|
|||
|
~ The bLog Home ~ |
||
TUESDAY, OCTOBER 31, 2006 |
|||
Boo! I began with my habitual trip to Lowe's to pick up lots of little items needed for the work ahead, and also to pick up a dishwasher. I had tried an experiment; I ordered the dishwasher online for store pickup. I knew from the getgo that the process hadn't worked right, as I never received the proper email confirmation. But it seemed the order had gone through; my credit card had certainly been charged, and I had a printed confirmation. Still, I arrived at the store fully expecting that my dishwasher would not be ready. And I was not disappointed (as it were). First they couldn't find the order in the store computer; the store manager scrambled to find the order between the computer and the main office somewhere. While they searched for this, I did the rest of my shopping, and returned to the desk for an update. They had found the order, but now they couldn't find the dishwasher, though the inventory said they had three in stock. A loading ticket had been pulled, meaning supposedly that the dishwasher had been set aside, but the DW was nowhere to be found. I waited with amazing patience, perhaps because such efforts were being made on my behalf; there were probably 6 different people looking for the answer to the problem. Eventually, they never found the dishwasher, but they offered me the next higher model for the same cost. I checked it out and thought it looked good, and decided to take this model. I arrived home later than expected, about 8:15, and it was 8:30 before I got up to work. Since the house was all prepared for the floor finish after yesterday, I could get right to work applying the first coat, starting in the loft. |
|||
I used an oil-based floor polyurethane--gloss for the first two coats--, which was purportedly a quick-dry formula that would be ready for recoat in 3-4 hours. I applied it with a brush around the edges, and with a 10" lambswool applicator over the larger areas. This worked pretty well, though the applicator might have applied the finish a little too heavily. After the loft, I moved on to the craft room and pantry, working out towards a board seam in the doorways of each room, and then attacked the large living room, dining room, and kitchen. I finished these areas back to the basement door area, then finished the hallway so that I could exit through the basement door. The first coat took me about 2 hours to apply, and used about 3 gallons of product. |
|||
It took longer for the first coat to dry than I had hoped; by early afternoon, it was still tacky. I was worried because the later it became, the tougher it would be for me to do the second coat today, as it was getting dark so early and I didn't have any of the permanent lights installed in the house yet. I had placed 2PM as my deadline to begin the second coat, but this time came and went with the finish still curing. I had turned the heat up to 80 to accelerate the process. Finally, around 3:30 I decided I could begin. I set up what lights I could, but it was difficult since the lights need to stand on the floor. It had become cloudy, and the light was dim to begin with, but I was determined to get the second coat on today so that it could cure nicely overnight. I couldn't face another whole day of not being able to get into the house to continue the work that needed to be done. Fortunately, the light was good enough that I managed to finish, though not without some difficulty. I didn't worry that much since this was only the second of three coats, and while I wanted complete coverage, the coat didn't need to be perfect. I'd attack the final coat only first thing in the morning when the time came, to ensure that I had good lighting. |
|||
The fumes from the product didn't bother me much on the first coat, but this time around they became overwhelming--probably because of a continuing outgassing of the first coat coupled with the open second coat. Eventually, with my eyes watering and barely able to breathe, I had to put on my respirator to finish the job. The color was just what I had hoped, and the finish really enhanced the grain and color variation in the wood--perfect. It would probably be Thursday before I would apply the final coat, which will be satin rather than gloss. With my range arriving Thursday morning, I didn't think it would be smart to try to rush the final coat before then, as the final coat would need more substantial cure time to prevent damage. |
|||
Bob was here all day, and installed the cedar decking on the screen porch frame--a necessary first step, since the roof posts sit on top of the decking. I helped out for a couple hours in the afternoon while I waited for the floor finish to cure. It was too dark to take pictures of the deck by the time I got around to it, but I'll add these later. |
|||
MONDAY, OCTOBER 30, 2006 |
|||
My day started very early today.
