|
|||
|
~ The bLog Home ~ |
||
Click here to continue with the logs from October 17 to October 31. | |||
MONDAY, OCTOBER 16, 2006 |
|||
After three days away from the
jobsite, I was anxious to get back to work. I began bright and
early with my habitual pre-dawn journey to Lowe's to pick up a wide
variety of items, from a toilet to outlet face plates, from drywall
mud to finish nails, and from tape measures to shower drain fitting. I arrived back home before 8, and unloaded my haul. It was at about this point that I noticed that my toilet box read "round front"...uh-oh. From the display at the store, it seemed like the Kohler Wellington--a unit we had used previously with good success--came only with the elongated bowl, which I wanted. I opened the box and confirmed by fears: this was the wrong thing. Grr. I was not pleased with this development. Will I ever learn to double check the things I pick up? And why wasn't it more clear that there was a choice, and that the stack from which I took my unit was round and not elongated in the first place, Mr. Lowe? I managed to get past this annoyance, and since I wasn't sure if Bob would want or need my help today, I sort of dubbed around on some smaller things while I waited for him to arrive. I thought I'd install the outlet face plates in the kitchen, to cover the outlets I installed a while back. I opened the first one and installed it, and noticed immediately that the color didn't match. I had installed tan outlets, and had picked up tan faceplates. What gives? It turns out I had actually (and without knowing so) installed almond outlets, while my faceplates were ivory. Come on, will you? They're both nearly the same color, but just incrementally different enough to be blatantly noticeable if compared directly. I thought there were three choices: white, tan, and brown. But almond and ivory? Isn't this placing too fine a point on an el-cheapo receptacle? It never crossed my mind to consider that there might be a different tan. I was extremely annoyed at this, which, on top of the toilet debacle, more or less negated my entire trip of the morning. I almost headed right back immediately, but logic prevailed and instead I made plans to return tomorrow morning--aggravating, but better to just go and get the exchanges done. Besides, I had been looking forward to an operating bathroom in the house, and didn't want to delay much longer. |
|||
When Bob arrived, we eventually decided that he could do most of the work alone, and that I would work inside as necessary, though of course I'd be available at any time to help out as needed outside. So I got to work on the mud in the upstairs, and applied a third coat to the upper part of the bathroom, and a second coat to the remaining areas of the closet with the new bucket that I had picked up. |
|||
Next, I installed the vanity cabinet in the downstairs bathroom. This went smoothly, and I didn't even need to shim it for level. I did shim behind the solid pine back supports since I had to hold the cabinet slightly away from the wall to clear the electrical wiring running to the outlet box above the cabinet. For this cabinet, we chose a maple frame painted Jamestown blue, with white maple drawer fronts and doors with a Shaker bead. The drawer fronts ended up a bit more blank than I had expected, but since we had yet to choose our hardware it seemed that some good hardware could liven things up. Otherwise, I liked the cabinet. Later (soon), I'll build and install a standard Formica countertop. |
|||
I installed a drain fitting in the downstairs shower pan in preparation for the final connection in the basement. I bedded the fitting in lots of plumber's putty and tightened the nut from the basement beneath. I also installed the closet flange in the floor. |
|||
![]() |
|||
I finished up the day by installing 5 or 6 of the cheap porcelain light fixtures in the basement. I had installed 11 boxes some weeks ago, along with the wiring, and now I began to wire these up so that I'd have light in the basement; I figured my cutting station would probably move down here sooner than later, once the finish floor was installed upstairs. I hated installing these cheap fixtures. I just don't understand why the manufacturer couldn't leave more room around the screws for the wires; things were extremely tight, particularly for the 12 ga. wire I was using. Would it have killed them to leave 1/4" clearance around the screw, rather than to have it nearly butted directly against the molded contours of the back side of the fixture? Who designs these things? |
|||
While I worked inside, Bob worked on the deck framing, picking up where we left off last Wednesday. New material had been delivered Friday, sometime after we left for the weekend, and he finished installing the joists, cut the ends to length, and installed the double box frame. I helped hold some of the larger pieces of the box frame, but that was about it. He also installed some blocking in the area where the front porch met the large deck off the south end, where we planned to miter cut the deck boards.
|
|||
THURSDAY, OCTOBER 12, 2006 |
|||
We had heavy rain and very strong
winds overnight, which kept me awake for a time. When I
arrived at the house this morning and climbed the basement stairs,
imagine my surprise to see a large puddle of water in the hallway at
the top of the stairs!
