I spent the morning cutting and fitting the remaining pieces of the ceiling:  the smaller, custom-cut sections required to fill in the short areas at the ends.  Although I was out of the proper screws to fasten the slats, I chose to press on and use different screws for now, just to finish the ceiling work since I was on a roll and anxious to complete the long-awaited ceiling.  Later, I'd switch out the screws, which would be a simple and quick job by comparison.

When I had all the slats in place, I cut and installed trim as needed over some of the edges, and applied more tung oil to the completed ceiling; I'd continue adding coats of tung oil over the next several days to build up the finish.

    
         

         


With the ceiling complete, I sanded and varnished the interior companionway trim and swashboards to keep that process moving along.


    


Total Time Billed on This Job Today:  4 hours