I was up at the house a little after 5:30, since the carpet guys
were supposed to be there at 6. They actually arrived at 6:30
because of some undetermined snafu with their not being properly
notified by the flooring store, or something. If that were the
case, I'd say that being only 30 minutes late is pretty good. The father and son installation team didn't waste any time. They were all done and gone by 7:45. With that, the bedroom and closet were done. |
|||
While the carpet guys worked, I finished up the electrical trimout in Heidi's craft room, installing the remaining outlets. Then, I cleared off the remaining stuff from the kitchen countertop in preparation for the granite guys. I also cleaned out the excess stuff from the craft room--some insulation for the basement, excess tools, and the closet bifold doors--and considered getting started on the interior doors downstairs. Since I expected the granite at any time, though, I was reluctant to get going, as I'd be in the way. So I sort of stood around, not sure what to do next. Fortunately, the granite got here pretty soon. |
|||
Over a couple hours, the team of 4 people installed the granite countertops in the kitchen. It looked great. I love the color. It looked like it was pretty heavy when they carried in the two larger pieces. |
|||
In between watching the granite folks, I fooled with some of the track lighting that Heidi had picked up on Friday. I installed some of the end feed connectors on some of the tracks, since it had to be done sometime and I wasn't doing anything else. Once the granite was done, I got right to work on the remaining interior doors, which I wanted hung and out of the way before I started finishing the floor. I had to cut a bit off each door jamb before they doors would fit into the rough openings; one one side of the hall (the center wall, which Bob framed way back in May), the ROs were very tight all around, and the doors barely fit. In fact, the door to the basement ended up a bit tight since I couldn't push the jamb any further away from the door itself. I figured I could trim the door if necessary. The doors on this side also ended up with little clearance to the floor; later, I'll trim 1/2" or so off the bottoms of the doors. I finished up the last door in time for a late lunch. After lunch, I began the task of preparing the wood flooring for finishing, which I planned to start tomorrow. I picked up the protective rosin paper, removed trash cans and other obstructions, and then installed plugs on all the screw holes I had drilled in some of the boards. This took longer than I had expected because the only plug cutter I could find was apparently an older one, and was extremely dull. It burned, more than cut, its way into the scrap flooring as I cut the 50 plugs I needed (I thought). This was very slow as well as annoying. Then, while installing the plugs, I ran short and had to go back down and cut 10 more. |
|||
When the glue on the plugs had dried, I cut off the excess with a chisel and dressed them with some sandpaper. Then, I swept all the floors, opened the doors to let the wind blow some of the dust out, and then vacuumed all the floors. Finally, I washed the wood with paint thinner, using about a gallon to wash the entire floor. This was tough on the knees by the end, but the paint thinner gave a sneak preview of what the floor would look like with finish. I finished up this final task at about 4:30, and called it a day. Tomorrow: 2 coats of gloss oil-based polyurethane; according to the package, it dries for recoat in 3 hours. Then, I'll do one coat of satin over the top the next day. Outside, Bob finished up the roof on the front porch. He arrived around 11 after doing something else earlier in the day, and left once the roof and trim were complete. Good enough. |
|||
SUNDAY, OCTOBER 29, 2006 |
|||
Today's first order of business was to install the baseboard in the bedroom and closet upstairs--the final critical task to complete before tomorrow's carpet installation. I really don't like installing baseboard. It just seems to be an unsatisfying piece of trim somehow, and is more difficult to install than it ought to be. The problem comes from the fact that wall corners are rarely square and true, particularly with drywall, and this complicates the miter joints between pieces of baseboard.