I located a few other leaks here and there, mostly around windows and doors, probably since I had done no exterior work on the windows and doors, and they still required caulking, rubberized flashing, and trim. Small leaks were no surprise here. The tarp covering the fireplace opening was still in place, but water had driven beneath it--no surprise at all here. I guess I should be glad the tarp survived the night. Anyway, no harm was done, but I resolved to take care of these exterior projects as soon as I reasonably could. |
|||
![]() I replaced the first cabinet and spent some more time leveling and positioning it. This was made challenging by the fact that the floor began to drop off significantly between the sink base and this peninsula cabinet, and they were not directly connected thanks to the gap in between for the eventual dishwasher. I had to raise the cabinet nearly 1/4" with shims, but after some fussing I got it level in all directions, and with the other cabinets. The proper positioning was very important, of course, since not only did the peninsula have to align and level properly with the other cabinets, but the first cabinet would also be the benchmark for the remaining peninsula. Once I had it right, I screwed it to the blocking through the toekick and the cabinet side. I continued with the other cabinets in the peninsula, though these went more quickly since I had the accurate first cabinet to use as a reference. When I reached the corner cabinet at the outer edge, where the peninsula makes a 90° turn, I discovered a problem, though: the cabinets were 3" short of my layout. I checked for any spacers or fillers that should be in there; none were noted. I double checked the physical measurement, but was still 3" short. This wasn't necessarily the end of the world, but I wanted all the counterpace I could, and besides: the extra 3" made the cabinets relate better to the nearby log post. I decided to measure each cabinet box to ensure that I wasn't sent the wrong thing. I immediately discovered that the blind end cabinet, the first one in the line, was 36" long, where it was designated as a 39". There were my missing three inches. |
|||
![]() The only problem was that by using one of these spacers, I'd end up short later on, when I needed one on one side of the range hood. But I had no need for this right at the moment, and figured I could easily get a replacement. This was my suggestion to Wendy, along with double-checking to ensure that I got the right or wrong cabinet, and was appropriately charged. Later, I heard back, and she told me that the cabinet company said the 39" blind corner cabinet is supposed to be 36". Huh? Come on, now. All cabinets are designated by an alphanumeric code that usually includes letters as shorthand for the cabinet type (i.e. W for wall, SB for sink base), followed by a number that indicates the cabinet length. This is standard in the industry, and all other cabinets ordered from this company were so designated--and accurately so. The cabinet in question was called a "BC39L", for "blind corner, left side"...and 39" long. It also came in a 42" and 48" version, but not a 36". This was a ridiculous explanation, but whatever. I had already finished the entire installation by the time I heard this, and had implemented my solution. Who can wait around for silliness like this? |
|||
I installed the spacer, and then the corner cabinet before turning the corner and installing the final base cabinet in the second peninsula. I finished this up at 10:30.
I was done with the kitchen cabinets before I originally even thought they'd arrive. Pretty good. Now, I wished that I'd had the granite people come earlier instead of way off on next Thursday, but if I'd scheduled them too soon probably something would have gone wrong and I would have had to really push to get done. Now, I could relax, knowing that the cabinets were all set, and focus on the myriad other jobs. I love the cabinets. They look great, and seem pretty well made. Would you believe I actually had to sign a waiver, at the time of ordering, stating that I understood that they were wood cabinets and that the paint might crack at the joints between the various pieces of the face frame? The thought that someone might not expect this just makes me shake my head. I suggest some nice white Formica cabinets for those people who can't seem to handle the natural characteristics of wood. |
|||
![]() |
|||
After lunch, I mixed the grout and then grouted the floor. I like grouting: you make a big mess, and then clean it up. Grouting small joints, like those in this tile, is particularly straightforward, since there's less tendency to remove too much or too little of the grout from the joints. We chose "warm gray" grout. |
|||
Next, I lugged the remaining cement board (about 11 sheets and some scrap) up to the bedroom upstairs so that I could begin installing it in the upstairs bath. Why is this stuff in 3x5 sheets? I know that weight of the product has to be limited, but still. Neither direction is the proper dimension to fit conventional stud spacing, so that means that each sheet must be cut when hanging on a wall. What a ridiculous product. They should be at least something like 3x4, so that it would fit the stud spacing. Things'll be different when I'm in charge, let me tell you. |
|||
![]() I ran out of steam by about 5:30 and called it a day. I had hoped to install that strip at the top, but I just couldn't bring myself to fight another piece. No updates till Monday, folks. See you then! |
|||
WEDNESDAY, OCTOBER 11, 2006 |
|||
I had a little time this morning
before Bob arrived to start installing the sheets of Homosote
material on the loft deck. The purpose of this material is to
acoustically insulate the hardwood flooring planned for here from
the ceiling boards and joists beneath, so that every footfall
doesn't creak and echo through the house. We only needed it in
this small area since the remainder of the upstairs is either carpet
or tile. I installed three full sheets of the Homosote in a bed of construction adhesive, nailing it to the joists beneath and being careful near the wall to avoid the wires running to the kitchen lights. But Bob arrived earlier than expected, so this was all I got done at this point. |
|||
We continued with the deck framing outside. I installed some solid bridging in the screen porch deck frame while Bob did some layout, and then we used Bob's transit level to determine the height at which the final deck posts needed to be cut--and then cut them off at this height.
