before recoating.  For now, I focused on the starboard side.

Where possible, I removed fittings that were in the way, such as the anchor roller and stop and assorted screwed-on installations.  I didn’t attempt to remove anything that was through-bolted.   Then, with a scraper and heat gun, I started at the starboard bow platform and removed the old finish from the platform, and eventually worked my way aft along the entire toerail and rubrail to strip the finish to the bare wood.  I also had time to strip the eyebrow trim before the end of the day.

I’d continue with other parts of the boat in the days ahead.

 

Total time billed on this job today:  5 hours

0600 Weather Report:
20°, clear.  Forecast for the day:  Mainly clear, highs in the 20s but falling

Nomad 16

< Back to Nomad

Sunday

With all the spray painting complete, I removed all the masking tape, paper, and plastic, exposing the boat again in full for the first time since I first taped her (or will it be him?) up several months earlier.  It was great to see the whole boat again, and with the fresh new hull I was inspired anew to attack the original decks (badly in need of cleaning, polishing, and varnish work) and interior.  I’d postponed–actively and otherwise–work on the hull for a long time, but it was great to be on the other side of the hull work.  I’d been wanting to use this paint color for ages and it had always been my vision as I imagined what this boat would become.

I’d seen this apparent phenomenon before, on another boat with another color,  but I think the paint got darker as it continued its curing process.  Now it looked much more like the expected result; at first it had seemed a little brighter.

The final step required to bring the new appearance of the boat together was to paint the bottom.  This was a purely aesthetic requirement, as I expected the boat to live on the trailer so antifouling wasn’t strictly necessary, but the old red paint had to go.  After masking off along the bottom edge of the boottop, I painted the visible areas of the bottom.  I didn’t worry about the underside where things weren’t visible, and anyway, the trailer mostly got in the way of these areas and would have prohibited a decent paint job regardless.  As a final touch, I added a gold leaf stripe just beneath the character line in the hull, where there had originally been a thin gold stripe.  The devil is in the details.

Total time billed on this job today:  3.75 hours

0600 Weather Report:
22°, clear.  Forecast for the day:  Mostly cloudy, 34°

Nomad 15

< Back to Nomad

Friday

After giving the hull paint a full extra day to cure (almost 48 hours total), I was looking forward to to finishing the boottop, which required plenty of masking work to get ready.

As usual, I began with a narrow strip of special vinyl fine-line tape (1/2″) at the top edge of the boottop, which would help provide a crisp, clean paint line there.  Then, I applied a layer of 1″ masking tape, covering as much of the vinyl tape as possible  because overspray on the vinyl, which was non-absorbent, would tend to run down onto the boottop below, and, when cured, would also tend to create annoying feathers of paint that didn’t stick to the vinyl and therefore wouldn’t peel off cleanly during removal.

With the top of the stripe now taped off, I spent another hour or so draping the hull from the gunwale to the boottop with plastic sheeting and then, because I never trust the plastic entirely like this, a 12″ wide strip of masking paper at the lower edge, just to safeguard against any of the boottop paint getting on the new hull.  It seemed excessive, as always, but the peace of mind was worth the extra effort.   Covering the entire hull in order to spray a 2″ stripe seemed ridiculous sometimes, but there you are.

To complete the masking, I covered the raised forward bulwarks with more paper and tape.

After final preparations, I applied three coats of Alexseal off-white gloss topcoat to the boottop.  This color would tie in well with the off-white color of the original decks, which were in good-enough condition and would stay as is.

Total time billed on this job today:    3.75 hours

0600 Weather Report:
25°, clouds.  Forecast for the day:  Partly sunny, 36°

Older posts Newer posts