Since I had moved my saw and raw materials to the basement, it took many trips up and down the two sets of stairs to get all the pieces cut and installed in both rooms, but I got it done--thankfully. |
|||
![]() |
|||
![]() Now, the only trim remaining unfinished is that in Heidi's craft room (as well as on the interior doors downstairs, which haven't been hung yet...). |
|||
![]() |
|||
I was kind of hoping to start installing the doors downstairs, but I discovered that the rough openings were a bit shorter than they should have been, and I'd need to cut 1.2" - 3/4" off door jambs before I could install them in the openings. I just didn't have it in me to do this right now, so instead I changed out the almond outlet in the bathroom for ivory, and installed a toilet paper holder. Then, I cleaned up a bit more, and called it a day a bit early so that I could do some cleanup outside and remove the pile of cement board scraps and the waste from the porch construction. I had to hurry because, with daylight savings time over, it was getting dark quickly--and early! |
|||
SATURDAY, OCTOBER 28, 2006 |
|||
It was a thoroughly miserable fall
day, with a strong southeast storm outside complete with driving
rain and very high wind gusts. The house was warm and cozy,
though, and well isolated from the fury outside. Heidi had picked up all our interior lighting fixtures last night--some wall sconces and a large amount of track lighting that we needed for the general lighting in many areas. It filled her car, and I unloaded all this stuff into the basement this morning. Inspection and installation would have to wait a bit, though, since I had more pressing projects to complete this weekend in order to be ready for carpeting and granite on Monday morning. I began, once again--but for the last time--in the upstairs bathroom, where I applied the third and final coat of mud to the remaining sheetrock. Now all I have to do is sand it tomorrow, and that messy, never-ending job will actually end. What a long road that has been; I began hanging sheetrock in early September. |
|||
Next, I installed the remaining two doors in the upstairs--into the closet and bathroom. I should have added yesterday that these doors have no casing applied, which is what made their installation so much more of a challenge alone. Normally, one can nail through the casing on the inside of the door to secure it before opening the door to nail it the rest of the way.
With the doors in place, I prepared the site-made casing for installation. I had previously milled my chamfer and bead details on a number of pieces of my pine trim stock, and from this material I cut pieces to fit the sides of the doors and sanded them, then applied two coats of poly before installation. This work took up until lunch time, and after lunch I installed the casing on both sides of all three doors, except for the bathroom, where I left the inside casing off since there was so much work ahead in the bathroom, and to install the casing would be premature. |
|||
![]() |
|||
FRIDAY, OCTOBER 27, 2006 |
|||
I began with the second coat of mud in
the upstairs bathroom. This took about an hour. Next, I continued by installing the interior door into the bedroom from the loft. I needed to install all the upstairs interior doors before Monday, when carpeting was scheduled to arrive, but I chose this one first because I also needed the door jamb in place before I began the flooring in the loft. Because of the transition to carpet, I wanted to install a threshold in the doorway, and I wanted the threshold to pass beneath the jambs. I'd have to cut the jambs either way, but I thought it would be easier to use the pull saw to cut them after installation, keeping them even with the top of the flooring, than to cut them beforehand. Installing an interior door by oneself can be a bit challenging, since one really needs access to both sides of the door to properly install--first the inside, to plumb the door using the hinges, and then the outside to secure it. With no way around it, I had to open the door to get through, which meant I needed to temporarily secure the jamb from inside so that the door would stay in place and in the proper position. Anyway, I got the door installed, and then cut the jambs at the bottom to make room for the threshold, which I made by cutting the tongue off a piece of 5" wide flooring. |
|||
I moved on to the hardwood flooring in the loft. Because the edge of the loft flooring would be exposed, I chose to install a band or nosing around the exterior perimeter, which I made from more of the 5" wide flooring from which I removed the tongue; then, I milled a bullnose edge with a router. I laid out the banding first, beginning with the nosing at the top of the staircase. I let the nosing hang over the edge by a bit to provide a reveal when all the trim was complete later on. I figured and cut the miter joint at the angle adjacent to the staircase on both the stair nosing and the next piece of banding, but I didn't install either piece just yet, since I planned to let the floorboards run wild over the angled edge and cut them off later at the proper angle--rather than try to cut such an oblique angle on each individual piece. This layout took a lot of time. |
|||
![]() |
|||
![]() |
|||
![]() The roof looks great, though, and it was nice to see it begin to truly blend in with the house. He's done a great job on the details, and mostly alone--though I've offered to help a number of times. He feels it's better that I keep working to finish my work inside, which is fine with me, but somehow I feel guilty that I'm not out there helping to the extent possible. So I'm not complaining--just pointing out a difference in our approaches! |
|||
THURSDAY, OCTOBER 26, 2006 |
|||
![]() We chose a lively color called Tantalizing Teal--pretty bold stuff. No boring colors in this house. Over the course of the morning, I got the two coats applied, cut off the edge taping when the paint was dry enough, and removed the staging. |
|||
![]() |
|||
![]() |
|||
I applied the fiberglass mesh tape and first coat of mud to the remaining drywall areas in the bathroom, which went well and without incident. Then, to use up the last hour or so of the day, I continued some electrical trimout work in the bedroom. I had to return to Sherwin Williams late in the day to pick up some additional polyurethane that hadn't been in stock this morning, but which had been brought up from another store. |
|||
![]() |
|||
WEDNESDAY, OCTOBER 25, 2006 |
|||
![]() |
|||
![]() I finished up
the floor in mid-morning and then shifted gears for a change of
pace. I couldn't begin the loft flooring just yet because I
needed some 1-1/2" L-nails instead of the 2" I had used downstairs.