Sorry...it was getting dark by the time I got around to taking these pictures of the decks! |
|||
It was about 11. We discussed a plan of attack for a while, and considered going to pick up material immediately, but it was enough pieces that it would have been tough to fit even on Bob's truck, and eventually we decided to order it from Moose Creek. Factors in this decision also included the fact that my cabinets were due any time this morning, and that of course Bob had lots to do on Will's house. With lousy weather forecast for Thursday, and since we had plans to be away during the weekend, it just made sense to get going again on Monday, armed with the material we needed. |
|||
![]() It was great that the cabinets came a day early, as it meant that it was likely that I'd have the whole kitchen installed before we went away on Friday morning. That will make for a much happier and more relaxed Tim during our mini-vacation! |
|||
![]() |
|||
![]() The cabinet company didn't provide installation screws, annoyingly; every cabinet I've installed in the past has had a little packet of screws included. Fortunately, I found some stainless steel pan head screws in the boat shop that would work, so I was back in business without needing to waste half the afternoon driving to buy some. |
|||
![]() |
|||
![]() I placed the first cabinet for the peninsula in position, but didn't secure it yet, since I needed to add blocking to the floor sot hat the cabinets would be able to be screwed in place. At this point, I called it a day, feeling good about my progress and sure that I could easily finish the installation tomorrow. |
|||
TUESDAY, OCTOBER 10, 2006 |
|||
Happy birthday Dad! I had time this morning to apply the second coat of mud to the sheetrock in the bathroom (just the top areas; the lower sections will wait till the top is done). Then, I had just enough time to run down and pick up a spec sheet for the porch materials that I needed before Bob arrived around 8. We got right to work on the front porch frame, and before long had the ledger board secured to the house. The ledger board supports the joists, and we secured it 7-3/8" below the bottom of the first log, to provide the proper step-down. This meant that part of the ledger was up in the house framing, and part overhung the foundation. We secured it to the house box sill at the top with 4" Tap-Con screws, and every so often the to concrete foundation with special concrete lags. |
|||
![]() |
|||
With the beam complete, We cut 8' joists roughly to length from 16' 2x10 stock, and Bob toenailed them to the ledger board. I followed behind and installed joist hangers, and when they were all nailed Bob measured out the exact distance at each end joist, snapped a chalk line, and cut off the excess. Then, we installed a double box sill outside of the joists, completing the basic porch framing. |
|||
![]() After Bob left, I cleaned up a bit, and then went inside and mudded and taped the lower portions of the closet upstairs, which took the rest of the afternoon. It looks like the cabinets are coming tomorrow instead of Thursday, so that's good news! Can't wait to see them. |
|||
MONDAY, OCTOBER 9, 2006 |
|||
I knew Bob was on his way sometime
this morning with pump jack staging to set up on the back of the
house, and I figured he'd arrive a little later in the morning, so I
filled the first couple hours of the day with some smaller projects. First, I mixed up a small amount of mortar and filled in some of the space beneath the future vanity cabinet in the bathroom with the leftover tile, and also filled in some small pieces around the toilet pipe. I didn't worry here about whether the pieces fit the pattern or not, since they'll be hidden, but I wanted the area to be as level as possible, and didn't want to have to use excess grout later. |
|||
![]() |
|||
![]() |
|||
![]() |
|||
We spent some time discussing the porch and deck construction, and soon determined that we needed some lags and fasteners to get started. So Bob left to pick those up, and to spend the remainder of the day working on his son's house, which he has been building in his "spare" time since about January. This was fine with me, since I had plenty to do. |
|||
![]() |
|||
![]() These pieces represented the end of the rock hanging, finally! There was no more to be done. Never mind the cement board that I have to install in half the upstairs bathroom. I take my small victories one at a time! |
|||
![]() |
|||
SUNDAY, OCTOBER 8, 2006 |
|||
![]() |
|||
![]() |
|||
After a break to help Nathan move and set up some wooden staging around his boat--staging that had been up at the house all summer and now needed to be moved down to the shop--I started to work on the floor tile in the downstairs bathroom. First, I laid out a dry run to determine how the tile sheets would fit between the walls and so forth. We chose a mosaic tile in a pinwheel pattern, which came pre-attached in 12" x 12" sheets, so it seemed that cuts might be at a minimum. The tile we chose happened to be called Chloe, which seemed appropriate since we have a dog named Chloe; in addition, the pinwheel pattern was reminiscent of some vintage tile that had been in Heidi's house growing up...though that tile was pink!