I thought the shorter nails might be necessary to avoid the
possibility of any of the nails showing through the exposed ceiling
boards. |
|||
Instead, I moved on to the dreaded chore of finishing the cement board in the upstairs bathroom. Now was as good a time as any, since I needed to have this done before Monday. I worked on this for the remainder of the day and got most of the large pieces installed. All that remained was a number of small strips and pieces, which in many ways are more difficult because it's so hard to get a decent cut with this material. I hoped to finish up tomorrow. Sorry--no pictures of this, since you've seen it all already and it's almost impossible to take pictures inside the odd-shaped bathroom. | |||
Meanwhile, outside, Bob and Rod were here to work on the porch roof. They managed to install all the roof rafters, one gable end, and all the sheathing save for a bit at the south end, which they didn't get to because it required the more time-consuming work of building the gable end wall, gable rafter, and some shingling on the main roof. But the bulk of the roof was done, and it drastically changed--and improved--the appearance of the house, as expected. Bob said he'd finish the remaining end tomorrow, and get ready to shingle the roof. |
|||
TUESDAY, OCTOBER 24, 2006 |
|||
I worked on the flooring all day again today. I began with the dining area, and spent most of the morning completing this area--a surprisingly long time, I thought, to complete a smallish area. The subfloor had a good bow in it in this area, which complicated the installation since it was harder to engage the full lengths of the tongues on the floorboards. |
|||
I finished up late in the morning, and shifted my operations towards the craft room. Before I broke for lunch, I installed floor boards through the door openings from the hallway into the craft room and pantry, and then moved all the excess stored stuff out of the craft room--boxes of tile, a kitchen cabinet that I hadn't installed yet, the refrigerator end panel, and some other things. I also moved part of the pile of remaining flooring out to the living room near the saw, so that I'd have room to work in the craft room. My final step before leaving for a short break was to install the felt paper on the floor for the first rows of flooring. After lunch, I worked on the flooring in the craft room. With the short pieces through the door opening, I had reversed the direction of the floor tongue so that I could work from the inside wall towards the outside, and I continued in this manner. Flooring this room took the rest of the day. It went pretty well. I had a few cuts to make around the center post of the double closet openings, but these went smoothly. I got nearly to the far wall, but I wasn't as lucky today and found that I needed to rip a 2" strip to fill in the last opening against the wall and beneath the heat register. I bundled up a few pieces of the flooring to bring down to the shop overnight so that I could rip them on the table saw, and finish up their installation in the morning. I could hardly wait to get the pantry floor covered in the morning. It would be the last vestige of that nasty subfloor to disappear. Ugh. |
|||
MONDAY, OCTOBER 23, 2006 |
|||
Well, today we did it: we
scheduled the movers. The date is Friday, November 10.
Now I really have something to work towards. It's at
once exciting and scary! I hope I can get enough done in time.
Even though we'll be able to move in, I know that the house won't be
complete; there will be several jobs remaining to be done,
including, but not limited to:
I continued work on the hardwood flooring today. I began where I left off: at the corner of the living room extending into the hallway. Fortunately, the spacing of the flooring had ended up being perfect in that I could run a full width of flooring for the first run down the hallway, leaving the ideal 1/2" space next to the wall. It was just a fluke that it turned out this way, and saved me the chore of ripping a piece to fit. It took a while to lay out the felt paper in the hallway and get the first couple rows installed. I installed these rows much as I did the first row yesterday, though I didn't see a need for screws here. As before, I used another row of flooring outside of the first to help align things properly. It was dreary and dismal outside when I took these photos; it looks like night, but it was actually about 8AM when I took these two photos. |
|||
Once the first two rows were in, I continued laying the flooring up and down the full length of the hallway and living room, spanning the entire 44' length of the house. This took a while, compounded by the need to cut and fit the flooring around a heat register on the other side of the hallway. However, I was fortunate once again in that I did not need to rip flooring to fit--a full width for the final row was just right. Considering the random placement of the various width boards in this floor, I think it was pretty amazing how nicely the hallway worked out. The remaining photos in today's log were all taken late in the day at the end of work hours. I didn't use a flash because there was a lot of dust in the air from my sweepdown. I'll try and get some better ones in the daylight later. |
|||
Eventually, I finished up the hallway--and corresponding width of the living room--and then made it to the log post outside the corner of the kitchen. Faithful and detail-oriented readers may remember way back in June when I cut the bottom of the log post to incorporate a built-in rabbet so that I could slide the flooring cleanly beneath. Now it was time to put this to the test. I cut and fit pieces around the post as needed, using relatively short pieces to make the task easier. I think it turned out well. | |||
Once I made it to the edge of the kitchen cabinets and slightly into the dining area, I shifted focus and worked in the kitchen--for the rest of the day, as it turned out. I floored the entire kitchen, which took a surprisingly long time because of so many cuts required. |
|||
I had hoped to get the dining area also floored today, but I had to be satisfied with what I accomplished. I spent the last hour or so of the day moving my saw table out of the dining area and cleaning off and removing a portable table covered with tools and supplies, moving these to the basement for storage. I needed to clear the area so that I could continue the flooring in the morning, and all this excess stuff just seemed out of place suddenly in a house that, with the addition of the flooring, seemed to be nearing completion. Plus, I don't want to install the hardwood too fast, since I need to ease myself away from the beautiful Advantech subfloor that I've been staring at, lying on, kneeling on, dewatering, sweeping, and generally loving for the past 6 months. I'm really going to miss it...NOT! |
|||
SUNDAY, OCTOBER 22, 2006 |
|||
Today, I began the installation of the
hardwood flooring throughout the downstairs. We chose
traditional 25/32" thick "rustic red birch" flooring in 3", 4", and
5" face widths, purchased from and milled by a local company.
|
|||
![]() |
|||
![]() Once I had the line snapped, I laid a strip of roofing felt on the floor, aligning one edge with the chalk line. I could have used red rosin paper beneath the floor also, but I had lots of the felt paper on hand from the roofing job, and it's also a good material to use beneath wood flooring. The paper simply serves to provide a modicum of moisture barrier, and also to isolate the strip planks from the subfloor, reducing the chance of squeaking later. |
|||
![]() |
|||
![]() |
|||
![]() I didn't find any unusable pieces at all, and the milling quality was excellent; the flooring fit tightly and evenly together. I was thrilled with the choice. |
|||
![]() This picture makes things look darker than they are, since it was (duh) dark outside, but I actually think that the floor will end up being close to this color when the finish is applied. By reaching this corner, I had completed the largest single section of flooring in the house. The remainder ought to cover a bit faster, particularly once I complete the 4' wide and 17' long hallway. |
|||
SATURDAY, OCTOBER 21, 2006 |
|||
I began the day early with a trip to
the Augusta Home Despot to pick up the remaining cement board that I
needed to complete the upstairs bathroom (19 sheets). I also
picked up a few other smaller items that I needed. Going to
Augusta means that I can leave the house much later than I would
have to if I went to Brunswick and Lowe's, and still get to the
store early, before the unwashed masses start showing up for their
weekend projects. I wash every day, so obviously I don't fit
in with that crowd. I was back home by 7:30, and carried all the sheets up to the bedroom for storage and eventual use. I love cement board and I wish I needed more. I need to have all these sheets all cut and installed by a week from Monday, when our bedroom carpeting arrives; it'll take about a full day to finish this up, so I'll address that a bit later. I didn't feel like attacking the board right then, so I worked on a few smaller projects downstairs. I attached the shower head in the bathroom, and then wired up the bathroom outlets. To my disgust, I discovered that a "Decora" outlet (the square, boxy type), which I had purchased this very morning and that I needed to match the GFCI outlet in a double gang box, was (wait for it) almond instead of ivory! How annoying. You'd think I'd learn. Again, though: they all look the same in the store. A new outlet went on the ever-present shopping list for next time.