|
|||
![]() The pinwheel design incorporated a colored dot in the center. Unfortunately, these dots were sold separately, and did not come pre-attached to the sheets. I was well aware of this at the time of order, but somehow the enormity of the task of installing these small 1" squares remained lost on me until I began to actually install them. The sheets of pinwheel tile had gone down very quickly, but I soon discovered that with 16 of the colored dots in each square foot, progress would be slow. |
|||
![]()
|
|||
![]() By the time I finished cleaning up my tools and the mess, it was about 5:30. The floor looked great, though, and was well worth the effort to install. |
|||
SATURDAY, OCTOBER 7, 2006 |
|||
![]() |
|||
![]() |
|||
![]() |
|||
I started with the extension jambs, which were required for these windows. For weeks, I had been looking at the dizzying array of extra pieces and jambs down in the basement, unsure of what the purpose of each was. By now, though, having completed most of the windows, it was easy enough to find the necessary pieces by default. Since each large trapezoid unit is actually two smaller units mulled together in the center, each window required two full sets of extension jambs--four pieces per glazing, or eight total for each of the two windows. Unlike the regular, rectangular windows, the extension jambs were not cut to size for these windows; each piece was overlong, so in order to fit them I had to cut each to size. I finally sorted out which pieces were for which side of which window, and set aside the 8 pieces for the second window to avoid confusion. (You, dear reader, are probably thoroughly confused yourself by now.) But other than the many trips up and down the staging required, the extension jambs went fairly well, if over an overly long time period. The extension jambs feature a tongue on the inside edge that fits into a groove milled in the window, which ensures proper alignment. On these windows, the tongues fit securely in the grooves (which wasn't my experience elsewhere), and I secured them with 2-1/2" nails from my finish gun. Next, I installed some ogee trim pieces around the inside perimeter of the windows. These pieces covered the seam between extension jamb and the window jamb itself, and dressed up the opening. These came pre-cut and -mitered, so installation was straightforward once I determined which piece went where. I tacked these in place with my brad nailer. |
|||
![]() With the odd shape of the window, I had to think for a time about how to deal with the joints between the top casing and the side casings. My miter saw wouldn't adjust to a steep enough angle to properly bisect the acute angle at the topmost corner of the window, which would have been the ideal method. While I could have bisected the angle at the bottom corner, it didn't make sense to do the two ends differently, so I chose instead to let the side casing run past the top casing; with the windows so high on the wall, the end grain at the top of the side casing would never be seen. |
|||
![]() Overall, nice mitered joints would have been easier and better, but I wasn't about to try cutting them by hand for that top corner. I was pleased with my solution, and it looked good from ground level. |
|||
![]() Confused? Don't worry. Just look at the pictures and ignore the text. If you've managed to follow and understand my description, then congratulations: it means you've cased plenty of windows in your day. (No, that's not like "casing the joint"...if you've done that, I'd rather not associate with you, thank you.) |
|||
![]() |
|||
FRIDAY, OCTOBER 6, 2006 |
|||
I spent the entire morning installing
the cement backer board in the downstairs bathroom, on the floor and
then in the shower enclosure.