I forgot my camera this morning, and since I didn't even go down for lunch I never picked it up. It doesn't matter much, since most of today's progress was not of the visually exciting type. (I did add a picture that I took of the fireplace opening the next day.) I spent most of the rest of the day working on electrical trimout, installing switches and outlets through the rest of the downstairs (except Heidi's craft room, which was too full of wood flooring at the moment), and part of the upstairs. I gave in and started using the backwire terminals on the outlets that I had in stock, having decided that with the screw-down clamps, they were acceptable for use versus side wiring--and it was too much of a pain to sidewire these, since the side screws flop around in this design. Tugging on the wires, I didn't see any contact problem, so backwire it was. I'd still choose sidewire outlets in the future, but with the materials on hand I saw no reason not to press on rather than wait to exchange the outlets I had in stock. Late in the day, I cleaned up downstairs, and vacuumed the floor; then, I brought some of the hardwood flooring out of its storage room and laid it in piles in the living room in preparation for tomorrow, when I planned to begin laying the flooring. The look of the house will really begin to change tomorrow! I'll bring my camera--I promise. |
|||
FRIDAY, OCTOBER 20, 2006 |
|||
It wasn't really an exciting day here
today, but I got a few smaller jobs done and knocked off the list.
It rained on and off all day, so there was no opportunity for
outdoor work on the porch.
After I cleaned up, I primed the walls, another job for which I had little enthusiasm. Then, I painted the walls in the closet with the final coats of paint--the same taupe color as in the bedroom. I was thrilled to be done with this. Each step in this process today just seemed like pulling teeth for some reason. |
|||
![]() Later, I'll skim coat the exposed cement board at the top of the shower, and paint it to match the room. |
|||
![]() I spent some time late in the afternoon cleaning out much of the excess tools, boxes of nails, and so forth from the main floor of the house. I stored these in the basement for now. I also moved my saw table to the other side of the room, all this in preparation for my anticipated commencement of the wood flooring within the next couple days. Some milestones to come in the next couple weeks: -October 23: LPG tankage and
piping for the range to be installed |
|||
THURSDAY, OCTOBER 19, 2006 |
|||
![]() When Bob arrived, we worked outside to raise the porch posts (6x6 pine) and header beams (6x8 pine) for the front porch. We secured these from beneath the deck with a couple nails and then some 10" log screws. Once these pieces were up, Bob didn't need me anymore, so I continued my work inside. |
|||
![]() Even with just the most basic parts of the porch in place, the appearance of the house changed drastically. I've been looking forward to this forever; the house has been missing this important visual feature, but even with just the posts in place, it began to soften and lower the front facade of the house. Excellent! |
|||
![]() |
|||
![]() Electrical trimout takes time, with little in the way of visual result. Here are some fancy switch plates we bought for the main switch center under the stairs; we used these plates in this area only since it seemed so front and center to the living room, and I hated to use the cheesy plastic plates here. |
|||
![]() There's more rain forecast for tomorrow, so it's unlikely that anymore work will occur on the front porch this week. I'm very anxious to see the roof! |
|||
WEDNESDAY, OCTOBER 18, 2006 |
|||
![]() 3-way switches are always confusing, and it had been a while since I wired one up. Late yesterday, I wired them the way I thought I remembered, but they were wrong; the circuit breaker tripped immediately when I turned it on. Obviously, I had something wrong. I did a little research overnight and found out what I had done wrong, so I rewired the switches successfully this morning. These are the first "real" lights to become operable in the house, making this a milestone, if an insignificant one. |
|||