To cut it, I scored one side with a utility knife, like drywall, and then snapped it at the score, finishing up by cutting the mesh on the other side. For cutouts in the center of a sheet, such as around the plumbing in the bathroom, I scored both sides of the sheet around the opening first, then used a hammer to break out the piece. Fun stuff, and time consuming, too. And the crumbly cement made a wonderful mess, which I was constantly cleaning so that no little bits of crumble ended up beneath one of the boards on the floor. I secured the sheets to the floor and walls with special screws designed for this purpose. They worked OK on the floor, where I could put my weight behind the screwgun, but on the walls the screws were a real pain to get started; as crumbly as the cement board seemed, it sure was hard wherever I needed to drive a screw! Later, I used some roofing nails to secure a drywall corner bead at the outer edge of the shower, and they went right in; I should have used these to secure the sheets instead. |
|||
![]() With the chimney officially done, I started the boiler again--it hadn't been run since its initial installation test. I also fired up the Boiler Mate hot water maker, which had never been run before, and was soon rewarded with hot water out of my tap. Once I confirmed its operation, though, I turned it back off, since I have no fixtures with which to use the hot water, and saw no need to continually heat the water just yet. I set all the thermostats to 50° for now, since there are still a couple rather large holes in the house--the fireplace opening and the window upstairs in the bathroom. |
|||
![]() |
|||
![]() Well, almost. With a stack of unused staging now available following the completion of the chimney, I planned to set up enough to install the final plates on the truss, and then to trim out the trapezoid windows. Then, I could remove the staging from the house-and just in time for true finish materials like kitchen cabinets and, soon, wood flooring. |
|||
THURSDAY, OCTOBER 5, 2006 |
|||
Errands--sometimes there's simply no
way around them.
|
|||
I finally got to work for real around 9:30, starting once again in the upstairs closet, where I applied the third coat of mud to the top portions of the walls. |
|||
![]() |
|||
Next, I worked for a while on the trim at the edges of the dormer knee walls, similar to the trim on the bottom edge of the loft wall that I installed earlier. In this case, though, the top cut was going to require some careful fitting in order to mate with the myriad angles where the valley rafter, dormer rafter, kneewall framing, and sheetrock came together. I got a test piece close to a proper fit by lunchtime, but I was sick of that project and decided to focus elsewhere. |
|||
![]() |
|||
![]() |
|||
![]() Bob Emery finished up the boiler chimney today, so I should be able to use the heat tomorrow and going forward as necessary. And with the tile now in stock, the prospects for a working bathroom are looming ever closer. |
|||
WEDNESDAY, OCTOBER 4, 2006 |
|||
First thing, I applied the second coat
of mud to the areas of the bedroom closet that I started yesterday.
With plenty of milled material now ready, I turned my attention to the windows in Heidi's craft room. I trimmed out all four windows in the same manner as the other windows in the house. There was nothing particularly noteworthy about the process, but it was nice to knock off the final window trim on the first floor. Well, almost...the big trapezoid windows still require trim. I expect to do that early next week, or before. |
|||
This all took me right up to noontime, and after lunch I began work on the two windows in the master bedroom upstairs. I started with the double window on the gable wall. The choice of V-match as the interior finish surface meant that the supplied window extension jambs were 1/2" too short, as they are designed to be flush with typical 1/2" drywall; V-match is 3/4" thick. So after I installed the extension jambs, I had to take some scrap material down to the shop to mill some 1/4" strips, which I then nailed over the extension jambs to make up the difference in thickness. |
|||
![]() The remainder of the window went smoothly, though it took several trips up and down the stairs to get the top piece fitted correctly (down the stairs to the chop saw each time I have to trim a bit more off the piece). |
|||
![]() |
|||
This all took time, and finishing up most of this window took the rest of the afternoon. For this window, I used some trim stock that had only the bead detail on the outer edge, with no chamfer on the inside. I did this because there would have to be a horizontal trim piece covering the joint between the double window unit and the triangle, and with this piece mating into the side casing right at the transition angle, I thought it would be best to mill the chamfers once all the trim was in place, so that the chamfer could continue right around these corners formed by the top trim piece. I did mill 12" or so of the chamfer at the bottoms of the casing, though, since the projecting stool would interfere with the router base plate and would prevent the router from reaching all the way down once the trim was installed. |
|||
![]() The only window trim remaining to be done is on the master bedroom closet window (to be completed once the sheetrock is mudded and painted in a few days from now) and the bow window in the upstairs bathroom, which still isn't even installed. |
|||
TUESDAY, OCTOBER 3, 2006 |
|||
I started the day up in the bedroom, where I cut away the tape at the edges of the sheetrock around the rafters, wall edges, and ceilings, as has now become routine. I worked my way around the room and was generally pleased with how everything came out. | |||
![]() With the sanding done, I applied two coats of polyurethane to the entire wall, completing yet another task on my list. I dismantled the staging and set it up in the walk-in closet so that I could finish up the drywall and taping in there. |
|||
![]() |
|||
I received word that the kitchen and bath cabinets would be done next week, and would be delivered on the 12th. Of course, we have long-standing plans to go away on the 13th for a long weekend in New Hampshire, so that meant that I wouldn't be able to start cabinet installation till Monday. Isn't that always the way? In any event, I was happy to hear that the cabinets were on schedule, and despite the minor inconvenience of a relaxing weekend away, looked forward to their arrival. I made further arrangements for the granite people to come in on the 19th to template the finished cabinets for the countertop. Yee-ha!