I spent most of the rest of the day working on the tile in the downstairs bathroom shower. I was surprised how long it took, but to be fair I did take an hour and a half off for a visit and lunch with my mom. I began with some layout. We chose 4-1/2" square tiles for the shower, mostly white with a bold color pattern partway up. But everything hinged on the first row of tiles, so I laid two in place on each wall of the shower at the top of the shower pan, and checked for level. Choosing the high point, I struck a level line all the way around that represented the top edge of the first row. I mocked up the colored tile band on the floor to check its appearance and determine its overall width, and then figured approximately where it should be located on the walls of the shower. We wanted it a little above halfway up the walls, or about chest level. This turned out to be 9 tiles above the base, or about 38-1/4". The tile band would be about 18" wide. Then, I laid a full row in each wall, so that I could check how much tile would remain at the corners. Fortunately, relatively large pieces (between 1/3 and 1/2 tile) would finish out each row, so there was no need to adjust the spacing. One hopes to avoid tiny slivers of tile, and by laying things out in advance adjustments can be made beforehand that avoid the tiny pieces. I installed the first row all the way around, cutting tiles as necessary to finish at the corners. I started with the back wall, and then installed the two sidewalls; in this way, the cut tiles from the side wall covered the cut tiles in the back wall, making the seam less visible. I used a simple tile scorer to cut the tiles. I worked my way up 9 rows, which brought me to the base of the colored accent band. This took till about 1130. |
|||
![]() The accent band turned out to be rather involved and challenging, but it looked great when complete. At the front edges of the side walls, I began the accent one tile back from the front, since I needed to use bullnose tile at the outer finished edge. |
|||
![]() I should have mudded and taped the top section of the wall before tiling, but of course I didn't; later, I'll have to smooth and paint the small area between the top tiles and the ceiling to finish the job. There was no outdoor work today because of the morning's rain. |
|||
TUESDAY, OCTOBER 17, 2006 |
|||
![]() Anyway, with the correct purchases in hand, I was back home before 8, and got right to work in the bathroom on toilet preparations. I soldered a chrome-plated valve on the copper pipe supply stub extending from the wall, and installed a trim plate to cover the raw hole in the sheetrock. Then, I installed a braided stainless steel supply line. |
|||
![]() In the meantime, I cut and installed as much of the baseboard as I could in the bathroom, leaving only a couple pieces near the doorway, which I couldn't install until the interior door and trim was installed. |
|||
Next, I applied the final coat of mud to the closet upstairs, thankfully drawing yet ever closer to the end of the drywall project. Once this room, and the upper portion of the bathroom, are sanded, all that will remain will be the lower portions of the sheetrock in the bathroom upstairs. |
|||
I began to install some of the trim rings and bulbs on the overhead recessed light fixtures, but I quickly discovered that the bulbs I had purchased were the wrong ones--too long, so they extended past the trim rings. Boy, I was really batting .000 with my Monday purchases. Later, I discovered that the 4th and final trim ring that I had purchased was missing one of the springs required to hold it in place, lowering my purchase average to negative levels. I dutifully added these items to my already shockingly long list and pressed onwards. | |||
![]() |
|||
![]() |
|||
![]() |
|||
![]()
(Actually, this was pure dumb luck!) |
|||
Finally, I could put it off no longer. I had to go upstairs and start installing the remaining cement board in the bathroom. I had bought a scoring tool to help cut the board, as utility knives didn't work that well and dulled very quickly. For the rest of the afternoon, I installed what was left in my pile of new boards, finishing up one wall and making good progress on another, including the area behind the heat register. I used the last full sheet on the floor, and figured out how many more sheets I would need to finish up the remaining areas. I planned to get this over with by next week, probably during the weekend. I need the cement board to be completed before October 30, when the carpeting is coming for the bedroom. | |||
Meanwhile, Bob was around today working on the front porch. He didn't need me today, so he worked alone, figuring out the roof details and then installing some decking at the outer edge of the porch so that the roof posts could be installed. Then, he cut all the 6x6 and 6x8 pine beams required for the posts and headers to length and laid them out in readiness for the next step: standing them upright. | |||
MONDAY, OCTOBER 16, 2006 |
|||
After three days away from the
jobsite, I was anxious to get back to work. I began bright and
early with my habitual pre-dawn journey to Lowe's to pick up a wide
variety of items, from a toilet to outlet face plates, from drywall
mud to finish nails, and from tape measures to shower drain fitting. I arrived back home before 8, and unloaded my haul. It was at about this point that I noticed that my toilet box read "round front"...uh-oh. From the display at the store, it seemed like the Kohler Wellington--a unit we had used previously with good success--came only with the elongated bowl, which I wanted. I opened the box and confirmed by fears: this was the wrong thing. Grr. I was not pleased with this development. Will I ever learn to double check the things I pick up? And why wasn't it more clear that there was a choice, and that the stack from which I took my unit was round and not elongated in the first place, Mr. Lowe? I managed to get past this annoyance, and since I wasn't sure if Bob would want or need my help today, I sort of dubbed around on some smaller things while I waited for him to arrive. I thought I'd install the outlet face plates in the kitchen, to cover the outlets I installed a while back. I opened the first one and installed it, and noticed immediately that the color didn't match. I had installed tan outlets, and had picked up tan faceplates. What gives? It turns out I had actually (and without knowing so) installed almond outlets, while my faceplates were ivory. Come on, will you? They're both nearly the same color, but just incrementally different enough to be blatantly noticeable if compared directly. I thought there were three choices: white, tan, and brown. But almond and ivory? Isn't this placing too fine a point on an el-cheapo receptacle? I was extremely annoyed at this, which, on top of the toilet debacle, more or less negated my entire trip of the morning. I almost headed right back immediately, but logic prevailed and instead I made plans to return tomorrow morning--aggravating, but better to just go and get the exchanges done. Besides, I had been looking forward to an operating bathroom in the house, and didn't want to delay much longer. |
|||
When Bob arrived, we eventually decided that he could do most of the work alone, and that I would work inside as necessary, though of course I'd be available at any time to help out as needed outside. So I got to work on the mud in the upstairs, and applied a third coat to the upper part of the bathroom, and a second coat to the remaining areas of the closet with the new bucket that I had picked up. |
|||
Next, I installed the vanity cabinet in the downstairs bathroom. This went smoothly, and I didn't even need to shim it for level. I did shim behind the solid pine back supports since I had to hold the cabinet slightly away from the wall to clear the electrical wiring running to the outlet box above the cabinet. For this cabinet, we chose a maple frame painted Jamestown blue, with white maple drawer fronts and doors with a Shaker bead. The drawer fronts ended up a bit more blank than I had expected, but since we had yet to choose our hardware it seemed that some good hardware could liven things up. Otherwise, I liked the cabinet. Later (soon), I'll build and install a standard Formica countertop. |
|||
I installed a drain fitting in the downstairs shower pan in preparation for the final connection in the basement. I bedded the fitting in lots of plumber's putty and tightened the nut from the basement beneath. I also installed the closet flange in the floor. |
|||
![]() |
|||
I finished up the day by installing 5 or 6 of the cheap porcelain light fixtures in the basement. I had installed 11 boxes some weeks ago, along with the wiring, and now I began to wire these up so that I'd have light in the basement; I figured my cutting station would probably move down here sooner than later, once the finish floor was installed upstairs. I hated installing these cheap fixtures. I just don't understand why the manufacturer couldn't leave more room around the screws for the wires; things were extremely tight, particularly for the 12 ga. wire I was using. Would it have killed them to leave 1/4" clearance around the screw, rather than to have it nearly butted directly against the molded contours of the back side of the fixture? Who designs these things? |
|||
While I worked inside, Bob worked on the deck framing, picking up where we left off last Wednesday. New material had been delivered Friday, sometime after we left for the weekend, and he finished installing the joists, cut the ends to length, and installed the double box frame. I helped hold some of the larger pieces of the box frame, but that was about it. He also installed some blocking in the area where the front porch met the large deck off the south end, where we planned to miter cut the deck boards.
|
|||
Click here to go back to the logs from the first half of the month, if you missed them. | |||
|