|
|||
I also fitted a few additional pieces of sheetrock in the basement stairwell, closing up the remaining side. I had waited on this to ensure that I had enough sheetrock in stock to complete the rooms upstairs, but it was now clear that I had abundant supply. |
|||
I knocked off around 5 so that I could clean up outside a bit. There was a gross pile of sheetrock that had been lying there for a couple or three weeks, and I was sick of it; in addition, I had determined that I had no need for the scraps that I had saved indoors, and had piled on the floor in the craft room, so I threw those out as well. I collected all this junk in my big ugly yellow truck for eventual transport to the dump. |
|||
MONDAY, OCTOBER 2, 2006 |
|||
![]() In any event, I'd like to figure this out before I install the interior trim on this door. |
|||
![]() |
|||
Afterwards, I really wanted to keep going with trim, but I decided instead to apply primer to the sheetrock in the master bedroom. After all, getting the walls done had to be the priority, since not only did I need the pipe staging elsewhere, but having the walls painted would mean that the room would be more or less complete and ready for additional steps. |
|||
There was a lot to prime, and it took a couple hours to complete. While I waited for the primer to dry, I decided to take an early lunch rather than try to get involved in some other project. See, I had decided to just get all the painting done today, while earlier I had thought that perhaps I'd just do the primer. |
|||
We chose a two-color approach for the bedroom. There was a lot of wall space, with the 13' tall walls on the interior walls of the bedroom, and we thought it might be nice to break up the color a bit. Inside the front dormer, we decided on Dover White; for the remaining walls, we selected Temperate Taupe. |
|||
![]() |
|||
To kill some more time, I moved some lumber around, removing some of the pine trim stock from the first floor and bringing them to the basement for storage and to get them out of the way. By now, the paint was dry, and I applied the second coat of Dover white to the dormer. Then, I continued right away with the taupe paint in the rest of the room, and spent the rest of the afternoon applying the two coats required. I'm just about painted out, so it's a good thing that all that remains is the master bedroom closet (still awaiting some small sheetrock pieces, mud, and tape) and the master bathroom, which is currently being neglected on the back burner. |
|||
SUNDAY, OCTOBER 1, 2006 |
|||
![]() I continued with some more trim work. Earlier, I had milled some pieces of trim to use as a transition between the sheetrock and vertical V-match in the hallway and craft room, and now I spent some time cutting those pieces to fit and installing them. This went quite smoothly, except for the last corner--between the stairwall and the hallway--where the mud and corner bead had created a corner that was far from 90°. This made the fitting a bit more challenging, but it worked. |
|||
Next, I worked on the third, and final, French door. This particular door, the one in the back of the house leading to the eventual screen porch, had some installation intricacies that caused the reveal around the door to be inconsistent on one side. Fortunately, the fix turned out to be easier than I had thought. The gap widened on only one side of the door, and only to a point about 24" off the floor, so I cut a thicker piece of extension jamb (3/4") for this section, and then framed the remainder of the door with the same 1/2" extension jamb that I used on the other doors. The slight inconsistency will never be noticed...except by all of you, since I was nice enough to highlight it here. |
|||
![]() |
|||
I kept moving with the trim, and installed the window trim in the pantry, using the same style and techniques as those employed in the great room and kitchen.
|
|||
The sanding went well, and fairly quickly. I finished in about 1-1/2 hours, which wasn't too bad. I spent a half hour or 45 minutes cleaning up the house and organizing tools, and then called it a day around 4. |
|||
|